Hot-to-hot paving upgrades Bremen City Airport runway

A new high quality runway surface has been laid at Bremen City Airport. This has provided a much-needed replacement at the airport as the old runway was laid over 20 years ago and was suffering from cracking and potholes. Laying the new surface required the airport to be closed, with the work having to be carried out in a tight time schedule. Contractor Heitkamp Erd- und Straßenbau was brought in to carry out the work as the firm had experience in runway rehabilitation projects having carried out pavemen
September 30, 2013 Read time: 3 mins
Efficient fleet operation meant that Bremen City Airport had its runway repaved with a high quality surface within the tight closure period

A new high quality runway surface has been laid at Bremen City Airport. This has provided a much-needed replacement at the airport as the old runway was laid over 20 years ago and was suffering from cracking and potholes.

Laying the new surface required the airport to be closed, with the work having to be carried out in a tight time schedule. Contractor Heitkamp Erd- und Straßenbau was brought in to carry out the work as the firm had experience in runway rehabilitation projects having carried out pavement rehabilitation at Zweibrücken Airport.

At Bremen the contractor’s first task was to use its 2395 Wirtgen milling machines to prepare the 45m wide by 2,045m long runway. The company employed five large Wirtgen W220 planers as well as two smaller W150 mills to remove the top 120mm of the surface, which was carried out successfully in 30 hours.

The paving work required effective logistics, with up to 60 trucks being used to deliver a continuous flow of asphalt to the site from the asphalt plant. Some 19,000tonnes of binder course was used, with this being laid to a depth of 80mm by three 1194 Vögele pavers, two Super 1800-2 models as well as a larger Super 2100-2. All three pavers feature AB600 screeds with a high compaction pressure bar system and the machines were operated in echelon, to allow hot-to-hot paving in two sets of three strips.
The combination of the compaction effect from the screed, the hot-to-hot joints and also the use of the Vögele 3D Navitronic Plus control system, helped ensure a good quality binder layer. The sophisticated Navitronic system used existing survey data for paving the two inner strips, optimising the profile accuracy as well as ensuring the surface was even. The system can control paving width, layer thickness and the longitudinal direction automatically.

The contractor then used six Vögele pavers to lay the wearing course in echelon, a combination of Super 1800-2 and Super 2100-2 machines. These laid the 40mm thick layer in paving widths of 7.5m, again using the hot-to-hot method. The high quality paving requirement called for the contractor to achieve an evenness of 3mm over a longitudinal distance of 4m, as well as to locate the necessary rain channels with high precision.
To ensure rainwater can drain effectively, the inner strips were paved with a transverse slope of 1.5%, while the outer strips were provided with a slope of 1%. All six of the pavers used Vögele’s Niveltronic Plus system for automated grade and slope control, with Multiplex Skis featuring sonic sensors to calculate a mean value and level out any irregularities in the base.

Providing a constant flow of asphalt into the paver helps with continuity and quality so the contractor employed material feeders for this task. Two of the latest Vögele MT3000-2 offset material feeders and two of the earlier Vögele MT1000-1 feeders were employed for this task. The MT3000-2 feeder can supply 1,200tonnes of mix/hour and also holds up to 40tonnes of material, allowing it to supply up to two pavers at a time using its pivoting offset conveyor.

Using this fleet of equipment the contractor was able to remove the old runway surface and replace it with a new high quality pavement that met the required specifications within a 149 hour closure window, just as planned.

For more information on companies in this article

Related Content

  • Maputo Airport runway rebuild
    March 26, 2019
    Rebuilding work has been carried out on the runway and taxiways at Maputo International Airport in Mozambique. The work was carried out for Aeroportos de Moçambique, with the engineering handled by NACO and US$64 million of funding being suplied by Agence Française de Dévelopement.
  • Istanbul’s new airport benefits from Wirtgen Group machines
    November 22, 2017
    Construction of Istanbul’s new airport facility is benefiting from the use of a large fleet of machines from the Wirtgen Group. When it is complete, this will be the world’s largest airport and will be able to handle 150-200 million passengers/year as well as 6 million tonnes of freight/year. This will make the facility substantially larger than the world’s current largest airport, the Hartsfield-Jackson Atlanta International Airport, which handles around 105 million passengers/year.
  • Wirtgen group machines flying high at İstanbul Yeni Havalimanı
    May 21, 2018
    Plant and machines from Wirtgen, Vögele, Hamm and Benninghoven are playing a vital part in the construction of Istanbul’s new airport . Istanbul’s new airport is Turkey’s biggest infrastructure project ever. It is also expected to become the world's largest airport by estimated passenger numbers.
  • Paving giant in action
    February 20, 2012
    The project to build a new orbital motorway to bypass the Spanish city of Barcelona has benefited from the use of the world's largest asphalt paver. This represents one of the first jobs in Europe for the power paver, Vögele's SUPER 3000-2, which was first launched at the Bauma exhibition in Munich in 2010.