Aggregate Industries finishes Leeds project ahead of time

Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning. Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail. The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly
January 24, 2019 Read time: 2 mins
No time to waste: Aggregate Industries worked full tilt 24/7 to finish the Leeds project
Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning.


Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail.

The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly and with minimum disruption to nearby businesses and the travelling public.

The 2297 Aggregate Industries contracting team liaised closely with local businesses for three months prior to the start of work onsite. They put together a phased 24-hour working programme that maintained access to affected businesses throughout the duration of the works.

Using this fastidious 24-hour working approach, no time was lost between shift changeovers. During phase 1 of the works, Aggregate Industries laid a 5,855tonnes of asphalt and around 7,500m2 of geotextile in just one weekend. Saturday night alone recorded 3,872tonnes of asphalt laid in 18 hours. This averaged at an 215tonnes every hour during this period.

Aggregate Industries completed their work well ahead of schedule and delivered the project in just 54 hours compared to the 58.5 hours that were originally scheduled.

“To plane out Friday night and inlay 5,855 tonnes of asphalt by Sunday evening is simply unprecedented and we are incredibly proud of what we achieved on this project,” said Paddy Murphy, managing director of contracting services at Aggregate Industries.

For more information on companies in this article

Related Content

  • Vulcan Burners offers finance options for plant upgrade
    April 16, 2015
    Vulcan Burners are proud to announce that we can offer a comprehensive range of finance options for your burner upgrade and efficiency projects, either for individual plant upgrades via Carbon Trust loans and finance options, or multiple plant upgrades in association with private finance funding options.
  • Austria's new tunnel meets safety regulations
    July 13, 2012
    New safety regulations and high traffic volumes require new tunnel construction all across Europe. Mike Woof reports Anew highway tunnel now being built in Austria will boost traffic volumes and safety standards on a key European route. The existing Pfänder Tunnel lies close to Austria's borders with Germany and Switzerland and carries a heavy traffic volume, so a new parallel tunnel is under construction to help spread this load, increasing capacity as well as safety. Stringent tunnel safety standards have
  • This runway builder perfected paving and landed remarkable results
    August 31, 2023
    This busy airport needed a complete runway renovation without disrupting daily scheduled take-offs and landings. Each workday, construction could start no sooner than 11pm and couldn’t end a minute past 6am. Without state-of-the-art technology from Trimble—including 3D machine guidance—and expert training from SITECH, this complex and high-precision project would've never got off the ground.
  • Asphalt plant upgrade in Germany
    May 8, 2019
    An asphalt plant upgrade has helped boost long-term efficiency for a producer in southern Germany. The firm, Fiegl, based in Bavaria, invested in a new asphalt mixing plant four years ago. More recently, the firm also replaced the plant’s baghouse. The retrofit has since helped lower the plant’s emissions, noise output and fuel consumption. The time frame for the retrofit was tight because it was important to avoid lengthy downtime and production outages in mid-season. This meant that the changeover had to