Removing runway rubber

When Dubai Airport contacted Waterblasting Technologies it faced a number of challenges. One was finding a waterblasting system that would operate successfully in the 42º-52ºC daylight heat of the summer and also to find the fastest and most productive waterblasting system because of very limited runway closure time. Chemicals, shotblasting and other waterblasting equipment had been tried on the runways, but eventually engineers and management chose the Stripe Hog SH8000T manufactured by Waterblasting Tech
April 4, 2012 Read time: 2 mins

When Dubai Airport contacted Waterblasting Technologies it faced a number of challenges.

One was finding a waterblasting system that would operate successfully in the 42º-52ºC daylight heat of the summer and also to find the fastest and most productive waterblasting system because of very limited runway closure time.

Chemicals, shotblasting and other waterblasting equipment had been tried on the runways, but eventually engineers and management chose the Stripe Hog SH8000T manufactured by 362 Waterblasting Technologies.

The system, which can be built on a variety of truck chassis, uses needle sharp water jets to quickly remove all types of roadway and airfield marking paint as well as runway rubber deposit build-up.

According to the company the Dubai airport runways is probably the most challenging rubber removal environment in the world with an average of 800-plus movements a day with summer-time peaks of 1,100/day and an average of only 5-10 days of rain each year.

"With the ability to remove runway rubber deposits on average of 1,672m²/hour and the ability to operate in the extreme heat without breaking down, the SH8000T became the product of choice for the Dubai airport," says Waterblasting Technologies, which also offers the SH8000T or the new SH8000R with optional, on-board water recycling.

For more information on companies in this article

Related Content

  • Fast flyover removal with specialist demolition equipment
    July 12, 2012
    An overcrowded Indian flyover was removed in record time using specialist demolition equipment, as Patrick Smith reports Demolition of the landmark Lalbaug flyover south of central Mumbai has been completed and work on a new bigger bridge has started in India's largest city. Although the 38-year-old Sant Dnyaneshwar (Lalbaug flyover) two-lane, one-way traffic artery was serviceable and used by to 15,000 vehicles/hour, there were daily traffic jams and environmental consequences. Despite the complex and dema
  • Big measuring from TinyMobileRobots
    February 27, 2017
    Small is beautiful, especially when it comes to robots, explains Jens Peder Kristensen, director of Danish company TinyMobileRobots With the increased functionality of outdoor robots, the market for autonomous robots as a replacement for human work has widened. The human touch is still needed when dealing with terrain that is difficult to navigate or with a crowded construction site.
  • Efficient milling and re-paving on historic Florence streets
    February 1, 2013
    Maintenance of roads in historic districts is a challenge for communities around the world. The sanctity of the surroundings limits the amount of re-engineering and widening that can be considered. Improvement options typically are limited to repairs. Yet repairs also have an impact. The historic areas usually attract tourists and their crucial economic contributions. If the street repairs create too much of an inconvenience, tourists are likely to avoid the area and a negative economic impact and a loss of
  • Kosovo's award-winning green highway construction
    March 20, 2012
    A new highway is proving an economic lifeline for the tiny country of Kosovo – Mike Woof reports. Road projects in Europe rarely meet such widespread public approval and support as the new Route 7 highway being built in the new Balkan state of Kosovo. The first sections of the new road opened to traffic in November 2011, with locals turning out in large numbers to celebrate the event. The official opening was carried out by the country’s prime minister Hashim Thaçi, president Atifete Jahjaga, and members of