All aboard the Wirtgen paving train on Germany’s A7 project

The A7 is being widened between Hamburg and Bordesholm from four lanes to six - in some places to eight - to ensure the motorway remains an efficient traffic artery. The aim is to create a pavement with a high degree of driving comfort but which withstands the loads of heavy-goods traffic. For widening the 60km stretch in the Schleswig-Holstein region, consortium Via Solutions Nord and joint venture ARGE A7 Hamburg-Bordesholm opted for steel reinforced concrete paving with an exposed aggregate concrete s
February 21, 2019 Read time: 3 mins
Dual-layer concrete placing on the A7: two Wirtgen SP 1500 slipform pavers and Wirtgen’s TCM 180i texture curing machine
The A7 is being widened between Hamburg and Bordesholm from four lanes to six - in some places to eight - to ensure the motorway remains an efficient traffic artery. The aim is to create a pavement with a high degree of driving comfort but which withstands the loads of heavy-goods traffic.


For widening the 60km stretch in the Schleswig-Holstein region, consortium Via Solutions Nord and joint venture 2841 ARGE A7 Hamburg-Bordesholm opted for steel reinforced concrete paving with an exposed aggregate concrete surface.

Meanwhile, contractor BT Beton-Technik was commissioned with the job. The company, which has specialised in concrete pavement construction for many years, has been relying on technologies and machines from 2395 Wirtgen for just as long. "I insist on 100% quality –precisely what Wirtgen has been delivering for over 25 years," says managing director Mirko Pokrajcic.

Concrete paving was carried out by two Wirtgen SP 1500 slipform pavers. As the first paver advanced, its inset mould laid the concrete slab as specified,- 14.5m wide and 23cm thick. A total of 41 curved electric internal vibrators ensured optimum material compaction by means of high-frequency vibrations.

Dowel bars were inserted into the fresh, pre-compacted bottom-layer concrete at 25cm intervals and parallel to the direction of travel. Tie bars were inserted transverse to the pavement. The top-layer concrete was simultaneously loaded by excavator into the receiving hopper of the belt conveyor, transported over the top of the first SP 1500 and deposited directly on the bottom-layer concrete in front of the second SP 1500.


The second machine compacted the material by means of 29 electric T-vibrators, as they are known, while paving it in a 5cm-thick layer. In this way, the duo from Wirtgen paved around 4,000m³ of concrete each day.


The retarder enables the surface mortar to be swept off, exposing the high-grade broken aggregate in the top-layer concrete. Depending on weather conditions, this can be done around four hours or more after paving. This gives the concrete pavement the required peak-to-valley depth and lasting grip. A curing agent is once again sprayed over the exposed aggregate.

Unlike in the process selected for the A7 in other countries, a 2833 TCM 180i self-propelled curing unit is used to create the desired texture. The machine moves a brush across the entire concrete surface to create a range of different surface textures to meet requirements. In addition to the well-established functions of transverse brushing and spraying, longitudinal brushing and spraying – and even the application of a diagonal finish – are possible.
Meander spraying is a special option. This method permits transverse spraying during uninterrupted travel. What is more, Wirtgen are continually advancing the associated components to ensure an optimum surface texture. The brush-cleaning unit of the TCM 180i is one prime example.

Cleaning the spray systems of curing machines economically is something of a challenge. With this in mind, Wirtgen has integrated into the TCM 180i a hot-water system with a 90-litre tank. With this system, any amounts of curing agent adhering to the inside of the pipes can be completely removed with water up to 60°C. The entire spray system is quickly and reliably cleaned – all at the push of a button and by shifting two ball cocks.


The hot water system has impressed Deni Pokrajcic, site manager BT Beton-Technik. “Wirtgen have struck gold with the new hot-water system of the TCM 180i. This added practical benefit will be a great asset to us in the future, too.”

For more information on companies in this article

Related Content

  • Developments in concrete road construction
    February 7, 2012
    Innovative developments are pushing forward concrete road construction techniques. The concrete road sector looks to benefit from some key innovations and developments now coming to market or being employed in different territories. Irregular weather and environmental conditions can alter the rate at which concrete cures, with a risk of plastic shrinkage cracks that can compromise the integrity of a pavement. Contractors cannot control the environmental conditions of a paving project and when weather patter
  • Vögele's global paving vision
    January 4, 2013
    German paver specialist Vögele is taking a global view of the construction equipment market, with machines developed for very different markets. A prime example of this is with the Dash 3 models now coming to market. The new SUPER 2100-3 paver is also available as the SUPER 2100-3i, a highly sophisticated machine that meets the European emissions requirements while offering high productivity and performance. At the same time, the company is also offering a heavy duty (HD) version of its proven SUPER 1800-2
  • Spray paving with Vӧgele and Dynapac
    March 8, 2023
    Applying emulsion and carrying out asphalt paving in a single operation can boost efficiency and save much money.
  • Sangamo wins the winter battle with a Wirtgen Slipform Paver SP 15i
    January 19, 2016
    Winter was coming in the northern US state of Illinois and Sangamo Construction had to build 1.5km of bridge parapets just before the end of the construction season. Sangamo Construction was contracted to work on five bridges where some parapets needed to be 1m high x 48cm thick at the bottom, tapering to a width of just under 27cm at the top, and with a perpendicular rear wall. As much as 26m3 of concrete were processed just for the construction of the four 150m-long parapets on the twin bridges on Interst