Indian airport revamp sets record

The use of machines from Dynapac has helped deliver upgrade work at Ahmedabad Airport in India, while setting production records
September 2, 2022 Read time: 4 mins
High paving quality was achieved at the airport through the use of equipment from Dynapac

The Sardar Vallabhbhai Patel International Airport is the busiest airport in India’s Gujarat State. The facility handled over 200 flights/day during the pre-COVID-19 period and as air traffic resumes, it is regaining its status as an important and bustling hub for both domestic and international flights.

However, the high level of traffic as well as the local climate have made it necessary for the facility to benefit from a number of improvements. The upgrade work will allow the airport to keep up with the growing post-pandemic travel demands.

Due to the resurgence of travel in 2022, the challenge of resurfacing the runway had to be faced. But this work had to be carried out without impacting on flight operations. The improvements form part of a wider programme as India’s airports are now seeing rapid growth in passenger numbers and flights, which is being reflected in considerable investment in aviation infrastructure.

To ensure the work was carried out to the necessary quality requirements and within the strict timeframe, the project at Ahmedabad was carried out using the latest technology and with the involvement of several leading companies.

Ahmedabad Airport features a single runway, 5/23, which is 3,489m long and 46m wide and surfaced with concrete and asphalt. The runway upgrade project has included the addition of a new overlay for the runway, strip grading and slope assessment and grading of the runway end safety area. It has also included the construction of new stormwater drains and the reinstallation of signs and markings.

The runway project was completed with one million safe working hours and with the help of 600 personnel as well as the use of over 300 pieces of equipment.

The runway resurfacing project was originally planned to be carried out in two phases, with the work taking 36 months to complete. However, the estimated time required was then revised at 90 days due to the use of modern equipment. And when the contracting team began working, progress was so good that the resurfacing was handled in just 75 days.

Aviation infrastructure specialist AICPL played a key role in fulfilling the project. Together with Adani Airport Holding Limited (AAHL), AICPL only used nine hours of Notice to Airmen (NOTAM) daily. During the 75 days of re-carpeting work, the team kept the runway open for 160 daily flights for almost 15 hours/day.

AICPL, along with Dynapac, was able to set a record. The resurfacing of the runway was completed in record time, an all-time best amongst brownfield runways in India. It is estimated that the amount of asphalt laid during the re-carpeting of the runway was equivalent to a 200km stretch of road, and the concrete used for the runway drainage system was enough to build a 40-storey structure.

In order to complete the runway in record time, Dynapac’s full fleet of equipment was used. This included a CP275 PTR rubber tyred compactor, CC425 tandem rollers and a SD2530CS paver. During the project, the company also achieved the milestone of laying 4,178tonnes of asphalt using Dynapac paving equipment in just 9 hours.

With the existing airports in the PPP model and the Indian Government's plan to privatise over 22 airports by 2025, AICPL envisions more opportunities in the aviation sector.

Kritarth Raja, chairman of AICPL was impressed by the cooperation with Dynapac and their contribution to achieving the world record. A key factor was the use of Dynapac paving equipment.

The Sardar Vallabhbhai Patel International Airport in Ahmedabad has been revamped. Along with the new runway, there are many new additions such as an EV charging station, a new cargo terminal and a new airfield lighting system.

Dynapac played a significant role in upgrading the runway and the Ahmedabad airport. The resurfacing work of a 3.5 km stretch with a 45m width was completed in record time.

The uni-directional cross fall of the runway was changed to a bi-directional slope. There’s now an 8km drain parallel to the runway on either side with 05 taxiways and 02 rapid exit taxiway stubs. The runway centreline lights offer a provision for touchdown zone lighting that illuminates Runway 23 for better visibility.

A total of 300 construction equipment units were deployed for the project, including pavers, excavators, rollers, dumpers, bowers, mechanical sweepers, transit mixers, and more.

For more information on companies in this article

Related Content

  • Highway developments in India
    April 10, 2012
    A major highway deal has been agreed for a road project in Gujarat, India, worth an estimated US$810.8 million. It will be handled under the build, finance, operate and transfer basis and will involve upgrading and widening to six lanes a 102km section of National Highway 8 (NH-8) from Ahmedabad-Vadodara. The project also includes upgrading 92km of the existing Ahmedabad-Vadodara expressway. Work is expected to take three years to complete, and the 25-year concession deal for the project has been a
  • It’s in with the new for asphalt plants
    April 4, 2013
    A leading asphalt plant manufacturer is playing a key role in the upgrade of a major European airport, while another is said to have created one of the most modern plants in Europe. Meanwhile, a host of new plants and plant concepts have been, or are about to be, unveiled. Guy Woodford reports Intrame says its ultra-mobile UM-280 asphalt plant has played a key role in the resurfacing of the runway and taxiways at Gatwick Airport in southern England – the busiest single runway airport in the world. Around 35
  • More Saudi airport capacity
    October 12, 2012
    A major expansion programme is underway at King Abdulaziz International Airport in Jeddah, Saudi Arabia. The work started in the third quarter of 2006 and is due for completion in 2015, with the construction activity being carried out in three main stages. Once the work is complete the airport will be able to handle up to 80 million passengers/ year, compared with 13 million/year before construction commenced. The project also includes three new terminal buildings and a high-speed rail link, as well as airf
  • Vögele Super 1803-3i wheeled paver rides high in the Swiss Alps
    December 18, 2017
    Asphalt paving is a challenge in the rough terrain of the Swiss Alps and nowhere more so than in the mountain village of Castiel. Extreme slopes, narrow roads and steep precipices place demands on the paving team and machinery. In the town of Castiel, in the Arosa district of the canton Graubünden, contractor HEW Bauunternehmung opted to use Vögele’s Super 1803-3i wheeled paver for rehabilitation of the combined base and surface course on a farm track. The site is around 1,200m above sea level and an