Aggregate Industries finishes Leeds project ahead of time

Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning. Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail. The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly
January 24, 2019 Read time: 2 mins
No time to waste: Aggregate Industries worked full tilt 24/7 to finish the Leeds project
Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning.


Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail.

The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly and with minimum disruption to nearby businesses and the travelling public.

The 2297 Aggregate Industries contracting team liaised closely with local businesses for three months prior to the start of work onsite. They put together a phased 24-hour working programme that maintained access to affected businesses throughout the duration of the works.

Using this fastidious 24-hour working approach, no time was lost between shift changeovers. During phase 1 of the works, Aggregate Industries laid a 5,855tonnes of asphalt and around 7,500m2 of geotextile in just one weekend. Saturday night alone recorded 3,872tonnes of asphalt laid in 18 hours. This averaged at an 215tonnes every hour during this period.

Aggregate Industries completed their work well ahead of schedule and delivered the project in just 54 hours compared to the 58.5 hours that were originally scheduled.

“To plane out Friday night and inlay 5,855 tonnes of asphalt by Sunday evening is simply unprecedented and we are incredibly proud of what we achieved on this project,” said Paddy Murphy, managing director of contracting services at Aggregate Industries.

For more information on companies in this article

Related Content

  • The use of telematics in construction machines is growing
    May 20, 2015
    Demand for telematics technology is growing, as equipment users begin to lean the value of these systems – Alan Dron reports With construction projects increasingly operating to wafer-thin profit margins, any technological assistance that can keep the accounts in the black is welcome. This is particularly the case with those projects where contractors can share a larger slice of the profits if they complete their work ahead of schedule. The downside, of course, is that they also share the pain if the
  • Digging It gets down with Hyundai fleet
    October 3, 2018
    Ben Boare is the founder and managing director of Digging It Groundworks – a multifaceted construction company based in Andover in southern England. Boare formed Digging in 2007. “We initially started out doing small groundworks jobs, but as the years pass by we are focusing more and more on the plant hire side of things and our crushing, screening and recycling operation,” he said. The company has historically run a mixed fleet of hydraulic excavators, including JCB, Volvo, Takeuchi and Kubota. But in re
  • Tunnel construction benefits from improved visibility
    November 14, 2012
    Major new tunnel construction projects will, on completion, help secure more reliable journey times for hundreds of thousands of people across the world. Meanwhile, as Guy Woodford reports, leading ITS solution companies have been providing vital equipment for major road tunnels The Martina Tunnel Boring Machine (TBM), a 4,500tonne Herrenknecht Earth Pressure Balance Shield said to have a world record diameter of 15.55m, has required just under a year to build the first of two tunnel tubes for the 2.5km lon
  • The side effect – paving with a road widener
    December 13, 2018
    Sidewinder UK has been using its novel road widener machines on a series of paving jobs, including smart motorway projects. Sidewinder UK has carried out work on the M6 smart motorway contract between junction 16 and junction 19. The company used one of its road wideners to place and grade the final layer of sub-base to the balanced central reservation in readiness for Tarmac Contracting to pave the base and binder courses. An estimated 5,000tonnes of sub-base was used in the initial 6.4km x 4.7m wide st