Highway widening project for the US

A highway widening project in the US state of New Hampshire is being assisted by the use of a gravity-fed asphalt paver. The widening work is being carried out as part of an upgrade for a 32km stretch of I-93, which was started eight years ago. The work is being carried out for the New Hampshire Department of Transportation (NHDOT) on a section of the highway between Exits 1 and 5 from the Massachusetts Stateline to Manchester, NH. According to NHDOT, the project involves widening I-93 from two lanes in
April 19, 2018 Read time: 4 mins
The Roadtec gravity-fed paver receives the material from a Shuttle Buggy
A highway widening project in the US state of New Hampshire is being assisted by the use of a gravity-fed asphalt paver.


The widening work is being carried out as part of an upgrade for a 32km stretch of I-93, which was started eight years ago. The work is being carried out for the New Hampshire Department of Transportation (NHDOT) on a section of the highway between Exits 1 and 5 from the Massachusetts Stateline to Manchester, NH.

According to NHDOT, the project involves widening I-93 from two lanes in each direction to four lanes in each direction. This will be from Salem, NH at the Massachusetts/New Hampshire state line heading northerly through Salem, Windham, Derry and Londonderry, and into Manchester, ending at the I-93/I-293 interchange. The US$750 million project was started in 2008 and is due for completion at the end of 2019. The first phases focused on clearing the land adjacent to the interstate, as well as building bridges, on- and off-ramps and park-and-ride facilities.

"We've joined the Rebuilding I-93 project at its final phase where we'll be completing the asphalt paving on the remaining 12miles (19km) of the project," said Amy Charbonneau, Continental Paving, Londonderry, New Hampshire. "We are the subcontractor on four separate contracts with three general contractors. The GCs are Audley Construction out of Bow, NH; Weaver Brothers Construction, based in Bow, NH; and Coleman Construction from North 2329 Conway, NH."

The first two contracts are for Audley Construction and are located on the southern section of the project. On these jobs, Continental Paving's contract includes some reclaiming, milling, onsite crushing, and the asphalt paving. The first Audley contract calls for approximately 126,300tonnes of asphalt. The total contract for Audley as a GC is valued at $49 million with a completion date of October 2019.

"We have used our 1252 Roadtec Stealth Paver with a Carlson screed for 90% of the work on the project, and when it wasn’t being used it was the Roadtec RP-190e rubber-tyred asphalt paver with the same MOBA-Matic II grade and slope levelling system on the machine," Charbonneau said. "The highway through  all four contracts is being reconstructed from the base up, and we plan on paving the entire main line portion from gravel up with the Stealth Paver."

The Roadtec RP-100e Stealth Paver is a low-maintenance gravity-fed paver specifically for operation with a material transfer vehicle. Continental Paving uses a Roadtec SB-2500e Shuttle Buggy to pair up with its Stealth Paver.

Charbonneau believes the gravity-fed paver offers benefits, "We do not track fuel costs/paver, but we see that the Stealth is saving on fuel and the paver is going to save us approximately 50% in wear part replacement cost on a yearly basis, due to the reduced number of moving parts."

The second contract with Audley Construction has a $62 million value and requires placement of 104,600tonnes of asphalt and a completion date of September 2020. As with all the contracts, Continental is paving from the gravel up. "Our paving calls for the placement of three lifts of HMA to reach the finished surface," stated Charbonneau. "There are different mix combinations in different sections, to help the state test paved surface longevity. "

With its fast paving rate, Continental was able to achieve a record night with the Roadtec RP-100e Stealth Paver. The machine placed 3,700tonnes of asphalt at 32mm by the morning during an 11-hour shift.

The third contract for the contractor is for Weaver Brothers Construction. On their site, Continental Paving will be milling and paving. The total contract awarded to Weaver Brothers was for $34 million and consists of approximately 79,400tonnes of asphalt with a completion date of August 2019.

The fourth contract for Continental Paving requires milling and paving and the $45.9 million contract calls for approximately 103,730tonnes of asphalt, with a completion date of October 2019. Throughout all four contracts a range of equipment is being used. A Roadtec SX-8e soil stabiliser-reclaimer was tested when the contractor had to reclaim a section of the existing highway, which required cutting depths of 305-457mm.

A half-lane Roadtec RX700e milling machine was used for tie-ins and shoulder slope adjustments for lane shifts. The mill also plays a role when bringing the lanes of traffic back from their shifts and swaps while making the surface ready and smooth for the wearing course. For some sections where removal of existing highway was the goal the company did mill off a majority of the asphalt for use as RAP in new asphalt production.

For more information on companies in this article

Related Content

  • Concrete paving a smoother surface using machine control technology
    May 17, 2017
    Innovative technology has been used to deliver a smooth concrete road surface on a busy stretch of highway in Nebraska. Much-needed work on a busy section of Interstate 80 has been carried out in Nebraska to improve the road surface. This is one of the most important highways in the US, providing a link that stretches right across the country between the east and west coasts. This busy highway carries a high percentage of heavy truck traffic as it is a vital transport route. However this constant flow of la
  • Airport's high demands on asphalt and concrete techniques
    July 11, 2012
    Airport runway, taxiway and parking areas make high demands on paving requirements, both with concrete and asphalt techniques. Mike Woof reports. High quality surface finishes are required in airport environments for runways, taxiways and aircraft parking areas. Because of the speed at which aircraft take off and land and the massive forces exerted due to the weight of the aircraft, particularly during landing, runway structures need to be incredibly strong. The surfaces also have to be constructed to very
  • Milling accurately for construction efficiency
    May 16, 2014
    The two-way flow of machine data is a crucial issue for machine optimisation and new telematics systems are becoming increasingly important in construction Telematics systems can be tapped into by machine control technologies to allow greater integration of the machine as a data provider within an operation. And for certain production machines that feature wear-intensive operation, telematics systems are becoming a vital tool for minimising maintenance costs by scheduling service intervals, maximising u
  • Long life asphalt paving reduces maintenance
    April 11, 2012
    Contractor FM Conway is working on a three year contract with Dover Harbour Board to reconstruct and resurface busy access routes and large vehicle parks within the port. One of the major factors for this contract being awarded was the company's strong green credentials. The contract is based around small and large individual paving projects within the Eastern Docks, which can range in time scales from three weeks to six months. The first phase of work, which started in early May, was to fully reconstruct