New runway for US military airbase in Florida

A new runway surface has now been laid at MacDill Air Force Base in the US, located approximately 6.4km south-west of downtown Tampa, Florida. This facility is the base for the US Air Force’s Air Mobility Command, which provides airlift, special missions, aerial refuelling, and aeromedical evacuation for the armed forces. MacDill is home to 16 KC-135 Stratotankers and three C-37 Gulfstreams, which use the runway every day. At any point, there will be a steady flow of aircraft departing and landing on the
December 7, 2017 Read time: 3 mins
Work carried on roudn the clock during the 96-hour possession

A new runway surface has now been laid at MacDill Air Force Base in the US, located approximately 6.4km south-west of downtown Tampa, Florida

This facility is the base for the US Air Force’s Air Mobility Command, which provides airlift, special missions, aerial refuelling, and aeromedical evacuation for the armed forces. MacDill is home to 16 KC-135 Stratotankers and three C-37 Gulfstreams, which use the runway every day.

At any point, there will be a steady flow of aircraft departing and landing on the base’s sole runway, Runway 4-22. The runway is 2,871m long by 46m wide and usually requires resurfacing every 15 years or so. In 2016 the surface had provided MacDill Air Force Base with 16 years of service and wear and cracks had developed, with even the best pilots finding it rough for smooth landings.

The US$8.1 million runway resurfacing project was awarded to Danner Construction Company, Tampa, FL, as the general contractor on the project. Ajax Paving Industries, North Venice, FL, completed the paving and Turtle Southeast, Largo, FL handled all of the asphalt milling of the old surface.

The overall project is expected to close the runway for about two months. The aircraft traffic was redirected to nearby Tampa International Airport and to Joint Base Charleston to continue the base’s operations.

“The challenge we faced was time,” stated T Allen Gill, general manager with Turtle Southeast, “Our window for milling the entire runway was set at 96 hours.”

To complete the project on time, Turtle assigned much of its equipment and staff. The company has 50 employees and a fleet that includes 13 1252 Roadtec milling machines, 13 service trucks, nine transports, five water trucks and various ancillary vehicles.

The total milling depth of the project was 108mm and required a total of 400 machine hours to complete. Turtle milled the first layer of asphalt at 57mm and then milled the second layer to final grade using a machine control GPS system. The company had 30 employees working on the project and dedicated eight of its Roadtec RX-700e cold planers to ensure the project was done accurately and within the tight timeframe.

Additionally, Turtle Southeast needed to ensure that the milled grade was tight enough so that Ajax could achieve finished paving tolerances of 6.35mm or less to meet FAA standards.

The firm said it ran its milling machines 20 hours/day without a single minute of downtime, with some older units included in that group but proving as reliable as the new ones.

The RX-700e features a 563kW Caterpillar engine and the machines have the exclusive Roadtec Guardian Telematics System, which monitors the machine in real time through a wireless signal, and can address any issues that may arise while the machine works. The telematics system also allows Roadtec service personnel to remotely view the machine in real time. 

“We worked hard on this project and put in some long hours,” stated Gill, who also credits Ajax for its support throughout the project and staging the trucks, so the milling could continue uninterrupted. “When we started the day on Saturday morning there were a total of 130 trucks lined up and waiting to be filled.”

For more information on companies in this article

Related Content

  • Take the lead in milling
    April 30, 2024
    Being an early adopter of machine control systems has been a benefit for a US contractor.
  • Brazil roads repaired with Wirtgen equipment
    November 6, 2018
    A large milling machine from Wirtgen has been used to help repair busy roads in the vicinity of São Paulo in Brazil. The roads provide important transport connections as they link São Paulo with Santos, Brazil’s largest port. The Anchieta-Imigrantes highway system provides the main link between the metropolitan region of São Paulo and the port of Santos, the busiest port in Latin America. Construction of the Anchieta highway began in 1947, with Imigrantes following at the start of the 1970s. Today the Anch
  • Milling machine developments to boost efficiency
    October 20, 2016
    A series of developments in the milling machine market will give customers both greater choice and performance – Mike Woof writes. Competition is heating up in the market for milling machines, which has been dominated for many years by Wirtgen. The German firm still retains a strong share of this market, but is now facing much tougher levels of competition from key rivals, and Atlas Copco, BOMAG, Caterpillar and Roadtec in particular. Meanwhile the market is also seeing the return of another familiar nam
  • Asphalt reinforcement extends road life
    July 12, 2012
    Special reinforcements can extend the life of an old or new road, and also offer environmental benefits. Patrick Smith reports. Asphalt reinforcement can extend the service life of a resurfaced road by a factor of 3-4, says Huesker, developers of the HaTelit range of asphalt reinforcement. Aimed at preventing the propagation of reflective cracking from an old asphalt layer through a new surface course, Huesker claims the formation of reflective cracking is considerably delayed or even completely prevented u