Maputo Airport runway rebuild

Rebuilding work has been carried out on the runway and taxiways at Maputo International Airport in Mozambique. The work was carried out for Aeroportos de Moçambique, with the engineering handled by NACO and US$64 million of funding being suplied by Agence Française de Dévelopement.
March 26, 2019 Read time: 3 mins
Maputo airport now has new runway and taxiway surfaces (image courtesy of Yves Chanoit)

The project was needed as the existing runways were suffering from cracking and had longitudinal profiles that no longer met ICAO requirements. To address these problems, the construction work required laying new asphalt surfaces on the airport’s two runways and taxiways. In addition, the construction team laid 30,000m2 of concrete slab for aircraft parking, as well as building a new fuelling system and installing improved a lighting system on the runways and taxiways.

The project was carried out in partnership with the 2779 Fayat Group, with its contracting division Razel-Bec carrying out much of the contracting work. Fayat provided the Marini-Ermont asphalt plants that produced the asphalt used, as well as the 172 BOMAG milling machines, asphalt pavers and compactors required for the work. The electrical work for the lighting meanwhile was carried out by the specialist contractor SATELEC (FESI).

The airport’s main runway measures 3.6km-long by 60m-wide, while the secondary runway measures 1.4km-long by 36m-wide. Both runways, as well as the taxiway links, had to be resurfaced with minimum 70mm-thick layers.

However flights to and from the airport were not interrupted as the construction work was carried out over a two years period, with much of the milling, paving and compaction duties having been carried out at night.

The existing runway and taxiway surfaces were removed using milling equipment, prior to the paving and compaction machines being used. Two BOMAG BM2000/60-2 milling machines with 2m-wide drums were used to plane the original runway surfaces. These planers removed the old surface layers in one pass, using Trimble total stations supplied by SITEC to provide accurate guidance and optimise the cutting process.

 

The contracting team used then BOMAG BF800C pavers featuring S50 screeds set to widths of 2.5-7.5m, with the machines working in echelon to allow hot to hot paving for better bonds. Compaction was carried out meanwhile using BOMAG BW141 AD-50 and BW202 AD-50 tandem rollers and BOMAG BW24 RH pneumatic tyre rollers.

The milled cuttings were not used as aggregates for the asphalt mix applied to the runway surfacing. However, this material was recycled and was used instead for the airport’s perimeter road as well as in the surface course for the shoulders of the secondary runway.

The asphalt was produced using Marini-Ermont TSM15 and TSM17 plants and delivered to the pavers using a fleet of large tipper trucks. The plants delivered three asphalt grades for the base, binder and surface courses, with the last utilising advanced polymer modified bitumen (PMB) technology.

 

For more information on companies in this article

Related Content

  • Meeting the challenge of desert runway resurfacing
    April 13, 2012
    Ferocious daytime temperatures can provide a tough challenge to construction firms working in desert conditions in Egypt's south. Despite the high daytime temperatures however, Egyptian contractor Orascom has managed to complete an airport project on budget and ahead of schedule, while meeting the client's tight specifications. The firm has just completed the project to revamp Suhag Airport in the south of the country. This airport now features a new runway, taxiways and aircraft hard standing, as well as n
  • Dual layer, hot to hot paving at German airport
    August 18, 2015
    An airport in Germany has seen the use of very innovative asphalt paving techniques, with the use of dual-layer, hot-to-hot working. The method was used to meet a very tight schedule for the runway rebuilding work, while also delivering the high quality required. Two InLine Pave trains from Vögele were used at Rostock-Laage Airport to lay a new surface and binder course. The operation was innovative as the process used both hot-to-hot, echelon paving as well as dual layer, hot-on-hot working. Using this
  • Runway rebuild for key Bulgarian airport
    August 21, 2013
    Varna Airport in north-east Bulgaria provides an important international link for the country, with a runway rebuild helping improve capacity. The airport is of particular importance for Bulgaria’s tourist trade as it provides a major connection for visitors to the Black Sea coast. And the reconstruction work at Varna Airport’s only runway will ensure the facility is able to handle the area’s increasing visitor numbers. The project had to be carried out quickly and efficiently to prevent delays to f
  • Rebuilding the busy Frankfurt Airport in Germany
    September 12, 2017
    Handling up to 450 take-offs/day, Runway West is Frankfurt Airport’s busiest runway. Over 50% of the aircraft taking off from the airport uses Runway West, and a point worth noting is that this German airport is one of the busiest in Europe. In 2016, Frankfurt Airport handled nearly 61 million passengers, surpassed by Schiphol in Amsterdam and Charles de Gaulle in Paris, Europe’s third and second busiest airports respectively. Meanwhile London’s Heathrow remained Europe’s busiest airport