Aggregate Industries finishes Leeds project ahead of time

Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning. Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail. The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly
January 24, 2019 Read time: 2 mins
No time to waste: Aggregate Industries worked full tilt 24/7 to finish the Leeds project
Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning.


Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail.

The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly and with minimum disruption to nearby businesses and the travelling public.

The 2297 Aggregate Industries contracting team liaised closely with local businesses for three months prior to the start of work onsite. They put together a phased 24-hour working programme that maintained access to affected businesses throughout the duration of the works.

Using this fastidious 24-hour working approach, no time was lost between shift changeovers. During phase 1 of the works, Aggregate Industries laid a 5,855tonnes of asphalt and around 7,500m2 of geotextile in just one weekend. Saturday night alone recorded 3,872tonnes of asphalt laid in 18 hours. This averaged at an 215tonnes every hour during this period.

Aggregate Industries completed their work well ahead of schedule and delivered the project in just 54 hours compared to the 58.5 hours that were originally scheduled.

“To plane out Friday night and inlay 5,855 tonnes of asphalt by Sunday evening is simply unprecedented and we are incredibly proud of what we achieved on this project,” said Paddy Murphy, managing director of contracting services at Aggregate Industries.

For more information on companies in this article

Related Content

  • JCB is stoked in Stoke
    February 7, 2022
    The UK city of Stoke-on-Trent has repaired 10,000m² of road with the JCB PotholePro in 130 days.
  • Meeting the IRF Fellows and hearing of their positive experiences
    April 23, 2019
    Morgan Morris, a master’s student at the University of Central Florida, recounts her life-changing experience as President of the 2019 Class of IRF Fellows After the short span of a week, a graduate research IRF Fellow transforms into an approachable, professional leader overflowing with inspiration and ideas. “In some ways, attending the IRF Fellows Road Scholar Program is comparable to going to an all-you-can-eat sushi buffet. You are not sure what exactly you signed up for, but in the end, you rea
  • Doka delivers on the Nawaseeb Road
    June 29, 2021
    The Nawaseeb Road in Kuwait forms an important part of the country's national infrastructure, providing a strategic, logistical corridor to neighbouring Saudi Arabia
  • McCann lights up the M1 in major upgrade
    January 7, 2019
    UK engineering firm J. McCann is installing 500 lighting columns and accessories as part of a major 12km upgrade to one of England’s busiest motorways.