Volvo machines help construct new Norwegian tunnels

Close to Larvik in Norway’s Vestfold County and around 80km south of Drammen, two tunnels are currently under construction as part of a state-funded infrastructure development programme. The project, which began earlier this year, comprises 7km of four lane highway – part of the E18 major route – linking the towns of Bommestad and Sky. This includes the new Larvik and Matineå tunnels, which will span 2.8 and 1.3km respectively. Worth €187 million, this project was awarded to Skanska Norway, the second la
January 12, 2015 Read time: 4 mins
Modified Volvo CE equipment is being used on this project
Close to Larvik in Norway’s Vestfold County and around 80km south of Drammen, two tunnels are currently under construction as part of a state-funded infrastructure development programme. The project, which began earlier this year, comprises 7km of four lane highway – part of the E18 major route – linking the towns of Bommestad and Sky. This includes the new Larvik and Matineå tunnels, which will span 2.8 and 1.3km respectively.

Worth €187 million, this project was awarded to 2296 Skanska Norway, the second largest construction company in the country. Running along the edge of Larvik town, the road will cross the new 570m long Ferris suspension bridge, which will span the southern end of Ferris Lake.

Two 7659 Volvo Construction Equipment EW230C wheeled excavators have been modified for this project. The machines are working in the Larvik tunnel section. The local dealer, Volvo Maskin is working with 2694 CeDe Group in Malmö, Sweden – an official partner to Volvo to supply special application underground solutions – ensuring the machines were ready for tunneling operation.

These units are equipped with a hydraulic elevating and tilting cab, raising the cab 2.4m with a maximum tilt angle of 30°– a feature allowing operators to get close to where they are working with no natural daylight. Efficient Xenon and customised LED lights aid visibility in the tunnel.

An air compressor unit, activated by the hydraulic breaker is fitted to blow clean air around the breaker, preventing ingress of dust and an upper structure-mounted 50m hose reel feeds through constant water to reduce dust and improve visibility. The water used during operations every day is pumped into large holding tanks situated close to the tunnel exit, where the water is then treated for reuse.
Bolt-on, heavy duty rubber guards protect the boom and dipper cylinders against damage from falling stones. The front screen features 6.8mm thick safety glass with additional certified front screen protection, and the engine compartment is equipped with a fire suppression system and central lubrication for increased safety.

Once a section of tunnel has been blasted, Volvo wheeled loaders form part of a load handling team before a EW230C wheeled excavator equipped with a bucket cleans up. The second machine, equipped with a breaker, will be handling stripping operations at the other end of the tunnel. To ensure operator and equipment safety, rock bolts are inserted at multiple points to secure the roof structure.

A specially equipped Volvo EC250DL is also working in Larvik, drilling the rock face alongside the existing road to prepare for blasting. This is where the road will be lowered to the tunnel exit – a short distance from where the new bridge will be constructed.

Volvo Maskin and CeDe Group modified the EC250DL to feature safety glass for both the front screen and the roof, with an additional roof wiper blade, boom suspension, a swing dampening system, plus additional LED lights. The drilling rig was then mounted by Norwegian company AMV, including the hydraulics and electrics for the motion control.

Traffic flow continues and is only disturbed 2-3 times a day when the rock is blasted. Though small blasts, handling 50-70m2 each time, heavy rubber protective mats are positioned over the rock to safeguard against flying debris.

“The average drill hole is 1.5-2m deep,” said Mads Bakken, equipment manager on site. “This rig can handle around 300m/day.

The attachment can drill to a depth of 10m in automatic mode or even deeper in manual mode. The machine is perfect for the job, offering both high and long reach and we can use it on other projects too.”

The attachment can be rotated through 180 degrees, but versatility is increased with a second coupler bracket mounted to the side of the attachment, enabling both drilling horizontally and vertically when installing rock bolts to stabilise the rock face.

“I like the Volvo,” said Ger Egil, machine operator. “I appreciate the space in the cab and low noise, but I especially like the elevating cab as I can get really close to where I am drilling.” He also explained how the entire operation can be handled via remote control depending on the working conditions.

There are about 20 Volvo units on the site, including EC250, EC380D and E-series excavators, a L110F and L250F, G-series wheel loaders and A35FFS and A40FFS full suspension articulated haulers. The project is scheduled for completion in 2017.

For more information on companies in this article

Related Content

  • Growth in a versatile workforce
    July 19, 2012
    Some of the biggest names in the construction industry have released innovative new utility machines and equipment in the first few months of 2012. Guy Woodford looks at some of the latest models To mark the 25th anniversary of the Bobcat compact excavaor range, the Doosan-owned company recently unveiled a new limited edition version of the Bobcat E16. The special 1.6 tonne model is said by the company to provide an attractive complement to the also new and enhanced versions of both the E16 and 1.4tonne E1
  • Brazil Tamoio highway and São Sebastião tunnel work
    July 5, 2016
    Brazil’s Tamoio Highway and São Sebastião tunnel construction is of major importance – Mauro Nogarin reports. The modernisation and expansion of Brazil’s Tamoio highway is a major project for Brazil. The project has an estimated cost of $1.5 billion and work on the first section from Planalto was completed in January 2014, costing around $350 million. The project is being managed by the state-owned agency DERSA, which deals with road development. According to the concessionaire for the Tamoios highway p
  • Versatile machines offer improved efficiency
    April 28, 2015
    An array of versatile new machines from different segments is available for the rental sector - Mike Woof writes The rental machine market continues to develop in many countries around the world. Equipment rental has a long history in the UK and the US and in more recent years has developed well in France also, while other countries are also benefiting from growth in this sector. As with other machines, equipment for the European and US rental sector now has to meet tough exhaust and noise emissions legi
  • Sandvik’s DT1131i jumbo and iSURE software in Iceland and Norway
    August 14, 2019
    Sandvik’s DT1131i three-boom, electro-hydraulic jumbo, iSURE tunnel management software and the latest drill bit hardware were recently put to the test in Iceland and Norway* Czech contractor Metrostav recently achieved 105m of tunnel excavation in a record-breaking six days. But it will be consistent performance and progress that will see Iceland’s Dyrafjordurgong Tunnel in the remote Westfjords region open on time and on budget. The 5.3km Dyrafjordurgong Tunnel is costing around €69 million and due