Asphalt airport runway refurbishment

Swedish contractor Peab Asfalt generally works on major road and highway projects in the inland portion of the country. However the company has shown itself able to take on a considerable challenge, by repaving an airport runway.
February 17, 2012 Read time: 4 mins
Despite time constraints a Swedish contractor more used to carrying out road projects was able to repave a local airport runway quickly, efficiently and to the necessary high standard

Swedish contractor Peab Asfalt generally works on major road and highway projects in the inland portion of the country. However the company has shown itself able to take on a considerable challenge, by repaving an airport runway.

The project involved construction a new runway surface at an airport in Jönköping, a relatively small facility but one crucial to the inland area of Sweden. To make the work easier for the contractor, most of the scheduled flights were re-routed during the project, with the exception of two/day in the later afternoon or evening. That enabled 2593 Peab Asfalt to make progress almost daily, and also kept outbound and inbound passengers and freight connecting to key hubs in Stockholm and Copenhagen.

Reijo Seppanen, project superintendent for the company said, "Even with the limited flights, we had to adjust paving schedules." Paving often started in the middle of the night and extended into the late afternoon of the following day. The work was complex and he added, "When you're working on a project like this, anything can happen. You can have problems with the weather and there are always time pressures, deadlines to meet. We have to get off the runway one hour before the next airplane is arriving." Another contractor handled the first phase of the project, which consisted of milling about

50 mm off the existing surface and Peab Asfalt then carried out the paving operation, which took around three weeks. Surface quality is crucial for airport runways given the high landing speeds of aircraft and the enormous impact loads they place on a runway structure. Material segregation presents a major problem in asphalt paving and something Peab Asfalt was particularly keen to avoid on this project. The firm took a series of steps, starting at the plant with proper loading of the trucks and also by using truck bodies with rounded rather than flat bottoms, a feature which prevents sticking when the materials are end-dumped into the paver.

The trucks travelled some 70km from the plant to the airport and material cooling was minimal as the tipper bodies are insulated, traffic volumes were low due to the area and because much of the paving was done at night. The short truck cycle times and various measures used to tackle material segregation helped boost paving quality. The mix left the plant at 170º-180ºC and was dumped into the hopper at about 160º-165ºC. Plant production, paving speed and trucking were all calculated to keep the paver moving at a consistent pace.

Another technique used to minimise segregation was to allow mix to collect in the sides of the hopper throughout the shift. "We don't close the sides between lifts to loosen material," Seppanen said. "The asphalt on the sides is cold, and we don't want to shake it loose and mix it with the hotter material. When the work is done for the day, we clean the sides." The contractors used a new 178 Caterpillar AP600D paver for the work, although the firm had previously used Cat pavers. The paver worked at a pace of about 4-5m/minute, placing a single lift of 40mm at a width of 4.5m. In all 10 passes were required to cover the entire width of the 45m runway.

"The middle of the runway is the highest point because of drainage," Seppanen said. "We started at one side, then made five passes until we reached the middle. Then we started at the opposite side, and worked our way back to the middle." The width of the project led to many longitudinal joints. Peab Asfalt crews placed the new, hot mat slightly higher than the adjacent cold mat. A breakdown compactor used a small side roller to compact the joint. Three 11tonne class rollers handled compaction and the first made 6-7 passes, operating close up to the paver and working as far back as 20-30m from the machine. The second roller worked in vibratory mode about 50m from the paver and the number of passes varied depending on the specific conditions on that day. The third roller had no set distance between it and the rest of the paving train and was largely used to take the tracks out of the mat and provide a smooth finish. Core samples were taken along the way to ensure adequate compaction was being achieved.

Although the project placed heavy demands on the contractor in terms of productivity and time the firm was able to meet the challenge and both the paving crew and machines used proved equal to the task.

For more information on companies in this article

Related Content

  • Dual layer, hot to hot paving at German airport
    August 18, 2015
    An airport in Germany has seen the use of very innovative asphalt paving techniques, with the use of dual-layer, hot-to-hot working. The method was used to meet a very tight schedule for the runway rebuilding work, while also delivering the high quality required. Two InLine Pave trains from Vögele were used at Rostock-Laage Airport to lay a new surface and binder course. The operation was innovative as the process used both hot-to-hot, echelon paving as well as dual layer, hot-on-hot working. Using this
  • Airport's high demands on asphalt and concrete techniques
    July 11, 2012
    Airport runway, taxiway and parking areas make high demands on paving requirements, both with concrete and asphalt techniques. Mike Woof reports. High quality surface finishes are required in airport environments for runways, taxiways and aircraft parking areas. Because of the speed at which aircraft take off and land and the massive forces exerted due to the weight of the aircraft, particularly during landing, runway structures need to be incredibly strong. The surfaces also have to be constructed to very
  • Caterpillar Paving offers a guide to efficient night time paving practices
    October 3, 2014
    Efficient night-time paving operations can reduce construction costs and cut traffic delays - *Todd Mansell writes As roads become more congested, the user cost of daytime lane closures to accommodate road construction and paving has increased dramatically. One solution to lower user costs associated with traffic delays is to carry out more paving at night during off-peak times. However night-time paving brings new challenges to producing quality work in safely.
  • Micro surfacing the Brooklyn Bridge with Bergkamps’ M210 paver
    May 16, 2018
    A major job for micro surfacing took place on the Brooklyn Bridge near New York. It was the third time in Ken Messina’s career that he would provide micro surfacing for the iconic Brooklyn Bridge, built in 1883. Messina, as president of New Jersey-based Asphalt Paving Systems (APS), knew only too well the challenges that lay ahead. And there were many. There would be only a brief window of opportunity for paving, with lane closures starting at 10pm and ending at 5am. The cool, humid atmosphere would a