Beijing airport runway features novel asphalt solution

Beijing ranks amongst the five busiest airports across the globe and its runway surfaces face tough stresses as a result. Over 94 million passengers flew through Beijing Capital Airport (BCA) in 2016 and as many as 70 flights/hour can take off and land during peak times. The 60m-wide middle runway of Beijing Capital International Airport is the busiest of the three runways, with a landing and take-off flight ratio of up to 40%. This runway was first rehabilitated in 1996 and then repaired in 2013 and 2015
December 7, 2017 Read time: 3 mins
Paving in echelon was carried out at Beijing airport, with the project benefiting from Evotherm technology

Beijing ranks amongst the five busiest airports across the globe and its runway surfaces face tough stresses as a result

Over 94 million passengers flew through Beijing Capital Airport (BCA) in 2016 and as many as 70 flights/hour can take off and land during peak times. The 60m-wide middle runway of Beijing Capital International Airport is the busiest of the three runways, with a landing and take-off flight ratio of up to 40%. This runway was first rehabilitated in 1996 and then repaired in 2013 and 2015 to address damaged areas. However in April 2017 major rehabilitation work was carried out, which included pavement milling, paving and light installing. The construction area consisted of 130,000m2 of runway and 70,000m2 of taxiway for a total construction area of 200,000m2.

Paving and maintaining an airport runway is never easy. The ageing issues of most concern are block cracking and fatigue cracking so 8536 Evotherm warm mix asphalt (WMA) technology was selected to help extend the life of the airport’s runway.

Chinese contractor Beijing Sino-Aero Construction Engineering (BSACE) worked with Evotherm to select the right technology for the project. When searching for a product, the focus was maximising compaction and consistency of the mix due to the stiff and difficult-to-compact mixture types on the runway.

Yifan Yang, technical services at Ingevity in China said, “This project lasted for four weeks in April. It required speed in daytime and night-time paving, so that the least amount of disruption to BCA’s traffic occurred.”

“Evotherm was chosen particularly because of the materials used in this project,” said Lennon Dong, structural technical management for Ingevity in China. He said that the airport mixtures resulted in Marshall stability over 14kN at 60˚C, along with rutting resistance of over 10,000 passes/mm when measured with the Chinese wheel rut test. The bottom course applied by BSACE contained a high concentration SBS and an anti-rutting agent, and the wearing course mix was a polymer modified stone matrix asphalt (SMA) mixture with a high concentration SBS, an anti-rutting agent and glass fibre additives.

BSACE had two mix plants set up for the project and Evotherm was added as the tank trucks were unloaded. The runway’s pavement structure consisted of about 50mm of warm SMA surface layer, another 60mm of warm dense-graded middle layer mixture, and 80mm of modified WMA mixture for the bottom layer.

The HMA production temperature reduction allowed the workability of the high viscosity and stiff asphalt mixture used on runway pavement to be improved. Compaction aids were utilised to better cope with the night construction conditions to optimise performance. The technology and methods used allowed for improved adhesion between the asphalt binder and aggregates as well as increasing resistance to water damage. The use of a lower production temperature meanwhile helped to limit binder ageing and improve overall durability. The Evotherm additive was easy to use as it can be added to the asphalt as the asphalt tank trucks are being loaded, while there was no need for any changes to the plant. Production temperatures for the asphalt ranged from 175-185˚C, with paving temperatures from 165-175˚C and compaction temperatures from 150-165˚C.

“Evotherm provided many benefits on this runway project,” said Merlin Zhou, technical marketing management with Ingevity in China. “We saw significant improvement in the workability of high viscosity and stiff asphalt mixtures typically used on runway pavements. We also encountered windy conditions during night paving and found the Evotherm helped greatly with compaction despite the windy conditions.” As an added bonus, BSACE completed the project three days earlier than expected.

For more information on companies in this article

Related Content

  • Cold recycling machine
    June 11, 2019
    Wirtgen claims that its new W 380 Cri cold recycler is highly sophisticated and productive.
  • Durable surface solution
    February 22, 2012
    Innovative spray pavers from Vögele have been used in Germany to rehabilitate a section of the A99 autobahn near Munich. In all, four SUPER 1800-2 pavers fitted with SprayJet Module were used to pave a thin, noise-reducing asphalt. overlay on spray seal on the A99 to the west of the Allach Tunnel. For pavement rehabilitation, this stretch of the busy orbital motorway near Munich could only be closed to traffic at night. The traffic volume on the A99 orbital motorway near Munich is 100,000-120,000 vehicles/d
  • Tunisia road rebuild with BOMAG machines
    October 29, 2018
    Machines from BOMAG have played an important role in the rebuilding of an important road link in Tunisia
  • Polish road strengthened by Tensar
    July 31, 2012
    Consultants have specified Tensar techology in the rebuilding of a deteriorating Polish highway in order to meet current standards. The use of Tensar geogrids enabled consultants Drotest and Dro-konsult Warsaw to create a stable asphalt pavement quicker and more economically than using conventional construction methods, says Tensar. The 40km long road, which connects Bartoszyce and Ketrzyhn, had exceeded its design life and clearly showed its structural weakness with bad rutting, extensive fatigue crackin