Volvo machines help construct new Norwegian tunnels

Close to Larvik in Norway’s Vestfold County and around 80km south of Drammen, two tunnels are currently under construction as part of a state-funded infrastructure development programme. The project, which began earlier this year, comprises 7km of four lane highway – part of the E18 major route – linking the towns of Bommestad and Sky. This includes the new Larvik and Matineå tunnels, which will span 2.8 and 1.3km respectively. Worth €187 million, this project was awarded to Skanska Norway, the second la
January 12, 2015 Read time: 4 mins
Modified Volvo CE equipment is being used on this project
Close to Larvik in Norway’s Vestfold County and around 80km south of Drammen, two tunnels are currently under construction as part of a state-funded infrastructure development programme. The project, which began earlier this year, comprises 7km of four lane highway – part of the E18 major route – linking the towns of Bommestad and Sky. This includes the new Larvik and Matineå tunnels, which will span 2.8 and 1.3km respectively.

Worth €187 million, this project was awarded to 2296 Skanska Norway, the second largest construction company in the country. Running along the edge of Larvik town, the road will cross the new 570m long Ferris suspension bridge, which will span the southern end of Ferris Lake.

Two 7659 Volvo Construction Equipment EW230C wheeled excavators have been modified for this project. The machines are working in the Larvik tunnel section. The local dealer, Volvo Maskin is working with 2694 CeDe Group in Malmö, Sweden – an official partner to Volvo to supply special application underground solutions – ensuring the machines were ready for tunneling operation.

These units are equipped with a hydraulic elevating and tilting cab, raising the cab 2.4m with a maximum tilt angle of 30°– a feature allowing operators to get close to where they are working with no natural daylight. Efficient Xenon and customised LED lights aid visibility in the tunnel.

An air compressor unit, activated by the hydraulic breaker is fitted to blow clean air around the breaker, preventing ingress of dust and an upper structure-mounted 50m hose reel feeds through constant water to reduce dust and improve visibility. The water used during operations every day is pumped into large holding tanks situated close to the tunnel exit, where the water is then treated for reuse.
Bolt-on, heavy duty rubber guards protect the boom and dipper cylinders against damage from falling stones. The front screen features 6.8mm thick safety glass with additional certified front screen protection, and the engine compartment is equipped with a fire suppression system and central lubrication for increased safety.

Once a section of tunnel has been blasted, Volvo wheeled loaders form part of a load handling team before a EW230C wheeled excavator equipped with a bucket cleans up. The second machine, equipped with a breaker, will be handling stripping operations at the other end of the tunnel. To ensure operator and equipment safety, rock bolts are inserted at multiple points to secure the roof structure.

A specially equipped Volvo EC250DL is also working in Larvik, drilling the rock face alongside the existing road to prepare for blasting. This is where the road will be lowered to the tunnel exit – a short distance from where the new bridge will be constructed.

Volvo Maskin and CeDe Group modified the EC250DL to feature safety glass for both the front screen and the roof, with an additional roof wiper blade, boom suspension, a swing dampening system, plus additional LED lights. The drilling rig was then mounted by Norwegian company AMV, including the hydraulics and electrics for the motion control.

Traffic flow continues and is only disturbed 2-3 times a day when the rock is blasted. Though small blasts, handling 50-70m2 each time, heavy rubber protective mats are positioned over the rock to safeguard against flying debris.

“The average drill hole is 1.5-2m deep,” said Mads Bakken, equipment manager on site. “This rig can handle around 300m/day.

The attachment can drill to a depth of 10m in automatic mode or even deeper in manual mode. The machine is perfect for the job, offering both high and long reach and we can use it on other projects too.”

The attachment can be rotated through 180 degrees, but versatility is increased with a second coupler bracket mounted to the side of the attachment, enabling both drilling horizontally and vertically when installing rock bolts to stabilise the rock face.

“I like the Volvo,” said Ger Egil, machine operator. “I appreciate the space in the cab and low noise, but I especially like the elevating cab as I can get really close to where I am drilling.” He also explained how the entire operation can be handled via remote control depending on the working conditions.

There are about 20 Volvo units on the site, including EC250, EC380D and E-series excavators, a L110F and L250F, G-series wheel loaders and A35FFS and A40FFS full suspension articulated haulers. The project is scheduled for completion in 2017.

For more information on companies in this article

Related Content

  • Work begins on Stockholm’s new bypass
    August 22, 2016
    The first tunnels are being excavated for the huge bypass tunnel in Sweden’s capital Stockholm – Adrian Greeman writes. After years of preparation and design, blasting and rock moving for Sweden's largest infrastructure project began south of the city this year. It sets in train a decade-long project that will create a new half-ring dual three-lane motorway for the city, 20km long. With most of it deep underground, it will also be one of Europe's largest ever road tunnels. The scheme is aimed at transformin
  • Volvo CE develops efficient new soil compactors
    December 17, 2013
    Volvo CE’s redesigned soil compactors offer improved cab designs and better performance, while the firm is offering other glimpses of future technologies - Nick Johnson reports This summer marked the 55th anniversary of Volvo Days – an event that enables Volvo Construction Equipment customers to find out more about the company’s latest products and services. An impressive machine demonstration at the Volvo Customer Centre in Eskilstuna, Sweden provided the official launch for several new models, including s
  • Higher production from all-wheel-drive haulers
    August 2, 2012
    The improvements to articulated dump trucks (ADTs) have been substantial in recent years. Comparing a present day machine with one from 20 or even just 10 years ago shows how far design has come. Major improvements have been made in visibility, operator comfort levels, rough terrain performance, driveline efficiency and productivity, to name but a few key areas. All of the latest generation ADTs available on the world market now come with Tier 3/Stage IIIA compliant diesels that produce far lower noise and
  • Caterpillar has improved three ADT models
    June 12, 2018
    Caterpillar has redesigned three of its ADT models, the 730, 730 EJ (Ejector), and 735. The firm says that the updates boost the proven features and performance of their C-Series predecessors (730C2, 730C2 EJ, and 735C). Improvements include operator stations with innovative new controls, transmission-protection features, new hoist-assist system, advanced traction control system, new stability-assist system, and a fuel saving ECO operating mode. In addition, the 730 and 730 EJ now have an automatic retarde