Aggregate Industries finishes Leeds project ahead of time

Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning. Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail. The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly
January 24, 2019 Read time: 2 mins
No time to waste: Aggregate Industries worked full tilt 24/7 to finish the Leeds project
Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning.


Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail.

The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly and with minimum disruption to nearby businesses and the travelling public.

The 2297 Aggregate Industries contracting team liaised closely with local businesses for three months prior to the start of work onsite. They put together a phased 24-hour working programme that maintained access to affected businesses throughout the duration of the works.

Using this fastidious 24-hour working approach, no time was lost between shift changeovers. During phase 1 of the works, Aggregate Industries laid a 5,855tonnes of asphalt and around 7,500m2 of geotextile in just one weekend. Saturday night alone recorded 3,872tonnes of asphalt laid in 18 hours. This averaged at an 215tonnes every hour during this period.

Aggregate Industries completed their work well ahead of schedule and delivered the project in just 54 hours compared to the 58.5 hours that were originally scheduled.

“To plane out Friday night and inlay 5,855 tonnes of asphalt by Sunday evening is simply unprecedented and we are incredibly proud of what we achieved on this project,” said Paddy Murphy, managing director of contracting services at Aggregate Industries.

For more information on companies in this article

Related Content

  • Asphalt plant retrofit with Benninghoven
    March 30, 2022
    An existing asphalt mixing plant in Braunfels, Germany has benefited from a retrofit solution to boost its performance. Asphalt plant manufacturer Benninghoven was able to supply a new mixing tower and drying section to upgrade the performance of the facility.
  • RubbleCrusher positions itself for US boom in crushing and demolition waste recycling
    March 14, 2023
    McLanahan believes that its newly-acquired RubbleCrusher range can make it big in North America, where it will appeal to SME (small-to-medium-sized) rock crushing, construction, and demolition waste recycling companies.
  • Improved runways for Jeddah International Airport
    August 21, 2013
    With an increasing number of aircraft using Jeddah International Airport in Saudi Arabia, the authorities realised there was a need to upgrade the facilities. King Abdulaziz International Airport opened in 1982 and serves over 15 million passengers/year, with a high percentage travelling on the annual Islamic pilgrimage to Mecca, some 80km away. The city has the largest port on the Red Sea and is named after Abd al-Aziz ibn Saud, the former king and founding father of Saudi Arabia, and is one of the kin
  • Tunnel Boom in Central and Eastern Europe
    September 15, 2015
    Following the success of the 41st World Tunnel Congress held in Croatia last May, World Highways looks at two signi_ cant projects in Slovakia and Serbia – Adriana Potts reports Central and Eastern Europe is buzzing with a number of major projects being developed - including highways, bridges and tunnels – and with many more in the pipeline. The region is expected to be highly active with plans for developing infrastructure in the next two decades, according to Davorin Koli , president of the Croatian