Aggregate Industries finishes Leeds project ahead of time

Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning. Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail. The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly
January 24, 2019 Read time: 2 mins
No time to waste: Aggregate Industries worked full tilt 24/7 to finish the Leeds project
Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning.


Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail.

The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly and with minimum disruption to nearby businesses and the travelling public.

The 2297 Aggregate Industries contracting team liaised closely with local businesses for three months prior to the start of work onsite. They put together a phased 24-hour working programme that maintained access to affected businesses throughout the duration of the works.

Using this fastidious 24-hour working approach, no time was lost between shift changeovers. During phase 1 of the works, Aggregate Industries laid a 5,855tonnes of asphalt and around 7,500m2 of geotextile in just one weekend. Saturday night alone recorded 3,872tonnes of asphalt laid in 18 hours. This averaged at an 215tonnes every hour during this period.

Aggregate Industries completed their work well ahead of schedule and delivered the project in just 54 hours compared to the 58.5 hours that were originally scheduled.

“To plane out Friday night and inlay 5,855 tonnes of asphalt by Sunday evening is simply unprecedented and we are incredibly proud of what we achieved on this project,” said Paddy Murphy, managing director of contracting services at Aggregate Industries.

For more information on companies in this article

Related Content

  • Towards sustainable mobility
    February 20, 2012
    Tony Marshall, Director at Arup, looks at ways in which the company encourages sustainable mobility. From policy and systems development through to the design and execution of major infrastructure projects, he reviews Arup's global project experiences and research programmes
  • 2020 vision for waste recycling
    February 22, 2013
    Brussels calls for 70% recycling of construction waste by 2020 but *Peter Craven asks if there is a greater target to be achieved in the UK. In the UK, over 90 million tonnes of construction, demolition and ground excavation (CD&E) waste is generated each year from construction, demolition and civil engineering projects. Across Europe this figure is well in excess of 1000 million tonnes and represents a valuable and sustainable asset to the construction sector, as well as protecting natural resources. The r
  • Testing recycled cold mix asphalt
    March 15, 2012
    Cold mix road repair material containing 100% recycled asphalt has been laid on rural routes in northWales, UK, by the contractor Hogan Construction.Work was carried out to demonstrate that structural integrity can be restored to a failing carriageway without making use of primary aggregates or hot bitumen.
  • Singapore F1 racetrack uses Shell technology
    July 20, 2012
    The Singapore Grand Prix at the end of September was a race to remember for many reasons. Formula One's first night race saw excitement on the track, and it was a test for the high-performance surface containing Shell premium grade bitumen binder Cariphalte Racetrack. The inaugural Singapore Grand Prix was staged on a new street circuit and is open to regular motorists. Work on the track started in April 2008 and was completed in just two months. Because the road circuit is used for everyday traffic, the ne