Tensar’s Glasstex makes the grade in UK’s Smart Motorway upgrade

A Stress Absorbing Membrane Interlayer is delivering stronger, safer and more reliable surfaces for the UK’s M3 Smart Motorways project in the southern England.
February 27, 2017 Read time: 3 mins
Smart move: Foster Contracting is laying 300,000m2 of Tensar’s Glasstex P100 composite on the M3

A Stress Absorbing Membrane Interlayer is delivering stronger, safer and more reliable surfaces for the UK’s M3 Smart Motorways project in the southern England.

More than 130,000 vehicles use the M3 between Junctions 2 (Thorpe and the M25 motorway) and 4a (Farnborough) every day.

As part of 8100 Highways England’s Smart Motorways programme, the capacity of this congested three-lane section is being increased, with hard shoulders converted to ‘smart’ running lanes.

Construction began on site in January 2015. Asphalt surfacing contractor 2399 Tarmac, working for the principal contractor 1146 Balfour Beatty, is carrying out structural resurfacing of the carriageway as part of the project.

“The road is in poor condition, the result of reflective cracking of the asphalt, due to movement of the underlying layers that are made up of both lean mix concrete and bituminous road base,” says Tarmac project manager Barrie Farquhar. “Repairs were needed to strengthen the road and to prevent further cracking, which could have led to water ingress and further deterioration of the concrete.”

Highways England needed a pavement solution that would reduce initial costs, increase service life, as well as minimise maintenance and future disruption.

Consultant 1397 Aecom had specified asphalt reinforcement in the pavement design. Tarmac, subcontractor Foster Contracting and 340 Tensar International proposed Tensar’s Stress Absorbing Membrane Interlayer (SAMI) Glasstex solution, while supporting the required departure from the standard process.

“The SAMI adds tensile stiffness, increasing pavement strength at low strain and mitigating reflective cracking from both traffic-induced stress and from defects in the underlying pavement structure. It also acts as a moisture barrier,” explains Tensar Highways manager Craig Andrews. “This low-maintenance solution will extend the operating life of the pavement, reducing whole-life costs.”

A total of 300,000m2 of Tensar’s Glasstex P100 composite is being laid by Foster Contracting, on both the northbound and southbound carriageways, along the 26km stretch of road – a total of 52km. This composite of glass yarn grid and paving fabric forms an interlayer between the fractured substrate and the asphalt overlay.

“Glasstex adheres to the underlying pavement structure using a straight run bitumen (160/220 pen) bond coat, with a calibrated spray rate of 1.1kg/m², to activate both stress relief and interlayer barrier functions [as given by BS EN 15381: 2008], with reinforcement provided by the grid,” Andrews says.

“Combined with Tarmac’s Ultilayer polymer-modified binder course, this delivers maximum possible crack resistance and durability.”

An added benefit of installing a SAMI Glasstex solution on motorway projects is speed, Andrews adds. “Work typically has to be carried out at night, which obviously limits the amount of time available. Using Glasstex means the reconstruction depth is far shallower. On the M3 it is just 120-150mm, rather than a minimum 360mm with a standard approach, which obviously saves time and, as a result, construction costs.”

With surfacing work progressing well and half the new gantries installed by the summer, the M3 Smart Motorway project looks to be on target to finish as planned in June 2017.

For more information on companies in this article

Related Content

  • Extreme climates pose tough duty cycles and challenges for testing procedures
    April 5, 2013
    This month we look at how pavement testing technology is responding to extremes of temperature, showcase concrete testing in Doha and look at how water drops could help identify delaminated bridge decks - Kristina Smith reports One of the biggest challenges that pavement engineers face is how to design for extremes of temperature. Designing for cold weather can result in problems at higher temperatures – and vice versa. In Scandinavia, generally a cold climate, they are facing this problem. In the summer,
  • Energy absorbing safety barrier
    March 9, 2012
    Barrier Systems says that its new tensioned barrier offers high energy absorbing capabilities in head-on collisions. The company says that this is because the X-Tension technology is a tension-based solution rather than compression-based. The new range delivers good performance in these applications, as energy is absorbed with resistance at the impact head rather than being transferred down the rail as occurs with other systems. Even high-angle (15° during testing) impacts on the nose resulted in the vehicl
  • €2.27bn UK road investment in 2014 to support over 9,500 construction jobs
    November 11, 2013
    Over 9,500 construction jobs will be supported in 2014 by more than €2.27 billion (£1.9 billion) of investment in Britain’s roads, Transport Minister Robert Goodwill announced today. The total investment in 209 schemes is €5.15 billion (£4.3 billion), with the €2.27 billion to be spent in 2014 more than twice the amount being spent this year. Due to either start or be completed in 2014, these road programmes are estimated to boost the economy by over €22.52 billion (£18.8 billion) and are part of a €119.8
  • Holding back
    February 6, 2012
    AN INNOVATIVE slurry wall solution has been used by Bachy Soletanche at the Alderley Edge By-Pass project in the UK. Bachy Soletanche provided assistance for the A34 Alderley Edge by-pass project in the UK being carried out by main contractor Birse Civils. This solution was required to tackle challenges posed by the water table at the Welsh Row section. Bachy Soletanche used its experience with slurry cut-off walls, a technique rarely used in Britain on road construction, to benefit a tricky section of the