Helsinki Airport is benefiting from a new runway surface

Finland’s main international airport, serving the capital Helsinki, is now benefiting from a runway resurfacing project. The rehabilitation work has been needed for one of the airport’s three runways due to a number of age-related defects. Helsinki Airport processes some 17 million passengers/year and due to a combination of the often severe winter weather and the heavy aircraft traffic, the runway condition was not of the standard required. Resurfacing work was scheduled by FINAVIA, with a budget of some
February 23, 2018 Read time: 2 mins
Finnish contractor Lemminkäinen used three W 220 large Wirtgen milling machines for the job
Finland’s main international airport, serving the capital Helsinki, is now benefiting from a runway resurfacing project. The rehabilitation work has been needed for one of the airport’s three runways due to a number of age-related defects. Helsinki Airport processes some 17 million passengers/year and due to a combination of the often severe winter weather and the heavy aircraft traffic, the runway condition was not of the standard required.

Resurfacing work was scheduled by 6704 FINAVIA, with a budget of some €11 million, while the total area to be rehabilitated 121,000m². The runway rebuild work was planned in stages, so as to mill off 250mm of asphalt from the runway surface, but with this work being handled in three passes. This method was required in order to separate the reclaimed material into different grades. The first stage of the planning job was to remove a 100mm layer, with a second stage milling away a 50mm asphalt layer, followed by the third phase to remove the final 100mm thickness.

The work was carried out by the Finnish contractor 3064 Lemminkäinen, which has a fleet of 2395 Wirtgen milling machines. The firm used three W 220 large milling machines for the job, allowing it to remove the layers within the tight timeframe required.

For more information on companies in this article

Related Content

  • Successful resurfacing at New York's JFK Airport
    February 8, 2012
    A huge logistics operation has been carried out successfully at New York's JFK Airport. One of the busiest runways at one of the world's busiest airports is now open to air traffic again, following a 120 day closure for resurfacing.
  • Successful resurfacing at New York's JFK Airport
    May 3, 2012
    A huge logistics operation has been carried out successfully at New York's JFK Airport. One of the busiest runways at one of the world's busiest airports is now open to air traffic again, following a 120 day closure for resurfacing.
  • Wirtgen machines at Beijing’s new airport
    June 10, 2019
    Slipform pavers from Wirtgen have played important roles for the Beijing New International Airport project. The four Wirtgen slipform pavers have been used for the construction of the apron area for the new Chinese airport.
  • Wirtgen milling machines and soil stabilisers land in Sardina
    July 26, 2016
    Wirtgen cold milling machines recently demonstrated their ability on runway rehabilitation work at Alghero-Fertilia Airport in Sardinia. Alghero-Fertilia Airport, about 8km northwest of Alghero, is one of three commercial airports on the Italian island. Built as a military airport in the late 1930s, Alghero-Fertilia still occasionally serves this purpose today. It is also a major hub for low-cost carriers that ferry many of the annual 1.7 million passengers who pass through the airport. Summer tourist mo