SuperPrixmat Ultra for Donington race track

Aggregate Industries completed the paving using its high-grip SuperPrixmat Ultra asphalt at the UK racing circuit just ahead of the British Superbike Championship last month.
By David Arminas June 8, 2023 Read time: 2 mins
Aggregate Industries’ supplied more than 5,000 tonnes of its high-grip SuperPrixmat Ultra asphalt, designed exclusively for motor racing circuits (image courtesy Aggregate Industries)

Construction materials supplier Aggregate Industries recently completed major resurfacing work at Donington Park race circuit, just ahead of the British Superbike Championship in May.

Essential and extensive track maintenance work included the removal and replacement of more than 6,500 tonnes of asphalt completed over 22 days. It represents the most significant improvement at the venue in almost 20 years, according to Aggregate Industries.  

Aggregate Industries worked with track-owners MotorSport Vision (MSV) and track designers Driven International as well as a complex supply chain. Provided were more than 5,000 tonnes of specially formulated high-grip SuperPrixmat Ultra asphalt, designed exclusively for demanding high-performance motor racing circuits. Aggregate Industries also provided 846 tonnes of binder course and 740 tonnes of stress-absorbing membrane interlayer, SuperSAMI.

The time-intensive project required Aggregate Industries to use two supply plants to maximise time and minimise disruption on-site during the 22-days of construction. This allowed for a continuous supply of asphalt to the site, enabling the team to lay the product at a consistent speed in echelon to achieve a jointless surface on the 4km (2.5 mile) track.

Aggregate Industries said that following the work, race officials noted an overall improvement to performance levels and circuit grip during the British Superbike Championship, resulting in the fastest laps set to date.

“The resurfacing of any major project requires meticulous planning and a true collaborative approach across all involved contractors. The resurfacing of Donington Park was no different,” said Vicky Smith, regional director for surfacing solutions at Aggregate Industries.

For more information on companies in this article

Related Content

  • Onsite asphalt recycling
    December 15, 2020
    Equipment from Ammann has played a key role in renovating a section of the N2 highway in Switzerland
  • From rubber to nanotechnology, new additives give longer life
    March 12, 2014
    This month: rubber comes to the rescue for cash-strapped UK authorities and Italian towns plagued by road noise; Japanese nanotechnology fights monsoon damage in India; and a new research programme promises to help define whether ‘sustainable’ bitumen technologies really live up to their billing - Kristina Smith writes A new venture in the UK aims to encourage the use of recycled tyres in road pavements. Billian UK is now manufacturing GTR Pellets which combine bitumen, ground tyre rubber (GTR) and miner
  • Super paving with Aggregate Industries’ SuperThin
    February 21, 2019
    Aggregate Industries’ contracting division recently laid a total of 1,800 tonnes of an ultra-low noise asphalt at Brampton Hut Services in Huntingdon in one weekend. Section 1 of Highways England’s A14 Cambridge-to-Huntingdon Improvement Scheme will see 21km of the road upgraded to three lanes in each direction and is expected to cut journey times by up to 20 minutes. The pavement works at Brampton Hut motorway services specified minimum sound level requirements of -7.5db (A). The limits are designed
  • Aggregate Industries finishes Leeds project ahead of time
    January 24, 2019
    Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning. Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail. The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly