Skip to main content

Hamburg-Finkenwerder airport has new runway surface

Hamburg’s Finkenwerder airport is now benefiting from a new runway surface following work carried out by contractor KEMNA BAU. The company recently used machines from Dynapac to resurface 36,000m2 of the runway track in Hamburg-Finkenwerder, a facility used by Airbus. The airport handles around 10-15 take-offs and landings/day when aircraft are either undergoing flight testing or being delivered to customers, as well as for deliveries of components by transport aircraft. The project was tricky as the
August 21, 2013 Read time: 3 mins
The contractor had to pave 36,000m2 within a short time frame using the Dynapac pavers and materials feeders

Hamburg’s Finkenwerder airport is now benefiting from a new runway surface following work carried out by contractor KEMNA BAU.

The company recently used machines from 206 Dynapac to resurface 36,000m2 of the runway track in Hamburg-Finkenwerder, a facility used by Airbus. The airport handles around 10-15 take-offs and landings/day when aircraft are either undergoing flight testing or being delivered to customers, as well as for deliveries of components by transport aircraft.

The project was tricky as the contractor had just four days in which to carry out the resurfacing so as to avoid impinging on air traffic. In this short time slot, the firm had to mill out the old asphalt surface down to the original binder course and then repave this with new asphalt. In addition, the contractor was also responsible for the subsequent application of the markings.

To meet the tight time schedule, the contractor used machines working together. Three Dynapac pavers were brought to the site along with Dynapac material feeders to meet the high surface requirements stipulated by the aircraft manufacturer Airbus. The three SD2550CS pavers were set up with R300 TV rigid screeds that were 12m wide. “In order to progress as quickly as possible, we decided to use two staggered machine units, consisting of a paver and a feeder,“  Henning Peter from KEMNA BAU explained. In case of any problems with the equipment, the third Dynapac paver and materials feeder were near at hand on standby.
The firm used the latest version of the MF2500 CS feeder with its short conveyor, which was launched at the 688 Bauma 2013 exhibition a few months ago. The contractor also used the new MF2500 CL version of the feeder with its long conveyor and

both machines worked reliably, with the standby units not being required in the end. As the two pavers were used alongside each other, they were also able to lay the surface with a hot-to-hot joint, which allowed a better bond and will contribute to a longer working life, as well as improving surface quality.

The contractor was able to use the machines to pave the surface and meet the tight quality requirements of the client. The specification stated that the new asphalt surface would not deviate more than +/-0.2% from the desired slope, while unevenness to be a maximum of 3mm over a 4m long test section.

For more information on companies in this article

Related Content

  • Vögele | Sustainable road rehabilitation on the Dutch coast
    January 23, 2024
    In-place cold recycling with Wirtgen Group machines
  • Oklahoma highway surface upgrade
    February 2, 2017
    A milling and paving project has provided a necessary surface upgrade for a busy stretch of highway in Oklahoma US Route 62 is an important route and runs 3,597km from the Mexico-US border at El Paso, Texas, to Niagara Falls, New York, on the Canada–US border. A 12km section of the road where it runs through in Oklahoma recently received a rehab. The Oklahoma Department of Transportation (ODOT) project started in Blanchard, Oklahoma, and headed west. This stretch was built in 2000 when ODOT was switc
  • Building an airport for St Helena
    August 29, 2013
    The remote South Atlantic island of Saint Helena will shortly benefit from the construction of a new airport as well as access roads and supporting infrastructure. This is the biggest construction project in the history of the island, which lies nearly 2,000km off the coast of Africa. The airport is expected to boost economic development for the island’s 4,000 residents with an estimated 20,000 people a year forecasted to visit this highly remote, 122km2 equatorial volcanic outcrop. At present the islan
  • SBS modified asphalt delivers added benefits
    February 17, 2012
    Special additives are used in asphalt mixes to give them added benefits as Patrick Smith reports