Meeting the challenge of desert runway resurfacing

Ferocious daytime temperatures can provide a tough challenge to construction firms working in desert conditions in Egypt's south. Despite the high daytime temperatures however, Egyptian contractor Orascom has managed to complete an airport project on budget and ahead of schedule, while meeting the client's tight specifications. The firm has just completed the project to revamp Suhag Airport in the south of the country. This airport now features a new runway, taxiways and aircraft hard standing, as well as n
April 13, 2012 Read time: 3 mins
For the asphalt paving duties at the airport Orascom used two Vögele Super 1800-2 finishers working together

Ferocious daytime temperatures can provide a tough challenge to construction firms working in desert conditions in Egypt's south.

Despite the high daytime temperatures however, Egyptian contractor 2414 Orascom has managed to complete an airport project on budget and ahead of schedule, while meeting the client's tight specifications. The firm has just completed the project to revamp Suhag Airport in the south of the country. This airport now features a new runway, taxiways and aircraft hard standing, as well as new perimeter and access roads. Orascom carried out all of this work for its client, the Egyptian Army, which will operate the facility as a joint civil/military airport.

Because the operation has employed an all new fleet of machines combined with the latest construction techniques and tight control of specifications, both structural and finish quality are high. According to one of the project team at Orascom, "This is one of the best runways in Egypt." The one year project to rebuild the runway started at the end of 2008 and took one year to complete, with the perimeter road, taxiways and concrete hard standing having all just been completed in May of this year.

In all Orascom says it paved around 34km of roads at the site, including the perimeter road around the airport. The runway itself measures 3km long by 70m wide while there are three taxiways of 400m each and two concrete aircraft parking aprons measuring 37,900m2 for military aircraft and 40,000m2 for civil aircraft.

The runway features three layers of asphalt, a wearing course, binder course and base course. Under this are two layers of compacted soil and aggregates, built to tight specifications to meet Egyptian requirements and regulations. The aircraft parking areas are made of high quality concrete and were laid in two layers, each 150mm thick and with a 700mm structure of earth and aggregate underneath. After laying the concrete was cut with slots every 5m and these were then filled with sealant.

In all nine 178 Caterpillar 14M graders were employed to lay out the site and also carry out the majority of the earthmoving duties. Egyptian practice is to make extensive use of graders for earthmoving, so these were key prduction tools. For the surfacing two Vögele Super 1800-2 pavers were used to lay the asphalt while the concrete paving for the aircraft parking areas was carried out with a 2395 Wirtgen SP1500.

In addition, 14 single drum soil rollers and twin drum asphalt rollers of various makes were used for compaction of the earth and asphalt surfaces. A 273 Marini Ultima batching plant able to deliver 120tonnes/hour produced the asphalt used on the runway and roadways around the airport, with the high specification concrete coming from an outside supplier.

Because the asphalt and concrete paving work had to be carried out to high specifications, total stations were used to monitor progress throughout and a tolerance of +/- 2mm was allowed on the concrete surface for instance. The concrete paving job was only carried out at night to save the crew from working with the material during the fierce daytime temperatures that can hit peaks of 45ºC.

Orascom had to build five concrete culverts along the length of the runway as well as two for each of the taxiways although these are all for electrical cabling rather than drainage, as rainfall in these desert conditions is a rare event. The new airport is now open to traffic and also benefits from a brand new control tower and terminal building, as well as other new facilities.

For more information on companies in this article

Related Content

  • New bypass for Meghalaya, India
    November 21, 2014
    A new two-lane road has been built in Meghalaya, India, providing a challenging project for the construction team The new road lies at a comparatively high altitude and provides a bypass around Shillong, the capital of Meghalaya and which is one of the smallest states in India. Shillong is located 1,496m above sea level, with the highest point being Shillong Peak at almost 2,000m, and the area has a much cooler climate than the rest of tropical India. Shillong is also only 55km away from Mawsynram, which is
  • New soil compactors round out Atlas Copco’s range
    December 20, 2013
    Atlas Copco has completed the introduction of its fifth generation soil compactor range with the roll-out of the compact CA models. The new Dynapac CA1300 and CA1500 machines share features with the larger machines launched earlier this year, with a focus on reduced operating costs, low operating noise and fuel consumption and ease of servicing.
  • CEMEX in the Sinai
    October 4, 2018
    CEMEX is supplying over 500,000m3 of concrete and approximately 760,000tonnes of cement for major infrastructure projects related to the main canal in Egypt, the Suez Canal. These projects involve the construction of tunnels to connect Egypt’s mainland to the Sinai Peninsula and the development of a commercial seaport. Through a joint venture with Orascom Construction and The Arab Contractors, CEMEX is supplying 350,000m3 of concrete and 160,000tonnes of cement for the construction of two tunnels that ext
  • Universal concrete plant saves time and money
    February 29, 2012
    An Astec Universal concrete plant is said to be proving a real time and money saver for APAC Tennessee, thanks to its fast set-up and reduced cement demand. In March 2011, Astec, of Chattanooga, Tennessee, USA, shipped a new Universal concrete plant to the APAC Tennessee site on President's Island in Memphis, which is central between two APAC projects: a Memphis Airport runway project and an upcoming Tennessee Department of Transportation (TDOT) ramp reconstruction job.