Skip to main content

Improvements to China's first desert expressway

The latest asphalt paving technology is now available and being utilised in novel ways to build and improve roads, often in challenging applications. Tough working environments, strict project deadlines and precise quality requirements are all posing engineering challenges for road construction projects around the world. For a number of asphalt paving applications, novel approaches and new technology are being employed to deliver projects on time and within specifications. In China, improvements to the coun
April 4, 2013 Read time: 4 mins
China's desert expressway is providing a tough construction challenge

The latest asphalt paving technology is now available and being utilised in novel ways to build and improve roads, often in challenging applications. Tough working environments, strict project deadlines and precise quality requirements are all posing engineering challenges for road construction projects around the world. For a number of asphalt paving applications, novel approaches and new technology are being employed to deliver projects on time and within specifications.

In China, improvements to the country’s first desert expressway are providing an engineering challenge for the contractor working on the project. This route runs through the remote Ordos Desert (also known as the Mu Us Desert) and links Yulin city with Manggaitu on the border between Shaanxi Province and Inner Mongolia. The Yulin-Jingbian Expressway is 160km long and is being resurfaced by the Second Expressway Engineering Bureau of 2661 China Communications Construction Company (CCCC). The two-year paving project was awarded by the Shaanxi Expressway Group in the northwest of China and will upgrade the expressway, first built in 2003.

The road provides an important route for trade and transport in the area and the 10-year old surface was in need of improvement due to the increasing volume of traffic and heavy vehicles using the route. The main section of the highway stretches some 116km and has three connection lines in Yulin, Hengshan and Jingbian, adding a distance of 18km to the highway.

Work on the upgrade is underway and the contractor is using four machines supplied by 2394 Volvo Construction Equipment; two Volvo P8820 tracked asphalt pavers, two Volvo DD118 double smooth drum rollers. The expressway is 24m wide while a green strip of vegetation has been designed that runs parallel to the road.

This green area provides a key environmental benefit as it protects the road surface from sand being blown onto the asphalt by the frequent gale-force winds that ravage the desert. To block off the elements, this area covers more than 100,000m2 and is being artificially seeded and planted with more than 60,000 trees, 28 million shrubs, flowers and grasses.
For CCCC, meeting the strict project deadlines is crucial. Bai Feiyang is CCCC’s section chief manager of operations and he said, “We are up against the clock on this project. Working in the middle of the desert can sometimes cause logistical difficulties and we have less than two years to complete the asphalt paving.”

The quality of the paving has to pass the Shaanxi Authority Road Bureau acceptance test at handover and again after 10 months of operation. “Equipment reliability is a key factor for paving quality since frequent downtime can result in the need for re-paving,” added Feiyang.

The Volvo DD118 compactors have been specifically built to handle diverse weather conditions, which suits the application in the Chinese desert. Meanwhile the P8820 paver is powered by a 182kW engine, which allows it to climb steep dunes. Maintenance of the machines is important and the dealer for the region, Xi'an Tongguan Construction Machinery (XATG), provides a service plan for all Volvo CE machines onsite. In addition, a representative from the dealership works with the construction team to ensure the machines’ productivity and efficiency.

As well as the pavers and compactors, two Volvo EC210B crawler excavators are also being used to deliver materials to the site and are heavily relied upon for the transportation of supplies to and from the team’s location. About 120 employees work at the nomadic construction site, moving up and down the desert highway.

The working conditions can be particularly problematic, giving rise to a number of challenges.

“The wind and dust reduce our visibility, which is hazardous because this job is all about creating a smooth and straight surface,” said Feiyang.

For more information on companies in this article

Related Content

  • Volvo CE’s arduous Andes assignment
    August 20, 2013
    Volvo Construction Equipment is working in some of the world’s most treacherous terrain to construct a high-speed road link across the Andes Mountains. A fleet of 60 Volvo Construction Equipment (Volvo CE) road-building machines is being used to construct a 140km highway across the Andes Mountains, from Bucaramanga, Colombia’s eighth largest city, to Cucuta on the border – providing the country with a much-needed high-speed link with Venezuela. Tasked with this huge undertaking is innovative Colombian hi
  • A new runway surface for a major airport in Indonesia
    August 12, 2020
    Major rebuilding work has been carried out at Minangkabau International Airport (PDG), while the New Yogyakarta International Airport (NYIA) has been built in Indonesia.
  • Fast roller paver from Terex
    October 12, 2012
    Terex says that its latest Bid-Well 6500 Automatic Roller Paver delivers high performance concrete paving for slabs up to 610mm thick. The machine benefits from a heavy-duty frame design and an 8.9tonne operating weight in standard form. The frame can be configured to meet paving widths from 7.3-18.3m wide, suiting applications in a range of duties including airport runways, taxiways and aprons. Capable of width changes in a matter of hours, the roller paver offers an alternative to slipform pavers for thes
  • Sealing the world's longest tunnel
    April 10, 2012
    Infrastructure construction in China is booming as never before, but sealing the world’s longest immersed tunnel is a technically complex engineering project. The impressive Hong Kong-Zhuhai-Macau fixed link project in China includes an immersed tunnel with a record-breaking length of almost 7km. In 2009 construction began on a project to link the island of Hong Kong with Macau and the mainland Chinese city of Zhuhai. The link will be one of the region’s most technically complex engineering projects ever. I