Achieving a smooth road surface has helped a US contractor gain a bonus payment of US$605,000 on a paving job in Montana. A recently renovated 16km section of I-90, starting in Alberton, Mont., which is located on the Western part of the state near the Idaho border, and stretching East, received sterling commendations, beat target IRI scores, and earned the general contractor quality bonuses. The project also won the 2014 MCA Excellence Award for Best Paving Smoothness from the Montana Contractors Associat
September 28, 2015 Read time: 4 mins
The Roadtec Shuttle Buggy played a key role in maintaining the flow of mix to the paver
Achieving a smooth road surface has helped a US contractor gain a bonus payment of US$605,000 on a paving job in Montana

A recently renovated 16km section of I-90, starting in Alberton, Montana, which is located on the Western part of the state near the Idaho border, and stretching East, received sterling commendations, beat target IRI scores, and earned the general contractor quality bonuses. The project also won the 2014 MCA Excellence Award for Best Paving Smoothness from the Montana Contractors Association.

Knife River Corporation was the general contractor on the $15.5 million I-90 renovation. The I-90 project commenced on June 10th with Knife River’s subcontractor, Industrial Builders, performing the shoulder-to-shoulder milling of the road to 90mm, with the milled material converted to Reclaimed Asphalt Pavement (RAP). The drive lane and passing lane were milled out an additional 90mm for a total of 180mm.

As Industrial Builders began completing the 64km of milling, Knife River could begin paving. The bonus incentives offered by MDT were based on achieving paved finished surfaces with favourable International Roughness Index (IRI) scores. The 45 – 55 IRI rating was considered acceptable, with no bonus and no penalty. Achieving the 35 – 44 IRI rating would have earned up to a 24% bonus, based on a sliding scale. Meanwhile a rating below 35 IRI would have earned a 25% bonus.

The contractor knew that to achieve a low IRI index throughout the job, continuous paving was needed with thoroughly mixed HMA at the right temperature. A key factor for this was the use of a material transfer vehicle to feed the paver.
Knife River owns three 1252 Roadtec SB-2500e/ex Shuttle Buggy MTVs and knew that employing one of the units would be crucial for maximising the performance of the asphalt paver. Using the unit would also cut haulage costs by allowing trucks to dump their loads quickly and then return to the asphalt plant, 37-45km away. The MTV’s 23.5tonne surge capacity provided the contractor with plenty of mix to feed the paver and keep it continuously productive, as well as reducing thermal and material segregation.

Knife River used a two-dump-truck train for asphalt hauling. The lead belly dump had a 23.5- to 25.3tonne capacity and the connected pup had a 10.8-12.6tonne capacity. The Shuttle Buggy used a windrow pickup head to add the hauled HMA to its dump hopper.

The Montana I-90 rehab project required a total of 148,830tonnes of HMA with around one third of that being recycled asphalt pavement (RAP). Knife River placed three lifts. The bottom lift was 91.4mm thick and the top two layers were each 45.7mm thick.
The project required cooperation and coordination to maintain uninterrupted paving.  In addition to the steady delivery of HMA from the asphalt plant, there was the removal and replacement of 18,288m of guardrails. Subcontractor Mountain West Holding Company used six punch trucks to pull guard rails in front of the paver and then replace them afterwards, and this work was also carried out efficiently.

The Montana I-90 project was completed a full year ahead of schedule. In addition to an early completion, Knife River Corporation also achieved an average IRI index score of 29, which gave the company the highest incentive payment for finished pavement smoothness, earning the firm its $605,000 in bonuses.

The MTV played a key role as the quick turnaround of the haul trucks helped maintain the high production pace that Knife River set. Early in the day, Knife River would pave at a rate of 406tonnes/hour and slow the pace down to 315.7tonnes/hour toward the end of the day because it was outstripping the asphalt plant’s production.

For more information on companies in this article

Related Content

  • Concrete paving a smoother surface using machine control technology
    May 17, 2017
    Innovative technology has been used to deliver a smooth concrete road surface on a busy stretch of highway in Nebraska. Much-needed work on a busy section of Interstate 80 has been carried out in Nebraska to improve the road surface. This is one of the most important highways in the US, providing a link that stretches right across the country between the east and west coasts. This busy highway carries a high percentage of heavy truck traffic as it is a vital transport route. However this constant flow of la
  • Wirtgen Group machines delivering new runway for German airbase
    October 26, 2016
    Machines from the Wirtgen Group are carrying out an important reconstruction job for the surface course at Büchel Air Base. Road machinery from Hamm, Vögele and Wirtgen as well as asphalt plants from Benninghoven have been carrying out the work, delivering a new runway within a tight timeframe. To achieve this, the work had to be planned well in advance, with the contractors organising the logistics and their personnel accordingly.
  • Advances in asphalt paving equipment coming to market
    June 27, 2018
    Some of the key manufacturers are improving asphalt paving technology with key developments to machines as well as the electronics and telematics systems fitted – Mike Woof writes. Several of the major asphalt paver manufacturers have unveiled new machines and systems that can optimise operations. Improved operating features for the BOMAG BF 800 C-2 paver are said to help increase its output and efficiency when working on-site. An important development is the new traffic light system, which helps improve co
  • Machine control technology shortens road contract
    May 28, 2013
    The use of sophisticated machine control technology has helped halve the schedule required for a road contract – Jeff Winke. By using the latest machine control systems on the equipment fleet, a US contractor has managed to halve worker hours, machine time and overall costs. “We chopped 50% off the contract schedule,” said Jim Swenson, licensed professional land surveyor for Oregon Mainline Paving based in McMinnville, Oregon. “The project was completed a year ahead of the two-year schedule,” he explained