Paving lower temperature asphalt

Equipment from Vögele and Hamm has been used to build a carriageway with reduced-temperature asphalt in Germany. The equipment was required for paving a road tunnel in Kahrlsruhe. Tough conditions were applied to paving in the road tunnel under the Kriegsstrasse road.
June 28, 2021 Read time: 4 mins
Two Vögele pavers were used for the low temperature surfacing work on the tunnel in Karlsruhe

To minimise emissions, the contractor employed machines with diesel particulate filters and reduced-temperature asphalts. Using Vögele pavers and Hamm rollers, the consortium handling the work, which comprised Schleith and Züblin, was able to meet the requirements and pave the mix efficiently and in high quality. The road tunnel work forms part of a wider project to improve the centre of Karlsruhe. What was previously a wide road for through traffic is being transformed into a public space for pedestrians, with a landscaped tram track and an avenue of trees featuring cycling facilities. An underground train line is being built while through traffic is being diverted into a 1.6km road tunnel.

The client Karlsruher Schieneninfrastruktur-Gesellschaft (KASIG) wanted to minimise exposure to exhaust fumes for the paving team surfacing the dual tunnel bores of 5.3m and 6.8m width respectively. Only construction machines fitted with diesel particulate filters were allowed to work in the tunnel. The use of low-temperature asphalts was also specified as their paving temperature is 30°C lower than hot asphalt, reducing vapours and emissions as well as exposure to heat. Lower temperature asphalts also have a high resistance to deformation and important advantage for the tunnel with its anticipated heavy traffic volumes.

This choice of mix presented several challenges. Special waxes were used to optimise compaction, even at low temperatures, while the mix had to be paved and compacted as quickly and smoothly as possible. The contractor, Martin Paschmann Asphaltbau, used two SUPER 1800-3i pavers from Vögele and three Hamm compactors: a DV+ 90i VT-S-type combination roller, a DV+ 70i VV-S tandem roller and an HD 14i VO compact roller.

Efficient paving was crucial and the pavers achieved high laydown rates, while also delivering a quality mat. A key benefit was the heated centre auger bearing box, patented by Vögele. Located where the mix drops onto the auger, this helps ensure that the surface was heated evenly while no material stuck to it.

The AB 500 and AB 600 extending screeds used feature tamper and vibrators, which allowed the pavers to achieve a high degree of pre-compaction, reducing the number of roller passes required. The

ErgoPlus 3 system on the pavers helped to boost paving efficiency and quality as the more viscous reduced-temperature asphalt had an impact on the compaction process. Meanwhile, the automatic functions for the AutoSet Plus control system allowed the paver operator to save the parameters once they had been used. These were then reused for the next section of the project.

The Hamm compactors had to work particularly closely to the paver
The Hamm compactors had to work particularly closely to the paver

The contractor commented that compared to paving hot, the compaction time is critical as the window available for achieving final density is shorter using reduced-temperature asphalt. This meant that the compactors had to work close to the paver and in short, regular runs.

Using a fleet of compactors comprising tandem rollers and combination rollers, thermal aprons proved helpful to prevent the tyres cooling down quickly. The tunnel bores were paved with asphalt in two sections. For the first short section, the firm adapted the paving process and rolling patterns to suit the ease of compaction. This different way of working was necessary as the reduced-temperature asphalt could be worked for a while and then would suddenly become hard, making full compaction difficult.

The client specified medium-weight rollers for the first pass to compact the combined base and binder courses. A 9tonne Ham DV+ 90i VT-S-type combination roller first used its pneumatic tyres to compact the mix, which is initially susceptible to pushing, generating a dense structure. The drum then ensured evenness. With the roller approaching the paver at an angle, this avoided corrugation. Meanwhile, the traction control system allowed the pneumatic tyres to knead and work the mix without pushing it or tearing it up.

Final compaction was completed by a 4.5tonne HD 14i VO tandem roller and a DV+ 70i-VV-S tandem roller, with the reduced time window meaning that compaction had to be carried out quickly.

For more information on companies in this article

Related Content

  • Smart road surfacing in a tunnel
    August 19, 2022
    Smart road construction techniques have been used in the widest tunnel in Switzerland. Efficient operation and logistics were required for paving a width of 11.5m in the Gubrist Tunnel and contractor Marti AG Solothurn Bauunternehmung made good use of Vögele’s WITOS Paving Plus technology to optimise its work on the project.
  • Asphalt compaction answer
    February 8, 2012
    A new generation of asphalt compaction technology is coming to market, reports Mike Woof. The market for rubber tyred compactors has grown in recent years, prompting manufacturers to develop a new generation of machines.
  • Caterpillar pavers assist in Malta airport upgrade
    August 23, 2016
    A new Cat AP600F paver used by Maltese contractor Bonnici Brothers has helped with important resurfacing work at Malta’s International Airport. The machine was able to carry out the paving job within a tight time frame, due to its high productivity. The work was needed at the airport as part of a programme to increase its capacity. Malta is seeing growth in passenger numbers at the airport from both business travellers and tourists and there was a need to upgrade the facility. Local contractor Bonnic
  • A new runway surface for a major airport in Indonesia
    August 12, 2020
    Major rebuilding work has been carried out at Minangkabau International Airport (PDG), while the New Yogyakarta International Airport (NYIA) has been built in Indonesia.