Severn Bridge resurfacing complete

Contractor Hanson has completed the latest phase of its resurfacing work on the Severn bridges following the removal of the toll booths and barriers. The contract for Highways England started in December 2018, when the tolls were abolished on the M4 Prince of Wales Bridge and M48 Severn Bridge, and resurfacing was needed for the new road layout. The move to provide free access for drivers from England into Wales is aimed at boosting the Welsh economy. Over the last few weeks Hanson has laid more than
April 30, 2019 Read time: 2 mins
Resurfacing work is complete for the Severn bridges
Contractor 2644 Hanson has completed the latest phase of its resurfacing work on the Severn bridges following the removal of the toll booths and barriers.


The contract for 8100 Highways England started in December 2018, when the tolls were abolished on the M4 Prince of Wales Bridge and M48 Severn Bridge, and resurfacing was needed for the new road layout. The move to provide free access for drivers from England into Wales is aimed at boosting the Welsh economy.

Over the last few weeks Hanson has laid more than 10,000tonnes of base, binder and surface course material to complete the remodelling of the westbound side of the M4 Prince of Wales Bridge. The contracting team laid the final 2,200tonnes overnight in just 12 hours – more than double the amount usually handled on a regular motorway nightshift.

As well as resurfacing the toll booth area, the work has included 950m of the westbound carriageway and a new emergency access road.

Next month (May), the Hanson team will start a similar job on the M48 Severn Bridge; resurfacing the toll booth plaza as well as 1.5km of carriageway on both sides of the bridge.

Hannah Milliner, Severn Bridges General Manager at Highways England said: “This is a significant project for the region and Hanson has worked collaboratively with Highways England and its contractors to ensure that we deliver these works both safely and to schedule. Hanson has played an important part in making toll removal a success. We are currently reaching the final stages of the scheme and drivers will soon be able to benefit from free-flowing motorways.”

For more information on companies in this article

Related Content

  • Pattullo Bridge deck near completion
    July 29, 2025
    For several weeks, crews have been installing concrete deck panels, steel girders and stay cables outward from the towers of the bridge that spans the Fraser River near Vancouver, Canada.
  • European digitalisation of construction industry offers roadmap for future
    June 11, 2018
    Europe’s leading construction industry associations are joining forces to publicise the release of a new manifesto on digitalisation. This construction industry manifesto focuses on the use of smarter construction technologies in a bid to deliver a stronger economy, an inclusive society and more efficient practises. The manifesto calls for strong political leadership from the EU, an appropriate regulatory framework on data policy and budgetary focus on digital skills, research and development and IT infrast
  • Solving congestion in Brisbane
    August 2, 2012
    Rapid growth in a major Australian city in recent years has created new problems for the infrastructure and especially transport Expansion in the city of Brisbane, the Queensland state capital and the third largest city in the country, is set to continue and some 1,500 people arrive/week from within Australia and from other parts of the world. At this rate by 2026 the city's population should increase by 1.4 million: at present it is 1.8 million. To cope, the Queensland government and city council have ini
  • Novel twin layer paving technology saves time
    February 28, 2012
    German paver specialist Vögele reports that market acceptance is growing for its novel twin layer paving technology