Equipment from Vögele and Hamm has been used to build a carriageway with reduced-temperature asphalt in Germany. The equipment was required for paving a road tunnel in Kahrlsruhe. Tough conditions were applied to paving in the road tunnel under the Kriegsstrasse road.
June 28, 2021 Read time: 4 mins
Two Vögele pavers were used for the low temperature surfacing work on the tunnel in Karlsruhe

To minimise emissions, the contractor employed machines with diesel particulate filters and reduced-temperature asphalts. Using Vögele pavers and Hamm rollers, the consortium handling the work, which comprised Schleith and Züblin, was able to meet the requirements and pave the mix efficiently and in high quality. The road tunnel work forms part of a wider project to improve the centre of Karlsruhe. What was previously a wide road for through traffic is being transformed into a public space for pedestrians, with a landscaped tram track and an avenue of trees featuring cycling facilities. An underground train line is being built while through traffic is being diverted into a 1.6km road tunnel.

The client Karlsruher Schieneninfrastruktur-Gesellschaft (KASIG) wanted to minimise exposure to exhaust fumes for the paving team surfacing the dual tunnel bores of 5.3m and 6.8m width respectively. Only construction machines fitted with diesel particulate filters were allowed to work in the tunnel. The use of low-temperature asphalts was also specified as their paving temperature is 30°C lower than hot asphalt, reducing vapours and emissions as well as exposure to heat. Lower temperature asphalts also have a high resistance to deformation and important advantage for the tunnel with its anticipated heavy traffic volumes.

This choice of mix presented several challenges. Special waxes were used to optimise compaction, even at low temperatures, while the mix had to be paved and compacted as quickly and smoothly as possible. The contractor, Martin Paschmann Asphaltbau, used two SUPER 1800-3i pavers from Vögele and three Hamm compactors: a DV+ 90i VT-S-type combination roller, a DV+ 70i VV-S tandem roller and an HD 14i VO compact roller.

Efficient paving was crucial and the pavers achieved high laydown rates, while also delivering a quality mat. A key benefit was the heated centre auger bearing box, patented by Vögele. Located where the mix drops onto the auger, this helps ensure that the surface was heated evenly while no material stuck to it.

The AB 500 and AB 600 extending screeds used feature tamper and vibrators, which allowed the pavers to achieve a high degree of pre-compaction, reducing the number of roller passes required. The

ErgoPlus 3 system on the pavers helped to boost paving efficiency and quality as the more viscous reduced-temperature asphalt had an impact on the compaction process. Meanwhile, the automatic functions for the AutoSet Plus control system allowed the paver operator to save the parameters once they had been used. These were then reused for the next section of the project.

The Hamm compactors had to work particularly closely to the paver
The Hamm compactors had to work particularly closely to the paver

The contractor commented that compared to paving hot, the compaction time is critical as the window available for achieving final density is shorter using reduced-temperature asphalt. This meant that the compactors had to work close to the paver and in short, regular runs.

Using a fleet of compactors comprising tandem rollers and combination rollers, thermal aprons proved helpful to prevent the tyres cooling down quickly. The tunnel bores were paved with asphalt in two sections. For the first short section, the firm adapted the paving process and rolling patterns to suit the ease of compaction. This different way of working was necessary as the reduced-temperature asphalt could be worked for a while and then would suddenly become hard, making full compaction difficult.

The client specified medium-weight rollers for the first pass to compact the combined base and binder courses. A 9tonne Ham DV+ 90i VT-S-type combination roller first used its pneumatic tyres to compact the mix, which is initially susceptible to pushing, generating a dense structure. The drum then ensured evenness. With the roller approaching the paver at an angle, this avoided corrugation. Meanwhile, the traction control system allowed the pneumatic tyres to knead and work the mix without pushing it or tearing it up.

Final compaction was completed by a 4.5tonne HD 14i VO tandem roller and a DV+ 70i-VV-S tandem roller, with the reduced time window meaning that compaction had to be carried out quickly.

For more information on companies in this article

Related Content

  • Emphasis on the new at record-breaking World of Asphalt 2013 & AGG1
    February 21, 2013
    The 2013 World of Asphalt and AGG1 expositions taking place March 19-21 in San Antonio, Texas are on course to be sold out by opening day, setting new records for exhibitor numbers and attendees. Guy Woodford discovers that major construction industry manufacturers will be highlighting new as well as established machine models in their exhibits at the co-located events Covering more than 10,870m² of exhibit space, attendees at the 2013 World of Asphalt and AGG1 shows can expect to find a huge line-up of new
  • Benninghoven | Reducing the carbon footprint in asphalt production
    May 5, 2023
    Working more efficiently with sustainable and economical technologies is the challenge of today and tomorrow. Solutions from Benninghoven lower emissions and secure the future of asphalt mixing plant sites.
  • Topcon’s asphalt logistics solution
    January 19, 2023
    Topcon says that its new Pavelink system offers efficient logistics for asphalt supplies from the plant to the paving operation. Each truck load from the plant is weighed, with data showing the type of mix and also the estimated time of arrival at the paving site.
  • High production paving
    February 28, 2012
    In Germany a high production paving operation has been achieved using the largest machine available on the market. This project is all the more notable as the operation has been carried out in a continuous process, without joints. The Vögele SUPER 3000-2 paver was able to advance continuously at a rate of almost 4m/min. The machine was preceded by a bustle of activity, for no fewer than 24 feed lorries were needed to ensure an uninterrupted supply of mix to the paver, which placed an even asphalt surfacing