Helsinki Airport is benefiting from a new runway surface

Finland’s main international airport, serving the capital Helsinki, is now benefiting from a runway resurfacing project. The rehabilitation work has been needed for one of the airport’s three runways due to a number of age-related defects. Helsinki Airport processes some 17 million passengers/year and due to a combination of the often severe winter weather and the heavy aircraft traffic, the runway condition was not of the standard required. Resurfacing work was scheduled by FINAVIA, with a budget of some
February 23, 2018 Read time: 2 mins
Finnish contractor Lemminkäinen used three W 220 large Wirtgen milling machines for the job
Finland’s main international airport, serving the capital Helsinki, is now benefiting from a runway resurfacing project. The rehabilitation work has been needed for one of the airport’s three runways due to a number of age-related defects. Helsinki Airport processes some 17 million passengers/year and due to a combination of the often severe winter weather and the heavy aircraft traffic, the runway condition was not of the standard required.

Resurfacing work was scheduled by 6704 FINAVIA, with a budget of some €11 million, while the total area to be rehabilitated 121,000m². The runway rebuild work was planned in stages, so as to mill off 250mm of asphalt from the runway surface, but with this work being handled in three passes. This method was required in order to separate the reclaimed material into different grades. The first stage of the planning job was to remove a 100mm layer, with a second stage milling away a 50mm asphalt layer, followed by the third phase to remove the final 100mm thickness.

The work was carried out by the Finnish contractor 3064 Lemminkäinen, which has a fleet of 2395 Wirtgen milling machines. The firm used three W 220 large milling machines for the job, allowing it to remove the layers within the tight timeframe required.

For more information on companies in this article

Related Content

  • Rebuilding a scenic route in South Africa
    April 20, 2018
    Equipment from Wirtgen has played a key role in the rehabilitation of a major route in Cape Town. The scenic Camps Bay Drive provides access to Camps Bay and Hout Bay Based on the project brief and geometric analysis, Camps Bay Drive required widening to cope with high volumes of tourist traffic and MyCiti buses. In order to minimise the impact on traffic, the design brief targeted construction outside the summer peak tourist season and also required investigation into shortened construction periods. The
  • Ammann plant assists in Indian airport rebuilding
    October 2, 2020
    Cochin Airport in India’s Kerala State is benefiting from an improved runway. A local contractor, Tarmat, has upgraded the runway, providing a new asphalt surface.
  • Machine control technology shortens road contract
    May 28, 2013
    The use of sophisticated machine control technology has helped halve the schedule required for a road contract – Jeff Winke. By using the latest machine control systems on the equipment fleet, a US contractor has managed to halve worker hours, machine time and overall costs. “We chopped 50% off the contract schedule,” said Jim Swenson, licensed professional land surveyor for Oregon Mainline Paving based in McMinnville, Oregon. “The project was completed a year ahead of the two-year schedule,” he explained.
  • Asphalt milling optimised by 3D controls
    February 20, 2012
    3D machine controls can optimise milling efficiency, Mike Woof reports. More efficient milling and recycling operations can be carried out by using the latest 3D control systems on the market. At the last Trimble Dimensions event in Las Vegas, the advantages of 3D controls for milling operations proved a key topic. The use of 3D control systems can offer huge advantages in milling operations. This technology helps increase productivity as the milling machine will only remove what is required, which also hel