An innovative solution was put forward to support slip roads on a Dutch motorway. Patrick Smith reports. The 2010 opening of the A7 motorway extension on the southern ring road of the city of Sneek, The Netherlands, brings an end to local traffic misery. By using innovative Tensar Geocell Foundation Mattress technology over weak estuarine clay, MNO-Vervat Noord, the main contractor, constructed a key junction and its slip roads in weeks instead of months, with considerable cost savings.
May 9, 2012 Read time: 3 mins
The A7 Motorway at Sneek, Friesland, Netherlands, and the new Lemmerweg interchange

An innovative solution was put forward to support slip roads on a Dutch motorway. Patrick Smith reports.

The 2010 opening of the A7 motorway extension on the southern ring road of the city of Sneek, The Netherlands, brings an end to local traffic misery. By using innovative 340 Tensar Geocell Foundation Mattress technology over weak estuarine clay, MNO-Vervat Noord, the main contractor, constructed a key junction and its slip roads in weeks instead of months, with considerable cost savings.

The conversion of the ring road around Sneek to a new highway, with replacement of the signal-controlled junctions for client Rijkwaterstraat, the Province of Friesland, City of Sneek, began in 2007, but a problem with the soil was encountered at the Lemmerweg junction in 2009. A 2.5m thick layer of weak peat and soft clay was found below the proposed four slip roads connecting to an overhead roundabout over the A7. In addition, the slip road ramps up to 6m high with a vertical face, and exerting considerable load, meant that site access would have been difficult for heavy construction plant.

"To instigate soil improvement measures over such a large area would have been costly, and the conventional heavy sheet piling techniques would have held the project up by several months. The project budget and schedule would have been under threat," said Theo Huybregts, of Tensar International.

The consultant engineers, Ingenieursbureau Geologics and Fugro Ingenieursbureau (Regio Noord), worked with the Tensar design team to propose a different approach to the contractor. This comprised installing a load-bearing 1m thick Tensar Geocell Foundation Mattress over a 6,000m2 area of weak clay to stabilise the embankment foundations and to reduce lateral movement. Controlling ground movements was particularly important because the existing ring road, which is located only 1m from the vertical face of the new ramps, had to remain open to normal traffic throughout the construction.

Filled with aggregate, the Tensar Foundation Mattress was installed in 13 working days to provide a stiff layer for the foundations, which allowed access for plant and facilitated drainage from the road construction above. In addition, the Geocell Mattress structure provided the ideal base for Tensartech TR2 steel mesh-faced reinforced soil-retaining walls to the motorway embankments, which were built safely without scaffolding or disturbance to the nearby live traffic.

Meanwhile, the 1589 Maccaferri erosion protection systems, Enkamat and Biomac, have been used to prevent soil erosion and stabilise steep cuts and embankments on the M1 motorway widening project in the UK (see separate story).

German company 3831 NAUE says it has carried out the first public testing of geogrid-reinforced stone columns with a 2.2tonne vehicle standing on the structures.

The company worked with Professor Karl Josef Witt and Mary Noack from Bauhaus University Weimar, Germany, to create the 40cm³ columns.

The geogrid used in the experiment was NAUE's Secugrid, and the four columns were constructed in front of an audience of some 120 at the university.

Crushed gravel of 8-32mm was poured into the formwork with NAUE Secugrid 40/40 Q1 geogrid inserted every 10cm to create three layers of reinforcement.

A forklift placed the vehicle on the columns, and two television crews captured what happened when the forms were removed and Secugrid's ability to absorb such direct forces was put to the test. The reinforced columns held.

For more information on companies in this article

Related Content

  • Seal of approval for Sika
    June 22, 2012
    Skikaflex Construction by UK-based Sika was chosen by Skanska Balfour Beatty Joint Venture to seal movement joints during the widening of one of Europe’s busiest motorways. The M25, also known as the London Orbital, handles around 200,000 vehicles every day on its busiest sections. Its widening between junctions 27 and 30 is said to be delivering much needed extra capacity to tackle congestion and improve journey times.
  • Plants for Kazakhstan
    November 28, 2022
    CITIC Construction is now using no less than five Lintec CSM4000 asphalt mixing plants for road construction works in Kazakhstan. The Chinese contractor said that these units were selected as they met its needs. The containerised design of the Lintec CSM4000 asphalt plant allows ease of transport, fast installation and also ensures protection for core components.
  • Tensar wins Chinese patent cases
    March 20, 2012
    International ground stabilisation specialist, Tensar has successfully defended its TriAx product range against several Chinese patent infringements.The TriAx geogrid, patented in many countries around the world by Tensar for use in ground stabilisation, road, rail and other applications, has received many awards for innovation and has achieved considerable commercial success since its introduction a few years ago."Several Chinese manufacturers and their distributors attempted to take advantage of this succ
  • Using technology so assess road surface quality
    April 4, 2014
    Advances in survey technology and the evolving face of road procurement are driving demand for highway condition data. Mark Thomas, infrastructure services manager at Fugro Aperio writes how surveys of new roads can improve long-term quality While a growing suite of non-intrusive testing, measurement and survey technologies are widely used to target highway repairs and to determine asset management strategies, the use of these powerful tools remains patchy in the early stages of the infrastructure life cycl