Volvo machines help construct new Norwegian tunnels

Close to Larvik in Norway’s Vestfold County and around 80km south of Drammen, two tunnels are currently under construction as part of a state-funded infrastructure development programme. The project, which began earlier this year, comprises 7km of four lane highway – part of the E18 major route – linking the towns of Bommestad and Sky. This includes the new Larvik and Matineå tunnels, which will span 2.8 and 1.3km respectively. Worth €187 million, this project was awarded to Skanska Norway, the second la
January 12, 2015 Read time: 4 mins
Modified Volvo CE equipment is being used on this project
Close to Larvik in Norway’s Vestfold County and around 80km south of Drammen, two tunnels are currently under construction as part of a state-funded infrastructure development programme. The project, which began earlier this year, comprises 7km of four lane highway – part of the E18 major route – linking the towns of Bommestad and Sky. This includes the new Larvik and Matineå tunnels, which will span 2.8 and 1.3km respectively.

Worth €187 million, this project was awarded to 2296 Skanska Norway, the second largest construction company in the country. Running along the edge of Larvik town, the road will cross the new 570m long Ferris suspension bridge, which will span the southern end of Ferris Lake.

Two 7659 Volvo Construction Equipment EW230C wheeled excavators have been modified for this project. The machines are working in the Larvik tunnel section. The local dealer, Volvo Maskin is working with 2694 CeDe Group in Malmö, Sweden – an official partner to Volvo to supply special application underground solutions – ensuring the machines were ready for tunneling operation.

These units are equipped with a hydraulic elevating and tilting cab, raising the cab 2.4m with a maximum tilt angle of 30°– a feature allowing operators to get close to where they are working with no natural daylight. Efficient Xenon and customised LED lights aid visibility in the tunnel.

An air compressor unit, activated by the hydraulic breaker is fitted to blow clean air around the breaker, preventing ingress of dust and an upper structure-mounted 50m hose reel feeds through constant water to reduce dust and improve visibility. The water used during operations every day is pumped into large holding tanks situated close to the tunnel exit, where the water is then treated for reuse.
Bolt-on, heavy duty rubber guards protect the boom and dipper cylinders against damage from falling stones. The front screen features 6.8mm thick safety glass with additional certified front screen protection, and the engine compartment is equipped with a fire suppression system and central lubrication for increased safety.

Once a section of tunnel has been blasted, Volvo wheeled loaders form part of a load handling team before a EW230C wheeled excavator equipped with a bucket cleans up. The second machine, equipped with a breaker, will be handling stripping operations at the other end of the tunnel. To ensure operator and equipment safety, rock bolts are inserted at multiple points to secure the roof structure.

A specially equipped Volvo EC250DL is also working in Larvik, drilling the rock face alongside the existing road to prepare for blasting. This is where the road will be lowered to the tunnel exit – a short distance from where the new bridge will be constructed.

Volvo Maskin and CeDe Group modified the EC250DL to feature safety glass for both the front screen and the roof, with an additional roof wiper blade, boom suspension, a swing dampening system, plus additional LED lights. The drilling rig was then mounted by Norwegian company AMV, including the hydraulics and electrics for the motion control.

Traffic flow continues and is only disturbed 2-3 times a day when the rock is blasted. Though small blasts, handling 50-70m2 each time, heavy rubber protective mats are positioned over the rock to safeguard against flying debris.

“The average drill hole is 1.5-2m deep,” said Mads Bakken, equipment manager on site. “This rig can handle around 300m/day.

The attachment can drill to a depth of 10m in automatic mode or even deeper in manual mode. The machine is perfect for the job, offering both high and long reach and we can use it on other projects too.”

The attachment can be rotated through 180 degrees, but versatility is increased with a second coupler bracket mounted to the side of the attachment, enabling both drilling horizontally and vertically when installing rock bolts to stabilise the rock face.

“I like the Volvo,” said Ger Egil, machine operator. “I appreciate the space in the cab and low noise, but I especially like the elevating cab as I can get really close to where I am drilling.” He also explained how the entire operation can be handled via remote control depending on the working conditions.

There are about 20 Volvo units on the site, including EC250, EC380D and E-series excavators, a L110F and L250F, G-series wheel loaders and A35FFS and A40FFS full suspension articulated haulers. The project is scheduled for completion in 2017.

For more information on companies in this article

Related Content

  • Doosan launches DX190W-3 19-tonne wheeled excavator
    February 20, 2014
    Doosan has launched its new Stage IIIB compliant 19tonne DX190W-3 wheeled excavator. The DX190W-3 is said to offer increased digging power, lifting capacities and faster working cycles with improved fuel efficiency to reduce costs and preserve the environment. With its operating weights varying from 18.4 to 20.3tonnes, the DX190W-3 is powered by the well-proven Stage IIIB compliant Doosan DL06KB 6-cylinder ‘common rail’ diesel engine, fitted with a waste gate turbocharger with intercooler as standard a
  • Tunnels eliminate bottlenecks
    February 10, 2012
    Some of the bottlenecks on the multi-lane Mittlere Ring, Munich, Germany, one of the main arterial roads circling the city centre have been eliminated by the addition of new tunnels. The Luise-Kiesselbach Square, the last section of this road improvement effort, is an important traffic hub south-west of the city where motorways A96 from Lindau and A5 from Garmisch meet, causing long delays in daily rush-hour traffic, writes Patrick Smith.
  • Demonstrating the latest in construction machines
    February 28, 2012
    Sandvik Mining and Construction and Volvo Construction Equipment have jointly held a series of machinery demonstrations and customer events in Sweden.
  • New earthmoving machines
    July 29, 2019
    An array of advanced earthmoving machines are coming to market, offering increased performance, lower fuel consumption and reduced emissions The global market for earthmoving machines has been particularly strong over the last year. Demand for new equipment has been at a high, with sales of crawler excavators proving especially robust. Manufacturers have responded by increasing output, while tempting customers with new models offering major performance gains. Dozers In the market for dozers, Caterp