Aggregate Industries finishes Leeds project ahead of time

Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning. Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail. The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly
January 24, 2019 Read time: 2 mins
No time to waste: Aggregate Industries worked full tilt 24/7 to finish the Leeds project
Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning.


Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail.

The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly and with minimum disruption to nearby businesses and the travelling public.

The 2297 Aggregate Industries contracting team liaised closely with local businesses for three months prior to the start of work onsite. They put together a phased 24-hour working programme that maintained access to affected businesses throughout the duration of the works.

Using this fastidious 24-hour working approach, no time was lost between shift changeovers. During phase 1 of the works, Aggregate Industries laid a 5,855tonnes of asphalt and around 7,500m2 of geotextile in just one weekend. Saturday night alone recorded 3,872tonnes of asphalt laid in 18 hours. This averaged at an 215tonnes every hour during this period.

Aggregate Industries completed their work well ahead of schedule and delivered the project in just 54 hours compared to the 58.5 hours that were originally scheduled.

“To plane out Friday night and inlay 5,855 tonnes of asphalt by Sunday evening is simply unprecedented and we are incredibly proud of what we achieved on this project,” said Paddy Murphy, managing director of contracting services at Aggregate Industries.

For more information on companies in this article

Related Content

  • Glass ceiling breakthrough for Ammann in Australia
    November 18, 2019
    An Ammann ABP High Recycling Technology (HRT) asphalt mixing plant is a key part of an Australian recycled glass-for-asphalt scheme.
  • New Holland 'space savers'
    February 15, 2012
    Zero tailswing excavators from New Holland are part of a plant deal won by civil engineering contractor K Rouse with Balfour Beatty. The machines, 11 E135BSRs and two smaller models, the E80 and E50, are being used on a section of the M621 motorway near the city of Leeds, northern England, to remove existing metal crash barriers and install improved drainage prior to the erection of a new concrete central reservation.
  • Itinera wins Sweden’s Skurusunds Bridge near Stockholm
    January 21, 2019
    Italian contractor Itinera will build the new 99m-long and 31m-wide Skurusunds Bridge near Stockholm in Sweden. Trafikverket, the Swedish transport administration, awarded the €75 million contract to Itinera, part of Gruppo Gavio. The new bridge will be parallel to the existing bridge which will remain. It handles around 52,000 vehicles daily, many of them commuting to and from Stockholm. Work will include improvements to traffic junctions at Skuru and Björknäs. The four-lane steel bridge will have
  • New asphalt compaction technologies boost quality
    February 28, 2012
    More sophisticated compaction technologies are now coming to market, offering a wide range of benefits to users