Bolivia’s new highway

Bolivia’s new highway will provide better access into mountain areas – Mauro Nogarin writes At the beginning of 2015, work began on the construction and paving for the Tupiza - Atocha - Uyuni highway project. The route is located in Bolivia’s Potosí department: it is 189m in length and forms part of the Southwest Basic Road Network (RVF) of Bolivia.
October 10, 2017 Read time: 4 mins
Bolovia’s Potosí Department is benefiting from an upgraded road connection
Bolivia’s new highway will provide better access into mountain areas – Mauro Nogarin writes


At the beginning of 2015, work began on the construction and paving for the Tupiza - Atocha - Uyuni highway project. The route is located in Bolivia’s Potosí department: it is 189m in length and forms part of the Southwest Basic Road Network (RVF) of Bolivia.

The completion of this important route is requiring funding worth US$150 million, of which 72% is being delivered through loans from the 1054 European Investment Bank and the CAF - Latin 4900 American development bank, and the remaining 28% comes from the government of the department of Potosí.

This route will increase and diversify the economic development in the southern region of the country, both with tourism at the Salar de Uyuni and with agricultural and mining activity. It is estimated that the travel time will be reduced from 5 hours to two hours and 25 minutes, benefiting the populations of Uyuni, Noel Mariaca, Cerdas, Atocha, Villa Solano, Thola Mayu, Palca Flores, Salo, San Miguel and Tupiza.

According to the project the work is taking 42 months in all, and will open to traffic in June 2018. The majority of the area is located in the highlands, between the Eastern and Western ranges of the Bolivian Andes. The road runs along morphological zones that appear as flat and semi-flat, with undulations and relatively low mountains, where the road mapping is between a flat and wavy topography, as well as straight and winding. The road engineers will use gradients of between 9-10%.

In the Atocha and Tupiza Sector, the high mountains range in altitudes from 3,000-5,500m above sea level, with slopes between 15% and 60%, and their lengths of 200-500m. And the average mountains reach elevations from 2,500-5,150m, with slopes of around 10% to more than 60%, with variable lengths between 200 - 500 m.

The main climatic characteristics of the area covered by the project in the municipality of Uyuni are intense cold and little rainfall with an average relative humidity of 33%.

The design of the first 86km of the road consists mostly of long straight sections with few curves, while the vertical geometry features a few smooth slopes. However once the route reaches the town of Atocha, the horizontal geometry suddenly becomes more complex and includes a series of curves.


The next stretch of the road from Atocha to the town of Tupiza measures 103km long and climbs in altitude, with the route featuring with closed curves and drops that reach 10%. Meanwhile the area also features significant slopes as it is a mountainous zone. The road improvements required changes to the alignment and horizontal adjustment to boost safety.

Because of the complex geography and geology of the area, the drainage system designed for the Uyuni to Tupiza stretch of road features both surface and underground systems. The construction of 231 sewers is planned, most of which are in sectors where there are bofedales (high-altitude areas of boggy peat that are common in the Andes, having been expanded by human habitation to increase vegetation) and outcrops of water flows.

Three grades of concrete, type "A" (210kg/cm2), type "C" (160kg/cm2) and type "E" (110kg/cm²) are used for these drainage works, with the specific design catering to the volume of water calculated.

The construction company José Cartellone currently has two working areas on the project, with one located in the section between Km23 to Km63 where paving works are being carried out. The second is located in the section between Km77 to Km 90, where excavations are being carried out along with stabilisation of the embankment and alignment. In general the roadway is 7m wide in total and a features a 1m berm with a 50mm asphalt layer that includes the use of PMBs. The design speed of the road is estimated at 80km/h. The structure of the road itself features a sub-base layer of 220mm and with a base layer of 150mm and an asphalt surface 70mm thick.


Along the entire route, seven bridges will be built, with a total length of 351m. However the most important bridges are located at Choroma and Tolonias, with construction starting at the end of 2017. The Choroma Bridge features a design comprising two reinforced concrete supports sitting on deep foundations, while the superstructure has a reinforced concrete slab and a design with three pre-stressed concrete beams that are 35.6m in length. The bridge also consists of two spans and is 71.2m long.

The Tolonias Bridge meanwhile has a similar design with two reinforced concrete supports resting on piles that are 1.2m in diameter. The reinforced concrete slab superstructure has three pre-stressed concrete beams that are also 35.6m in length and with the two spans, the bridge is also 71.2m long.

Bridges

   
Name  Length (M)
Jhanco Kollu 2
 71.2
Inca cancha
 35
Quebrada honda
 41.2
El Tigre
 41.2
Colorado
 20
Choroma
 71.20
Tolonias
 71.20
Source. ABC

DATA

LENGTH:
189 Km
INVESTMENT:
US$150 millon
START DATE:
December 2014
CONSTRUCTION DURATION:
42 months
COMPLETION DATE:
June 2018
Source. ABC










For more information on companies in this article

Related Content

  • Choosing the right modified bitumen made easier
    February 10, 2012
    Choosing the correct high performance binder material for use in asphalt applications has been made easier following a product rebranding exercise by one company. Awareness among highway maintenance contractors of the benefits of selecting polymer modified bitumens when specifying road surfacing materials has risen markedly in the last few years.
  • Highlights for the IRF World Meeting technical & scientific programme
    August 28, 2013
    The call for papers was launched in late 2012 with two objectives in mind, to attract the best in innovative technical, institutional, economic, business and policy issues that are relevant, recent, and significant. These papers are suitable for presentation in a technical session, and to attract original research and technological innovation that is recent, relevant and significant, as well as for presentation in a scientific session. The Technical & Scientific program is being developed through the
  • Japanese dual layer paving technology
    October 9, 2012
    Most of the dual layer paving in Japan is performed by the Multi-Asphalt Paver, manufactured by SUMITOMO (S.H.I.) CONSTRUCTION MACHINERY CO., LTD (SUMITOMO) As per the introduction report to follow, this machine can simultaneously handle two different types of asphalt mixtures and can perform two kinds of paving methods. First one is Dual layer paving (it is called Dual Asphalt Pavement method), and the second is Multi Lane Pavement method. Hereinafter, paving methods using the Multi-Asphalt Paver will be
  • Bolivia’s latest highway project is underway
    May 29, 2018
    Bolivia’s new highway project will improve connections with Brazil and Chile – Mauro Nogarin reports. Work is underway on Bolivia’s new Rurrenabaque – Riberalta highway project, which will boost connectivity for the country. The project is being coordinated by the Bolivian Highway Administration (ABC), with an Eximbank loan of US$579.4 million providing the financing for 85% of the work. The remaining 15% of the funding will come from the Beni Department’s budget, where the route is being built. Located in