Aggregate Industries finishes Leeds project ahead of time

Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning. Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail. The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly
January 24, 2019 Read time: 2 mins
No time to waste: Aggregate Industries worked full tilt 24/7 to finish the Leeds project
Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning.


Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail.

The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly and with minimum disruption to nearby businesses and the travelling public.

The 2297 Aggregate Industries contracting team liaised closely with local businesses for three months prior to the start of work onsite. They put together a phased 24-hour working programme that maintained access to affected businesses throughout the duration of the works.

Using this fastidious 24-hour working approach, no time was lost between shift changeovers. During phase 1 of the works, Aggregate Industries laid a 5,855tonnes of asphalt and around 7,500m2 of geotextile in just one weekend. Saturday night alone recorded 3,872tonnes of asphalt laid in 18 hours. This averaged at an 215tonnes every hour during this period.

Aggregate Industries completed their work well ahead of schedule and delivered the project in just 54 hours compared to the 58.5 hours that were originally scheduled.

“To plane out Friday night and inlay 5,855 tonnes of asphalt by Sunday evening is simply unprecedented and we are incredibly proud of what we achieved on this project,” said Paddy Murphy, managing director of contracting services at Aggregate Industries.

For more information on companies in this article

Related Content

  • Asphalt paving innovation from Aggregate Industries
    October 20, 2017
    The firm developed this new surface course in a bid to match increasing traffic volumes on the UK’s road network. According to Aggregate Industries, this material can speed up road surfacing by more than 40%. There is a major need to repave many UK roads, with the country’s vehicle population having increased by 10 million in the last 10 years. This has triggered an increased need for infrastructure maintenance. But the time needed to carry out road repairs can cause major problems for motorists.
  • Act FAST when it comes to bridge maintenance, argues Cliff Weston
    February 27, 2017
    Deck waterproofing remains critical to a bridge’s structural integrity for its design life, explains Cliff Weston, director of Stirling Lloyd To properly maintain deck waterproofing there must be a willingness to look at solutions based on whole-life costing rather than just short-term initial costs. There are lessons to be learned from examples of prematurely failed infrastructure due to a focus on initial short-term costs.
  • CRCP is first choice for Belgian highway
    November 28, 2012
    Dan Gilkes reports on a Belgian highway upgrade When the Ministry of Public Works in the Belgian State of Flanders decided to reconstruct and resurface 19km of the N49 Antwerp-Knokke Expressway, continuously reinforced concrete paving (CRCP) with an exposed aggregate surface was the natural material choice. Indeed exposed aggregate, with its high grip and low noise benefits, has been the first option for all motorway surfacing work in Belgium since the 1980s. However, the €15.65 million contract is not a li
  • New UK motorway link under construction
    June 18, 2015
    Construction of a new junction on the M1 near Dunstable in Bedfordshire is starting in the UK. The new junction, junction 11A, is located just to the south of Toddington services and forms part of a new €225 million link road between the A5 and the M1 that will help to unlock growth and reduce congestion in the area. Work on the link road began in March.