Sandvik drilling rigs boost production

The drill and blast contractor Technical Drilling and Blasting in the United Arab Emirates (UAE) is standardising on Sandvik rock tools for its fleet of drill rigs. The firm operates across Fujeirah, providing quality gabbro aggregates for construction projects in Dubai and Abu Dhabi. Recognised as one of the worlds hardest rocks, gabbro features a typical density in excess of 3tonnes/m, a crushing factor of 10 and a 61% silica content and demand remains strong for this quality construction material. Every
July 9, 2012 Read time: 4 mins
Using Sandvik drilling consumables and rigs has helped boost productivity in the UAE
The drill and blast contractor Technical Drilling and Blasting in the United Arab Emirates (UAE) is standardising on 325 Sandvik rock tools for its fleet of drill rigs. The firm operates across Fujeirah, providing quality gabbro aggregates for construction projects in Dubai and Abu Dhabi.

Recognised as one of the worlds hardest rocks, gabbro features a typical density in excess of 3tonnes/m, a crushing factor of 10 and a 61% silica content and demand remains strong for this quality construction material. Every hour of each day, a continuous team of trucks make the journey from the dozens of quarries in the Hajjar Mountains to projects across the UAE.

Despite the global economic slowdown, demand is still strong in the aggregate sector. With blasting strictly regulated across the Emirate, five companies specialise in drill and blast contracting for the quarrying sector. Market leader is Technical Drilling and Blasting, which specialises in quarry activities and handles contracts for around 24 quarries in Fujairah.

Technical manager Bill Armstrong of Technical Drilling and Blasting has a fleet of 16 surface top hammer drills and two DTH rigs, which includes nine Sandvik machines. According to project manager, Alok Ojha, the long life and productivity of its Sandvik rock tools, supplied through local distributor Dynatrade, has been a major benefit. He said, "Initially we used rock tools from the respective rig manufacturer but trials soon found that the Sandvik rock bits and rods were providing 100% longer operational life."

For the drill bits, life expectancy is up to three times longer when using the Sandvik Retrac bits. According to Armstrong the firm is achieving 700-800 drill metres/bit in the hard rock areas and up to 2000 drill metres in softer conditions. To ensure maximum performance the firm carries out bit regrinding after the first 400m with a second regrind after another 200m.

Each blast site is thoroughly surveyed and blasts are planned weeks in advance. UAE police and security witness all blasting operations and monitor the explosives used. However the growth in demand for aggregates has put extra strain on the police forces resources and the firm has been negotiating with the local authorities to make changes to restrictions. Until recently there have been restrictions on the quantities of explosives used and blaster have only been allowed to carry out two blasts/day at each site. However Technical Drilling and Blasting has demonstrated that using a single blast with a much greater quantity of explosive allows the police and other authorities to visit more sites without taking any extra time. And the firm is keen to show that further increases to the quantities of explosives used will make the process even more efficient.

Aggregate supply increase

A new Atlas Copco compressor is helping a Korean contractor meet its need for aggregates to complete construction work on the 75km road linking Nittambuwa and Kandy in Sri Lanka. An 161 Atlas Copco ROC 442 PC drill rig and an XAMS856 air compressor with a free air delivery of 250litre/s at 8.6bar haves proved successful in ensuring Korean contractor Keangnam carry out the Kandy-Nittambuwa road upgrade.

Originally built by 1146 Balfour Beatty 20 years ago, the highway is Sri Lanka's busiest as it links capital Colombo with Kandy. The road carries cars and heavy bus and lorry traffic, causing the surface to become worn and in need of repaving. Keangnam's contract involved laying a new 100-200mm base course (and up to 300mm of base course in some places), with 50mm thick courses over the top. The asphalt is supplied by Keangnam's 104tonnes/hour asphalt plant, which is located alongside its 200tonnes/hour crushing plant and quarry operation at Thulhiriya, some 60km east of Colombo and which opened in 2007. The quarry is one of three operated by Keangnam, maintaining the company's policy to provide asphalt for its highway contracts across Sri Lanka. However, to meet aggregate demand for its 'key' Nittambuwa - Kandy project, the contractor opted for a new atlas Copco XAMS 856 to increase production at Thulhiriya; ordered through local dealer Swedish Trading.

The contractor opted for this unit as it already has a fleet of 10 Atlas Copco compressors in Sri Lanka, mostly XAS186's working on the highway projects. For three quarry operations, Keangnam had relied on the combination of Atlas Copco XAMS405 compressors and ROC442 PC drill rigs.

"Delivery of the latest XAMS856 compressor allowed us to increase production with ease," said plant manager, HLS de Zoysa, confirming that the rock encountered at Thulhiriya was very hard Gneiss with a hardness factor of 19.5.

The latest compressor is generally used for drilling at 6bar, "but," confirmed de Zoysa, "when really hard rock is excavated it can easily provide up to 8.6bar."

Complying with strict blasting controls, the contractor is generally drilling 15 holes x 6m depths for daily blasting using 65mm diameter holes; with holes taking up to 30 minutes to drill.


For more information on companies in this article

Related Content

  • Tunnelling with Atlas Copco's HPT
    February 6, 2012
    Atlas Copco claims that its high precision tunnelling (HPT) system will offer greater productivity and reduced costs in drill and blast tunnelling operations. The HPT system is a package with five options for use on drill rigs and other types of construction equipment. Advanced PC-based software allows a worksite office to provide operational support to Atlas Copco rigs equipped with the Rig Control System (RCS). The Tunnel Manager system can help plan, store and evaluate data for the drilling process. This
  • Okie hammer home advantage with Sandvik RH550
    January 24, 2014
    Although Okie Drilling’s flexibility enables the firm based in Stigler in the US state of Oklahoma to undertake a diverse variety of drilling projects, it core business is drilling for rock quarries and state road projects. According to Okie president Billy White, the cornerstones of Okie’s success in meeting the requirements of these demanding sectors is employees willingness to go the “extra yard” for customers, and the service and products he receives from Sandvik Construction’s Rock Tools & Drilling tea
  • Atlas Copco’s SmartROC D60 gets down for the challenge
    April 4, 2016
    Atlas Copco’s new SmartROC D60, a heavy-duty surface drill rig, is robust enough and smart enough to tackle aggregate and limestone quarrying. SmartROC D60, a highly versatile Down-The-Hole rig is designed for drilling 110-178mm holes. It also has a high level of automation for optimum efficiency and consistent productivity, according to Atlas Copco. The rig’s hole navigation and auto-positioning systems ensure that the rig locates the exact position of each hole and then accurately collars and drill
  • High quality Swedish stone
    April 13, 2012
    Close to Sweden's second largest city Göthenburg lies the efficient Jehander quarrying operation run by Heidelberg Cement. The site produces around 9,000tonnes/day at peak seasonal demand and has an output of some 1,000,000tonnes/year. The site has recently renewed its operating permission and now has the necessary approval to work until 2021. Niklas Osvaldsson is regional manager for Heidelberg Cement and said, "Since early 2000 this has been part of the Heidelberg Group." Stone production originally st