Skip to main content

Tensar’s Glasstex makes the grade in UK’s Smart Motorway upgrade

A Stress Absorbing Membrane Interlayer is delivering stronger, safer and more reliable surfaces for the UK’s M3 Smart Motorways project in the southern England.
February 27, 2017 Read time: 3 mins
Smart move: Foster Contracting is laying 300,000m2 of Tensar’s Glasstex P100 composite on the M3

A Stress Absorbing Membrane Interlayer is delivering stronger, safer and more reliable surfaces for the UK’s M3 Smart Motorways project in the southern England.

More than 130,000 vehicles use the M3 between Junctions 2 (Thorpe and the M25 motorway) and 4a (Farnborough) every day.

As part of 8100 Highways England’s Smart Motorways programme, the capacity of this congested three-lane section is being increased, with hard shoulders converted to ‘smart’ running lanes.

Construction began on site in January 2015. Asphalt surfacing contractor 2399 Tarmac, working for the principal contractor 1146 Balfour Beatty, is carrying out structural resurfacing of the carriageway as part of the project.

“The road is in poor condition, the result of reflective cracking of the asphalt, due to movement of the underlying layers that are made up of both lean mix concrete and bituminous road base,” says Tarmac project manager Barrie Farquhar. “Repairs were needed to strengthen the road and to prevent further cracking, which could have led to water ingress and further deterioration of the concrete.”

Highways England needed a pavement solution that would reduce initial costs, increase service life, as well as minimise maintenance and future disruption.

Consultant 1397 Aecom had specified asphalt reinforcement in the pavement design. Tarmac, subcontractor Foster Contracting and 340 Tensar International proposed Tensar’s Stress Absorbing Membrane Interlayer (SAMI) Glasstex solution, while supporting the required departure from the standard process.

“The SAMI adds tensile stiffness, increasing pavement strength at low strain and mitigating reflective cracking from both traffic-induced stress and from defects in the underlying pavement structure. It also acts as a moisture barrier,” explains Tensar Highways manager Craig Andrews. “This low-maintenance solution will extend the operating life of the pavement, reducing whole-life costs.”

A total of 300,000m2 of Tensar’s Glasstex P100 composite is being laid by Foster Contracting, on both the northbound and southbound carriageways, along the 26km stretch of road – a total of 52km. This composite of glass yarn grid and paving fabric forms an interlayer between the fractured substrate and the asphalt overlay.

“Glasstex adheres to the underlying pavement structure using a straight run bitumen (160/220 pen) bond coat, with a calibrated spray rate of 1.1kg/m², to activate both stress relief and interlayer barrier functions [as given by BS EN 15381: 2008], with reinforcement provided by the grid,” Andrews says.

“Combined with Tarmac’s Ultilayer polymer-modified binder course, this delivers maximum possible crack resistance and durability.”

An added benefit of installing a SAMI Glasstex solution on motorway projects is speed, Andrews adds. “Work typically has to be carried out at night, which obviously limits the amount of time available. Using Glasstex means the reconstruction depth is far shallower. On the M3 it is just 120-150mm, rather than a minimum 360mm with a standard approach, which obviously saves time and, as a result, construction costs.”

With surfacing work progressing well and half the new gantries installed by the summer, the M3 Smart Motorway project looks to be on target to finish as planned in June 2017.

For more information on companies in this article

Related Content

  • Smart traffic management market potential is the global future
    July 20, 2012
    According to a new report from ABI Research, as the global population hurtles past the seven billion barrier, more and more people are living in cities than ever before. This is especially true of developing countries which account for 20 of the world’s 27 megacities. With above average levels of population and economic growth in these regions, traffic congestion has quickly ensued, which is detrimental to GDP, the environment, as well as health and safety. The new ABI Research report predicts that companie
  • New barrier, crash cushion and access control technology will benefit road user safety
    October 26, 2012
    Protecting road users, with barriers, crash cushions or access control systems, is crucial for network safety - Mike Woof writes Tough regulations are now in place in Europe and the US, requiring road authorities to provide safer road infrastructure than in the past. Technologies to reduce the severity of vehicle impacts against obstructions or redirect vehicles into the roadway should help cut injuries amongst drivers and passengers alike. The specifications for the use of crash cushions and barriers can v
  • Severn Bridge resurfacing complete
    April 30, 2019
    Contractor Hanson has completed the latest phase of its resurfacing work on the Severn bridges following the removal of the toll booths and barriers. The contract for Highways England started in December 2018, when the tolls were abolished on the M4 Prince of Wales Bridge and M48 Severn Bridge, and resurfacing was needed for the new road layout. The move to provide free access for drivers from England into Wales is aimed at boosting the Welsh economy. Over the last few weeks Hanson has laid more than
  • Developments in geosynthetics
    February 24, 2012
    Independent tests are showing the benefits of the latest geosynthetics developments. Geosynthetics specialist Tensar has commissioned independent tests to prove the capabilities of its innovative TriAx product, which has set a lead in the field.