Road recycling in Denmark

A novel approach to road refurbishment has saved time, money and carbon emissions in Denmark, while delivering a quality road surface.
By MJ Woof May 13, 2024 Read time: 4 mins
Hamm rollers were used to carry out the compaction duties

The use of novel road recycling technology for a project in Denmark has delivered a quality surface in reduced time. And this has been achieved, while dramatically reducing carbon emissions from the work. 

The project was managed by the local contractor SR-Gruppen A/S, which used equipment from the Wirtgen Group to deliver the work in 50% of the time and a CO₂ reduction of over 50%.

A 6.5km section of the busy E 45 highway close to the famous Legoland resort at Billlund was becoming worn due to heavy traffic levels and was in need of major repairs. An innovative approach to the refurbishment work was taken, specifying recycling of the existing asphalt surface to produce a 200mm base layer of cold mix.

A KMA 240i mobile cold recycling plant from Wirtgen played a central role for the job, with the contractor also utilising Wirtgen milling machines as well as Vögele paving equipment and Hamm compaction rollers.

The client had specified cold recycling of the road surface material as this offers a sustainable construction method for structural rehabilitation. The work had to be carried out to a tight schedule so efficient production was crucial. “We produced up to 300tonnes of cold mix/hour with the KMA 240i,” said Morten Wold, divisional manager for the contractor.

The E 45 highway was milled at widths varying from 3.15-5.9m  and a depth of 280mm using Wirtgen W 210i and W 250i milling machines. The milled material was transported to the KMA 240i mixing plant located nearby, where it was recycled into cold mix. Because the cold mixing plant is mobile, the contractor was able to keep the treatment operation close to the asphalt removal and paving location, cutting material transport. This method reduced transport requirements by around 70%, cutting CO₂ emissions for the construction project.

To verify the quality of the finish, tests were carried out on the reclaimed asphalt pavement (RAP) before construction commenced.

The mix was loaded into an impact crusher and reduced to a size of 0–32mm, loaded by wheel loader into the KMA 240i’s large-capacity receiving hopper, and fed into the twin-shaft continuous mixer. The machine used featured twin feed augers with a double-trough system as well as an accurate weighing system that ensured the necessary quantities of lime and cement binding agent additives were used. The continuous weighing system ensured that the additives were precisely dosed. The foamed bitumen was added using the microprocessor-controlled dosing system and the mix included 2.2% foamed bitumen, 6% lime and 0.8% cement.

A total of 51,000tonnes of the stabilised bituminous cold mix was used for the project and was loaded into trucks and transported to the jobsite. Graders and Hamm rollers were used to prepared the frost protection layer beneath the milled off asphalt pavement as a roadway for pavers and trucks to operate on. A MT 3000-2i mobile feeder from Vögele was employed to ensure a steady material flow on the site.

As no road closures were permitted, the material transport logistics were challenging. However, the MT 3000-2i provided the necessary versatility to rehabilitate two lanes of highway, a total of 20.45m-wide.

A Vögele SUPER 1900-3i paver was used to lay the material true to grade and slope, providing a 200mm base layer of cold mix as the foundation for the highway. Care was taken during compaction, using a 12tonne Hamm HD 120i tandem roller carrying out the necessary compaction duties followed by a Hamm GRW 280i pneumatic-tyre roller, to deliver the final surface treatment.

After only two days, the contractor was able to lay down a binder course and a surface layer with a thickness of 80mm. For this, the firm chose a robust asphalt grade modified with polymers that suited the requirements of the route, which carries heavy traffic and a high percentage of large trucks. The Vögele SUPER 1900-3i and MT 3000-2i were also used to lay the binder course and wearing course, with the Hamm tandem roller carrying out the main compaction work and the Hamm rubber tyre rollers handling the finishing duties. Using this method delivered a significant reduction in fuel consumption, transport costs, CO2 emissions and also cut the time needed for the work by 50%.
 

For more information on companies in this article

Related Content

  • Bolivia tunnel and highway project under construction
    February 9, 2017
    In Bolivia work is progressing on the strategic Incahuasi tunnel project – Mauro Nogarin writes In southern Bolivia, the Bolivian Highway Administrator (ABC) is supervising the construction of the Incahuasi Tunnel and Monteagudo-Muyupampa-Ipati road. This work is of fundamental importance for the country as it will improve the flow of traffic and boost trade between the departments of Santa Cruz and Chuquisaca. The Monteagudo-Ipati highway project includes the Incachuasi tunnel which has a length of 96km
  • Smarter paving for Berlin ring road
    December 13, 2018
    Germany’s capital Berlin is now benefiting from a newly widened ring road, which will help reduce peak time congestion Much of the work has been carried out by local contractor Johann Bunte Bauunternehmung, which has helped to widen the Berlin ring road from six to eight lanes. The firm has made extensive use of sophisticated paving controls also on its Vögele machines, the AutoSet Plus automatic functions. And the firm claims that these tools have made the work easier for the paving team to move between t
  • Innovative asphalt plant from Benninghoven
    February 28, 2018
    Benninghoven claims that its innovative asphalt transfer system boosts the capabilities of the firm’s ECO mixing plant range. The newly developed alternating chute unit is fitted to the firm’s ECO asphalt plant and is said to be a key development for the sector, with a patent pending. The ECO asphalt plant is offered with output ranging from 100-320tonnes/hour and is said to combine the latest Benninghoven technology and quality. Designed for mobility, the plants fit inside standard shipping containers
  • Better road surfaces to last longer
    August 23, 2013
    Preservation can make roads perform better and last longer - and save money in the long run. Kristina Smith reports BAM Wegen has laid the first ever half-warm porous asphalt section on a major highway in the Netherlands. The asphalt for the 500m-long test section on the A18 near Varsseveld was produced at 105°C rather than 160°C, representing a saving on energy and CO2 emissions of around 30%.