Helsinki Airport is benefiting from a new runway surface

Finland’s main international airport, serving the capital Helsinki, is now benefiting from a runway resurfacing project. The rehabilitation work has been needed for one of the airport’s three runways due to a number of age-related defects. Helsinki Airport processes some 17 million passengers/year and due to a combination of the often severe winter weather and the heavy aircraft traffic, the runway condition was not of the standard required. Resurfacing work was scheduled by FINAVIA, with a budget of some
February 23, 2018 Read time: 2 mins
Finnish contractor Lemminkäinen used three W 220 large Wirtgen milling machines for the job
Finland’s main international airport, serving the capital Helsinki, is now benefiting from a runway resurfacing project. The rehabilitation work has been needed for one of the airport’s three runways due to a number of age-related defects. Helsinki Airport processes some 17 million passengers/year and due to a combination of the often severe winter weather and the heavy aircraft traffic, the runway condition was not of the standard required.

Resurfacing work was scheduled by 6704 FINAVIA, with a budget of some €11 million, while the total area to be rehabilitated 121,000m². The runway rebuild work was planned in stages, so as to mill off 250mm of asphalt from the runway surface, but with this work being handled in three passes. This method was required in order to separate the reclaimed material into different grades. The first stage of the planning job was to remove a 100mm layer, with a second stage milling away a 50mm asphalt layer, followed by the third phase to remove the final 100mm thickness.

The work was carried out by the Finnish contractor 3064 Lemminkäinen, which has a fleet of 2395 Wirtgen milling machines. The firm used three W 220 large milling machines for the job, allowing it to remove the layers within the tight timeframe required.

For more information on companies in this article

Related Content

  • Hamburg-Finkenwerder airport has new runway surface
    August 21, 2013
    Hamburg’s Finkenwerder airport is now benefiting from a new runway surface following work carried out by contractor KEMNA BAU. The company recently used machines from Dynapac to resurface 36,000m2 of the runway track in Hamburg-Finkenwerder, a facility used by Airbus. The airport handles around 10-15 take-offs and landings/day when aircraft are either undergoing flight testing or being delivered to customers, as well as for deliveries of components by transport aircraft. The project was tricky as the
  • Runway road rehabilitation
    February 29, 2012
    The Frankfurt/Hahn Airport is benefiting from an upgrade to its facilities as well as its road links that will help cope with increased traffic. The site was commissioned as a civilian airport in 1993 and is one of the fastest growing German airports as well as being the fourth largest cargo airport in Germany.
  • Recycling advances from Wirtgen
    June 18, 2012
    German firm Wirtgen is retaining its lead in road recycling technologies – Mike Woof writes Tests on cold recycling with a new layer thickness using Wirtgen's sophisticated WR 4200 machine have shown impressive results according to the firm. The road construction and traffic authority Landesbetrieb Mobilität (LBM) Cochem-Koblenz commissioned a pilot project as part of its plan to optimise the cold in-place recycling process (CIR). The aim was to examine the extent to which the layer thickness can be reduced
  • Italian highway benefits from road recycling job
    October 3, 2014
    The latest equipment from Wirtgen has been used to recycle a stretch of Italy’s busy A4 Autostrada, one of the country’s most important highways. The Wirtgen machine was the first WR250 recycler/reclaimer to be delivered to Italy and was put to work on the A4 Turin-Trieste highway where it proved highly productive. The A4 Autostrada runs 522km from Turin to Trieste via Milan and Venice across northern Italy from west to east. The A4 is divided into five segments, the Turin-Milan, Milan-Brescia, Brescia-Pad