Bolivia’s new highway will provide better access into mountain areas – Mauro Nogarin writes At the beginning of 2015, work began on the construction and paving for the Tupiza - Atocha - Uyuni highway project. The route is located in Bolivia’s Potosí department: it is 189m in length and forms part of the Southwest Basic Road Network (RVF) of Bolivia. The completion of this important route is requiring funding worth US$150 million, of which 72% is being delivered through loans from the European Investment
October 10, 2017 Read time: 4 mins

 Bolivia’s new highway will provide better access into mountain areas – Mauro Nogarin writes

At the beginning of 2015, work began on the construction and paving for the Tupiza - Atocha - Uyuni highway project. The route is located in Bolivia’s Potosí department: it is 189m in length and forms part of the Southwest Basic Road Network (RVF) of Bolivia.

The completion of this important route is requiring funding worth US$150 million, of which 72% is being delivered through loans from the European Investment Bank and the CAF - Latin American development bank, and the remaining 28% comes from the government of the department of Potosí.

This route will increase and diversify the economic development in the southern region of the country, both with tourism at the Salar de Uyuni and with agricultural and mining activity. It is estimated that the travel time will be reduced from 5 hours to two hours and 25 minutes, benefiting the populations of Uyuni, Noel Mariaca, Cerdas, Atocha, Villa Solano, Thola Mayu, Palca Flores, Salo, San Miguel and Tupiza.

According to the project the work is taking 42 months in all, and will open to traffic in June 2018. The majority of the area is located in the highlands, between the Eastern and Western ranges of the Bolivian Andes. The road runs along morphological zones that appear as flat and semi-flat, with undulations and relatively low mountains, where the road mapping is between a flat and wavy topography, as well as straight and winding. The road engineers will use gradients of between 9-10%

In the Atocha and Tupiza Sector, the high mountains range in altitudes from 3,000-5,500m above sea level, with slopes between 15% and 60%, and their lengths of 200-500m. And the average mountains reach elevations from 2,500-5,150m, with slopes of around 10% to more than 60%, with variable lengths between 200 - 500 m.

The main climatic characteristics of the area covered by the project in the municipality of Uyuni are intense cold and little rainfall with an average relative humidity of 33%.

The design of the first 86km of the road consists mostly of long straight sections with few curves, while the vertical geometry features a few smooth slopes. However once the route reaches the town of Atocha, the horizontal geometry suddenly becomes more complex and includes a series of curves.

The next stretch of the road from Atocha to the town of Tupiza measures 103km long and climbs in altitude, with the route featuring with closed curves and drops that reach 10%. Meanwhile the area also features significant slopes as it is a mountainous zone. The road improvements required changes to the alignment and horizontal adjustment to boost safety.

Because of the complex geography and geology of the area, the drainage system designed for the Uyuni to Tupiza stretch of road features both surface and underground systems. The construction of 231 sewers is planned, most of which are in sectors where there are bofedales (high-altitude areas of boggy peat that are common in the Andes, having been expanded by human habitation to increase vegetation) and outcrops of water flows. Three grades of concrete, type "A" (210kg/cm2), type "C" (160kg/cm2) and type "E" (110kg/cm²) are used for these drainage works, with the specific design catering to the volume of water calculated.

The construction company José Cartellone currently has two working areas on the project, with one located in the section between Km23 to Km63 where paving works are being carried out. The second is located in the section between Km77 to Km 90, where excavations are being carried out along with stabilisation of the embankment and alignment. In general the roadway is 7m wide in total and a features a 1m berm with a 50mm asphalt layer that includes the use of PMBs. The design speed of the road is estimated at 80km/h. The structure of the road itself features a sub-base layer of 220mm and with a base layer of 150mm and an asphalt surface 70mm thick.

Along the entire route, seven bridges will be built, with a total length of 351m. However the most important bridges are located at Choroma and Tolonias, with construction starting at the end of 2017. The Choroma Bridge features a design comprising two reinforced concrete supports sitting on deep foundations, while the superstructure has a reinforced concrete slab and a design with three pre-stressed concrete beams that are 35.6m in length. The bridge also consists of two spans and is 71.2m long.

The Tolonias Bridge meanwhile has a similar design with two reinforced concrete supports resting on piles that are 1.2m in diameter. The reinforced concrete slab superstructure has three pre-stressed concrete beams that are also 35.6m in length and with the two spans, the bridge is also 71.2m long.


Related Content

  • Key expressway route through Hunter Valley
    November 11, 2013
    Australia’s Hunter Valley will benefit from a new high speed expressway, which is currently under construction - Simon Gould reports Located two hours north of Sydney, the Hunter Valley region in New South Wales is one of Australia’s largest producers of coal and wine. With international demand, particularly from Asia, for both continuing to increase, a significant upgrade of infrastructure was required between the region and the port of Newcastle, the world’s largest coal export port. However the strict en
  • 48 hours re-opening
    July 6, 2012
    Using demolition tools from Atlas Copco helped to maximise productivity on a highly time-sensitive project in Germany. The A3 autobahn runs from the Dutch/German border through the western part of the Ruhr area, the Cologne area, the Rhine-Main area and Bavaria down to the Austrian border at Stuben. It is one of the most heavily used highways in Germany and because of increasing traffic volumes, widening the road to six lanes has become necessary.
  • Mongolia’s capital Ulaanbaatar is redeveloping its airport
    August 23, 2016
    Mongolia’s economy is growing fast, with capital Ulaanbaatar the centre for activity. Being landlocked, the country depends heavily on aviation to carry passengers and cargo. The existing Chinggis Khaan International Airport was built in 1956 and upgraded in 1987 and 1997 for international traffic. But the old airport cannot meet demands and boosting the country’s capacity to handle flights is essential. The New Ulaanbataar International Airport (NUBIA) will triple passenger capacity to approximately 3
  • Bridge engineering worldwide
    July 1, 2013
    Guy Woodford looks at vital bridge construction, repair and inspection projects in China, Europe, North America and Australia The Heron Road Bridge in Ottawa, Ontario in Canada is a vital link within the City’s transport network, as it crosses the Rideau River, which divides the east and west parts of the City. Constructed in 1966-1967, the Heron Road Bridge is approximately 275m long and includes six lanes.