Hamburg-Finkenwerder airport has new runway surface

Hamburg’s Finkenwerder airport is now benefiting from a new runway surface following work carried out by contractor KEMNA BAU. The company recently used machines from Dynapac to resurface 36,000m2 of the runway track in Hamburg-Finkenwerder, a facility used by Airbus. The airport handles around 10-15 take-offs and landings/day when aircraft are either undergoing flight testing or being delivered to customers, as well as for deliveries of components by transport aircraft. The project was tricky as the
August 21, 2013 Read time: 3 mins
The contractor had to pave 36,000m2 within a short time frame using the Dynapac pavers and materials feeders

Hamburg’s Finkenwerder airport is now benefiting from a new runway surface following work carried out by contractor KEMNA BAU.

The company recently used machines from 206 Dynapac to resurface 36,000m2 of the runway track in Hamburg-Finkenwerder, a facility used by Airbus. The airport handles around 10-15 take-offs and landings/day when aircraft are either undergoing flight testing or being delivered to customers, as well as for deliveries of components by transport aircraft.

The project was tricky as the contractor had just four days in which to carry out the resurfacing so as to avoid impinging on air traffic. In this short time slot, the firm had to mill out the old asphalt surface down to the original binder course and then repave this with new asphalt. In addition, the contractor was also responsible for the subsequent application of the markings.

To meet the tight time schedule, the contractor used machines working together. Three Dynapac pavers were brought to the site along with Dynapac material feeders to meet the high surface requirements stipulated by the aircraft manufacturer Airbus. The three SD2550CS pavers were set up with R300 TV rigid screeds that were 12m wide. “In order to progress as quickly as possible, we decided to use two staggered machine units, consisting of a paver and a feeder,“  Henning Peter from KEMNA BAU explained. In case of any problems with the equipment, the third Dynapac paver and materials feeder were near at hand on standby.
The firm used the latest version of the MF2500 CS feeder with its short conveyor, which was launched at the 688 Bauma 2013 exhibition a few months ago. The contractor also used the new MF2500 CL version of the feeder with its long conveyor and

both machines worked reliably, with the standby units not being required in the end. As the two pavers were used alongside each other, they were also able to lay the surface with a hot-to-hot joint, which allowed a better bond and will contribute to a longer working life, as well as improving surface quality.

The contractor was able to use the machines to pave the surface and meet the tight quality requirements of the client. The specification stated that the new asphalt surface would not deviate more than +/-0.2% from the desired slope, while unevenness to be a maximum of 3mm over a 4m long test section.

For more information on companies in this article

Related Content

  • Smart compaction at new airport project
    February 7, 2017
    A new airport project is benefiting from some of the latest developments in compaction technology Work started on a new airport for Istanbul in June 2014, with the facility set to be one of the world's largest and to set new standards when it opens for business. BOMAG has been playing a key role in the construction work at the new site, which is located close to the Black Sea coast. The construction equipment company has worked closely with the engineering team on site and BOMAG machines are now carr
  • Microsurfacing a cost-effective road rehabilitation solution
    July 13, 2012
    German company WEIRO has helped to introduce new microsurfacing technology to Estonia to upgrade its roads Estonia's rapidly growing road network requires modern and cost effective road surface rehabilitation technologies. As a result of technological and economical evaluations of the Estonian road network, it has been stated that repairs and upgrading of the existing network will remain the first priority, especially the repair of ruts, which represent a major problem in Estonia. The aim of a trial run of
  • Scotland’s new Queensferry Crossing over the Forth Estuary
    December 23, 2015
    The new Queensferry Crossing under construction in Scotland will be the third landmark bridge spanning the Forth Estuary - Mike Woof writes When the new Queensferry Crossing over the Forth Estuary opens at the end of 2016, it will be the third landmark bridge to be built spanning this short stretch of water. Lying alongside the existing road bridge and the historic rail bridge, this new structure will be as groundbreaking as the two earlier crossings were at the time of their construction.
  • Improved Lanzhou airport road link in China
    December 10, 2015
    An upgraded road link will reduce travel time to and from Lanzhou Zhongchuan Airport in China Work on the expressway connecting Lanzhou Zhongchuan Airport to Lanzhou city centre is now underway. An important role in the resurfacing work is being played by the use of materials supplied by Shell Bitumen. The facility is the main airport for Gansu Province and it is of major economic importance to the region. The expressway runs some 70km from Lanzhou Zhongchuan Airport to the centre of Lanzhou. Work on the