All aboard the Wirtgen paving train on Germany’s A7 project

The A7 is being widened between Hamburg and Bordesholm from four lanes to six - in some places to eight - to ensure the motorway remains an efficient traffic artery. The aim is to create a pavement with a high degree of driving comfort but which withstands the loads of heavy-goods traffic. For widening the 60km stretch in the Schleswig-Holstein region, consortium Via Solutions Nord and joint venture ARGE A7 Hamburg-Bordesholm opted for steel reinforced concrete paving with an exposed aggregate concrete s
February 21, 2019 Read time: 3 mins
Dual-layer concrete placing on the A7: two Wirtgen SP 1500 slipform pavers and Wirtgen’s TCM 180i texture curing machine
The A7 is being widened between Hamburg and Bordesholm from four lanes to six - in some places to eight - to ensure the motorway remains an efficient traffic artery. The aim is to create a pavement with a high degree of driving comfort but which withstands the loads of heavy-goods traffic.


For widening the 60km stretch in the Schleswig-Holstein region, consortium Via Solutions Nord and joint venture 2841 ARGE A7 Hamburg-Bordesholm opted for steel reinforced concrete paving with an exposed aggregate concrete surface.

Meanwhile, contractor BT Beton-Technik was commissioned with the job. The company, which has specialised in concrete pavement construction for many years, has been relying on technologies and machines from 2395 Wirtgen for just as long. "I insist on 100% quality –precisely what Wirtgen has been delivering for over 25 years," says managing director Mirko Pokrajcic.

Concrete paving was carried out by two Wirtgen SP 1500 slipform pavers. As the first paver advanced, its inset mould laid the concrete slab as specified,- 14.5m wide and 23cm thick. A total of 41 curved electric internal vibrators ensured optimum material compaction by means of high-frequency vibrations.

Dowel bars were inserted into the fresh, pre-compacted bottom-layer concrete at 25cm intervals and parallel to the direction of travel. Tie bars were inserted transverse to the pavement. The top-layer concrete was simultaneously loaded by excavator into the receiving hopper of the belt conveyor, transported over the top of the first SP 1500 and deposited directly on the bottom-layer concrete in front of the second SP 1500.


The second machine compacted the material by means of 29 electric T-vibrators, as they are known, while paving it in a 5cm-thick layer. In this way, the duo from Wirtgen paved around 4,000m³ of concrete each day.


The retarder enables the surface mortar to be swept off, exposing the high-grade broken aggregate in the top-layer concrete. Depending on weather conditions, this can be done around four hours or more after paving. This gives the concrete pavement the required peak-to-valley depth and lasting grip. A curing agent is once again sprayed over the exposed aggregate.

Unlike in the process selected for the A7 in other countries, a 2833 TCM 180i self-propelled curing unit is used to create the desired texture. The machine moves a brush across the entire concrete surface to create a range of different surface textures to meet requirements. In addition to the well-established functions of transverse brushing and spraying, longitudinal brushing and spraying – and even the application of a diagonal finish – are possible.
Meander spraying is a special option. This method permits transverse spraying during uninterrupted travel. What is more, Wirtgen are continually advancing the associated components to ensure an optimum surface texture. The brush-cleaning unit of the TCM 180i is one prime example.

Cleaning the spray systems of curing machines economically is something of a challenge. With this in mind, Wirtgen has integrated into the TCM 180i a hot-water system with a 90-litre tank. With this system, any amounts of curing agent adhering to the inside of the pipes can be completely removed with water up to 60°C. The entire spray system is quickly and reliably cleaned – all at the push of a button and by shifting two ball cocks.


The hot water system has impressed Deni Pokrajcic, site manager BT Beton-Technik. “Wirtgen have struck gold with the new hot-water system of the TCM 180i. This added practical benefit will be a great asset to us in the future, too.”

For more information on companies in this article

Related Content

  • Atlanta airport’s new apron
    October 12, 2012
    The new Maynard H Jackson Jr International Terminal at Hartsfield- Jackson Atlanta International Airport is now open for business. The 111,484m2 terminal features 12 gates, eight security checkpoints, separate levels for arrivals and departures, as well as a 148,831m2 concrete apron for aircraft to park on arrival. Archer Western won the contract to slipform the concrete apron, replace the existing Taxiway D, as well as other utilities and embankment work. The firm brought in one of its GOMACO paving trains
  • Innovative concrete paving technology is coming to market
    March 12, 2014
    Two of the leaders in the concrete paving sector are broadening their range of technology, with new systems now coming to the international market The concrete paving market is a niche segment of the construction equipment business, with only a few specialist firms competing. North America is the home of concrete slipforming technology and it is no surprise that all but one of the leading firms in the sector are based in the US. The technology is used worldwide however and with asphalt prices at a high, c
  • Concrete paving a smoother surface using machine control technology
    May 17, 2017
    Innovative technology has been used to deliver a smooth concrete road surface on a busy stretch of highway in Nebraska. Much-needed work on a busy section of Interstate 80 has been carried out in Nebraska to improve the road surface. This is one of the most important highways in the US, providing a link that stretches right across the country between the east and west coasts. This busy highway carries a high percentage of heavy truck traffic as it is a vital transport route. However this constant flow of la
  • Runway rebuild for Detroit airport
    January 25, 2017
    A US contractor has employed equipment from Guntert & Zimmerman to help carry out a runway rebuild at Detroit Metro Airport The busy airport handles around 30 million passengers/year and the project had to be carried out in a tight timeframe as a result, with the paving crew working 16 hours/day to meet the schedule. Ajax Construction has been using its G&Z S850 paver for the work, which was needed as the existing concrete surface on runway 4L/22R had suffered from an alkali silica reaction (ASR). The