FM Conway lays 92% RAP in UK road

The project in the City of Westminster – part of the London urban area - achieved a total embodied and operational carbon saving of 78% – equal to around 100 tonnes of CO₂ equivalent.
January 22, 2024 Read time: 4 mins
Around 280 tonnes of warm-mix asphalt was laid as a single layer, covering 1,600m² of carriageway (image courtesy FM Conway)

Paving contractor FM Conway says it has laid the UK’s highest ever recycled content in what it claims as a “one-of-a-kind carbon-neutral” scheme.

The work was done on Elmfield Way in the City of Westminster, part of the greater London urban area. The contractor laid a road surface containing 92% recycled materials - the highest percentage ever used on a UK road.

As Westminster City Council’s Highways partner, FM Conway delivered an upgrade of the road and footways, implementing multiple low-carbon techniques. It achieved a total embodied and operational carbon saving of 78% – equal to around 100 tonnes of CO₂ equivalent.

The residual unavoidable carbon emissions were then offset using high-quality Verified Carbon Standard (VCS) units. These are administered and certified by Verra, the world’s largest carbon registry, to make it a one-of-a-kind carbon neutral scheme, says Conway.

Around 280 tonnes of warm-mix asphalt was laid as a single layer, covering 1,600m² of carriageway. The proprietary mix, designed, manufactured and laid by FM Conway, was the combination of three specifications of the contractor’s 14mm SureLayer E product with the addition of extra recycled aggregate.

Surface course: 92% RAP

The finished product provided a surface course containing 92% recycled materials. This delivered other benefits in addition to carbon reduction, such as faster installation and less disruption to the neighbourhood. The material’s use of a polymer modified bitumen, specially designed for the project, also meant increased durability and resilience, extending its life for years to come, said Conway.

To achieve the substantial carbon savings, the asphalt material was manufactured at lower temperatures and laid in a thinner layer. This allowed for around 30% fewer tonnes manufactured, transported and laid – saving carbon throughout the life cycle.

The use of recycled content meant the use of less virgin bitumen and less quarried stone, preserving the natural environment and reducing the carbon impact from haulage of these materials. In addition, the road planings were transported back to the same plant where the asphalt was made, optimising the use of large transport vehicle logistics and minimising empty journeys.

The proprietary mix from FM Conway was the combination of three specifications of the contractor’s 14mm SureLayer E product with the addition of extra recycled aggregate (image courtesy FM Conway)
The proprietary mix from FM Conway was the combination of three specifications of the contractor’s 14mm SureLayer E product with the addition of extra recycled aggregate (image courtesy FM Conway)

Alongside the new carriageway, the scheme also involved the enhancement of the footway between the Woodfield Medical Centre and Harrow Road, as well as the installation of 11 LED lamp columns, 200m of cabling and a full drainage review and clean.

Additional carbon savings were made in the footway construction, through the implementation of FM Conway’s low-carbon model. This incorporated closed loop recycling of excavated materials, as well as the use of lower thickness paving materials and lower-carbon cement alternatives.

The full scope of works was carried out using no fossil fuels on site. This was achieved through the use of hydrotreated vegetable oil (HVO) in the resurfacing element of the scheme, plus the use of electric mini-excavators, disc cutters and compaction plates. Also employed was a solar-powered welfare unit which used HVO as a backup in the footways element.

After the embodied and operational carbon savings were achieved, the residual unavoidable emissions were offset using high-quality carbon removal and renewable power projects. The business has also supported tree planting in the UK, through the purchase of Pending Issuance Units administered by the Woodland Carbon Code, marking FM Conway’s investment in future UK-based carbon removals.

The completed project now joins a series of low-carbon trials delivered throughout Westminster as part of the council’s and FM Conway’s shared net-zero ambitions. For this the partnership is using these new specifications to provide significant carbon savings compared to traditional materials and methods.

Pushing RAP boundaries

FM Conway and Westminster City Council have a longstanding history in pioneering the use of recycled content. A trial to lay an 80% recycled content surface in 2019 was followed in 2021 by a warm-mix surface course containing 85% recycled content on another road.

“This one-of-a-kind scheme illustrates how it is possible to stack together the best low-carbon products, methods and techniques that are available today, to deliver massive carbon reductions,” said Matt Tallon, sustainability director at FM Conway Sustainability Director.

“It is only once these embodied and operational carbon savings are made, should the residual carbon be offset, which in this case was done with high quality, verified ‘VCS’ carbon removal and renewable projects, as well as the planting of trees in the UK.”

The project pushed the boundaries for using recycled asphalt in carriageway works, noted Phil Robson, head of highway operations at Westminster City Council.

“It is a really interesting time to be working in highways with partners and adapting services to achieve climate-resilience and low-to-zero carbon emissions. The transition requires the use of offsets at this time but we expect to see lower reliance on them over time,” said Robson.

For more information on companies in this article

Related Content

  • Steel sealed on Stonecutters Bridge
    February 6, 2012
    The stone mastic asphalt surface being laid on the bridge deck. The Stonecutters Bridge in Hong Kong, the second longest spanning cable stayed bridge in the world, is a dual three-lane crossing of the Rambler Channel. It utilises 33,500tonnes of structural steel in the bridge deck; 32,000m3 of concrete in the towers and 65 steel deck units relying on 224 cables. Effectively protecting the megastructure's deck from the weather extremes (monsoon rains and extreme heat in the summer) and the high levels of tra
  • Highway widening project for the US
    April 19, 2018
    A highway widening project in the US state of New Hampshire is being assisted by the use of a gravity-fed asphalt paver. The widening work is being carried out as part of an upgrade for a 32km stretch of I-93, which was started eight years ago. The work is being carried out for the New Hampshire Department of Transportation (NHDOT) on a section of the highway between Exits 1 and 5 from the Massachusetts Stateline to Manchester, NH. According to NHDOT, the project involves widening I-93 from two lanes in
  • Emphasis on the new at record-breaking World of Asphalt 2013 & AGG1
    February 21, 2013
    The 2013 World of Asphalt and AGG1 expositions taking place March 19-21 in San Antonio, Texas are on course to be sold out by opening day, setting new records for exhibitor numbers and attendees. Guy Woodford discovers that major construction industry manufacturers will be highlighting new as well as established machine models in their exhibits at the co-located events Covering more than 10,870m² of exhibit space, attendees at the 2013 World of Asphalt and AGG1 shows can expect to find a huge line-up of new
  • Novel dual layer paving work in Germany
    February 2, 2017
    A German contractor is now using two novel asphalt paving technologies from Vögele together for key projects The firm has acquired Vögele’s InLine Pave equipment with its innovative dual layer paving technology as well as one of the SUPER 1800-3i SprayJets for paving a surface course. This combination of technologies is allowing contractor Rask Brandenburg to carry out fast and efficient road rehabilitation work on some major routes, including a busy Autobahn stretch leading into capital Berlin. T