Road paving record set

Aggregate Industries has set what it believes to be a road paving record.
By MJ Woof July 10, 2020 Read time: 3 mins
Aggregate Industries was able to complete its paving works on the M23 a full six months ahead of schedule

Aggregate Industries has set what it believes to be a record for asphalt paving in the UK. The firm completed its work early on the M23, to the south of London.

According to the company, collaboration was a key to the successful early completion of the project. The firm was able to lay 52,000tonnes of asphalt on the M23 motorway in just one month. This was achieved using a number of evening and weekend closures and successful collaborative arrangements.

Aggregate Industries says that it was able to engage with external stakeholders across the supply chain to ensure the tight deadlines were met. This enabled the firm to break industry records and complete the work ahead of schedule.

The contract included widening the carriageway to achieve the all lane running requirement, full depth reconstruction of the hard shoulder, central reserve works and collaborative completion of junctions 9,10 and lane four surfacing to enable the road to open for traffic.

With Aggregate Industries’ Contracting Division acting as the lead surfacing partner, the materials for the project were supplied by its Asphalt and Aggregates Divisions, and delivered by its Logistics Team.

The company recycled 100% of the waste material from the pre-existing road using a local facility that crushed and screened it for use in the new asphalt. A proportion of the material will also be used, where possible, in the firm’s larger asphalt plants within its materials. As a result of the close proximity of the recycling facility, less haulage was required reducing the project’s carbon emissions.

Faced with a large tonnage of asphalt to lay in a tight deadline, Tarmac was enlisted as the second surfacing partner. This drew on a long standing relationship with Aggregate Industries through the Highways England Category Management Pavement Framework. The collaboration between all parties; similarities in systems of working; and the ability to share resources, drove efficiencies that resulted in laying 52,000tonnes one month. The pavement works were completed six months ahead of the initial forecasted date.

In addition to the logistical, technical and time requirements for the project, the team also adapted quickly to a new working environment due to the Covid-19 pandemic. The team planned stringent working arrangements to make sure that the project was finished in accordance with social distancing guidelines.  

Paddy Murphy, managing director of Contracting at Aggregate Industries, said: “Not only is this project a great example of collaboration, flexibility and ingenuity within Aggregate Industries, but it is also further testament that even in uncertain times, businesses like ours, and all the parties we worked in close partnership with, are essential to keeping the country moving.”

For more information on companies in this article

Related Content

  • Long life asphalt paving reduces maintenance
    May 8, 2012
    Contractor FM Conway is working on a three year contract with Dover Harbour Board to reconstruct and resurface busy access routes and large vehicle parks within the port. One of the major factors for this contract being awarded was the company's strong green credentials. The contract is based around small and large individual paving projects within the Eastern Docks, which can range in time scales from three weeks to six months. The first phase of work, which started in early May, was to fully reconstruct
  • Technology and collaboration bring massive time savings
    December 2, 2021
    The link between any major city and its airport is a crucial one. In Auckland, New Zealand, State Highway 20B connects the city of 1.6 million people with the rest of the nation and the international airport, one of only two roads leading there
  • Recycling concrete runway saves time, money
    February 17, 2012
    Nashville International Airport in the US state of Tennessee has revamped its facilities following extensive upgrades being carried out on its oldest runway in a project worth some US$23 million. The airport authorities realised that to improve both capacity and safety a major improvement of runway 2L-20R was required, with full-depth reconstruction needed to provide the necessary structural strength and working life. Engineering firm Garver Aviation worked on the project to rehabilitate the portion of Runw
  • Circuit of the Americas Formula for F1 success
    April 4, 2013
    In November 2012, the new Circuit of the Americas (COTA) in Austin, Texas, hosted the first ever Formula 1 US Grand Prix on a purpose-built track. But, as Jeff Winke and Guy Woodford report, the construction of COTA was just as demanding as competing in an F1 race itself For COTA construction contractor Austin Bridge & Road, L.P., nothing was more vital to the successful building of the 5.5km F1 track than meeting the strict criteria for its asphalt-paved surface. “The amount of stress this pavement will un