Severn Bridge resurfacing complete

Contractor Hanson has completed the latest phase of its resurfacing work on the Severn bridges following the removal of the toll booths and barriers. The contract for Highways England started in December 2018, when the tolls were abolished on the M4 Prince of Wales Bridge and M48 Severn Bridge, and resurfacing was needed for the new road layout. The move to provide free access for drivers from England into Wales is aimed at boosting the Welsh economy. Over the last few weeks Hanson has laid more than
April 30, 2019 Read time: 2 mins
Resurfacing work is complete for the Severn bridges
Contractor 2644 Hanson has completed the latest phase of its resurfacing work on the Severn bridges following the removal of the toll booths and barriers.


The contract for 8100 Highways England started in December 2018, when the tolls were abolished on the M4 Prince of Wales Bridge and M48 Severn Bridge, and resurfacing was needed for the new road layout. The move to provide free access for drivers from England into Wales is aimed at boosting the Welsh economy.

Over the last few weeks Hanson has laid more than 10,000tonnes of base, binder and surface course material to complete the remodelling of the westbound side of the M4 Prince of Wales Bridge. The contracting team laid the final 2,200tonnes overnight in just 12 hours – more than double the amount usually handled on a regular motorway nightshift.

As well as resurfacing the toll booth area, the work has included 950m of the westbound carriageway and a new emergency access road.

Next month (May), the Hanson team will start a similar job on the M48 Severn Bridge; resurfacing the toll booth plaza as well as 1.5km of carriageway on both sides of the bridge.

Hannah Milliner, Severn Bridges General Manager at Highways England said: “This is a significant project for the region and Hanson has worked collaboratively with Highways England and its contractors to ensure that we deliver these works both safely and to schedule. Hanson has played an important part in making toll removal a success. We are currently reaching the final stages of the scheme and drivers will soon be able to benefit from free-flowing motorways.”

For more information on companies in this article

Related Content

  • Attitude is key to sustainability, says Volvo CE’s Thomas Bitter
    June 27, 2018
    Whether you are in the global Volvo Ocean Race or working on-site locally, sustainability is about attitude as much as technology. David Arminas reports. Technology, sustainability and safety. We ignore these often related themes at our peril. This was the key point made by Volvo Group chief executive Martin Lundstedt during his brief opening presentation at the start of the Building Tomorrow Conference in Spain last October. The conference took place within the harbour of Alicante that was bustling wit
  • How bitumen technology solutions are solving paving problems around the world
    March 2, 2017
    This month we hear how additives can bring RAP back from the dead and fight the ravages of salt damage, how pellets reach parts that PMB can’t and how Shell and WeedsWest are expanding their respective businesses - Kristina Smith writes
  • Innovative, flexible bridge formwork systems
    February 14, 2012
    Innovative formwork systems have been used to construct a variety of bridge structures. Patrick Smith reports. As part of the work on Germany's new A4 autobahn near Eisenach, the contracting joint venture awarded the formwork contract for two of the three viaducts to Doka. What makes this assignment so special to the company is that although the two steel composite bridges each have very different cross-sections, the JV is using the same overslung composite forming carriage to pour the carriageway slabs of
  • Formwork developments in bridge construction
    February 23, 2012
    Major infrastructure projects worldwide are relying on innovative formwork solutions for speed and safety as Patrick Smith reports. The 970m long cable-stayed Golden Ears Bridge crossing the Fraser River in Vancouver, Canada, is the core element of a six-lane, highway project near the Canadian west coast.