Major new highway for Ecuador’s Piñas canton

Ecuador’s Buenavista – Zaruma Highway will provide a key route that will help boost economic activity – Mauro Nogarin writes Ecuador hopes to boost economic activity with the construction of new highway links. Most economic activity in the Piñas canton currently relies on agriculture, forestry and fishing. These sectors employ over 50% of the economically active population of the region. Meanwhile, most of the working population of the Portovelo canton is dedicated to mining and quarrying, with this area
September 30, 2015 Read time: 5 mins
The topography along the route presents a number of challenges
Ecuador’s Buenavista – Zaruma Highway will provide a key route that will help boost economic activity – Mauro Nogarin writes

Ecuador hopes to boost economic activity with the construction of new highway links. Most economic activity in the Piñas canton currently relies on agriculture, forestry and fishing. These sectors employ over 50% of the economically active population of the region. Meanwhile, most of the working population of the Portovelo canton is dedicated to mining and quarrying, with this area delivering 60% of Ecuador’s extraction industry.

The new road construction project consists of work on three main links, according to the Ministry of Transport and Public Works (MTOP). Section 1 runs from Zaruma – Zaracay, a length of 42.45km, while Section 2 is the 7.8km stretch from Osorio – Portovelo and Section 3 is the 9.15km stretch from Chinchas – Rio Pindo.

Although the climate of the province is conditioned by both the Pacific Ocean and the Andes Mountains, temperatures are very stable throughout the year and there is no difference between the seasons. The annual rainfall is 997.39 mm/year, the average temperature is 24.35°C, and the average humidity is 85.7%. This reduces the number of challenges to the road construction operation.
However the geology and topography faced by the engineers pose more challenges. The route of the road passes through different types of geotechnical areas: colluvial materials, weathered volcanic rock, volcanic rock that is weathered and fractured, alluvial terraces and serpentine rock (El Toro).

One of the geological features that has generated difficulties in designing the road comes from the risk of landslides. This problem is a feature of the entire length of the road, particularly in the area between the Buenaventura Reserve and Piñas; the area of the Monos River; the Moro-Moro area and the Prado area at the entrance to Piñas. In this area landslides are frequent and can cause significant damage to roads. As a result, the design of the road has taken particular consideration of the slopes, with a focus on solutions that can properly drain and stabilise the slopes.

The starting point of the road is located in the town of Zaruma, located at an altitude of 1,100m above sea level and runs to the town of Portovelo located at an elevation of 630m. This stretch of the route features a descent with gradients ranging between 7.5% and 10.7%. This stretch is mostly urban and there are houses on both sides of the current road. Along this stretch there are very small radius curves. Because of the density of the homes in this stretch, it was considered desirable to have an urban-type cross section, consisting of two lanes and sidewalk. The type of terrain in this section is residual and saprolitic rock and residual soil on volcanic rock.
Section 2 from Osorio – Portovelo features a descent and includes a stretch with a gradient of 8.5%. This is an urban area with houses on both sides of the road and housing is most common during the first 2km where it enters the town of Portovelo. In this stretch, some small corrections of curves are being made, but this work is complex and the area is very densely populated and features a number of high buildings. This section features two lanes, two shoulders, side ditches and berms.

Section 3 runs from the bridge for the Union Portovelence and features problems with the road surface in some areas at present. The surface in this last stretch is deficient and this is an issue, particularly due to the high percentage of heavy vehicles serving the extraction industries (40%) located on the left bank of the Rio Amarillo. The typical layout for this section that has been adopted is two lanes, two shoulders, with side ditches and berms. At the end of the third section, there is a single lane bridge crossing the Pindo River.

The longest bridge on the route meanwhile is the 140m structure over the Moro Moro, which has a speed limit of 80km/h. The viaduct passes some 22m above the bottom of the riverbed and descends gradually with a gradient of 1.95%. It has a central height of 30m.

The deck is a post-tensioned concrete slab that measures 1.2m thick and has sloping side walls.

The piles are 3m wide and 1.5m deep, with the alignment of their axes perpendicular to the axis of the board. The head of the piles are widened in the form of a Y so as to better distribute forces from the deck.

The foundation of abutments and piles will be direct, through shoes, following the recommendations of the geotechnical study.


Road characteristics
   
 Length  66.42 km
 Type of Road
 Class III
 Type of terrain
 Mountainous
 Width of Shoulders
 Variable from 0.5-1.5m on each side
 Berm  0.8m on each side
 Maximum incline
 Maximum 11%
 Surface  Asphalt



Bridges and their characteristics
 SECTION  NAME  HEIGHT  WIDTH  TYPE
 1  Rio Calera  152m  11m  Metal beam
 2  Monos River  120m  15m  Concrete
 3  Moro Moro R  140m  12.5m  Concrete
 4  Amarillo R   25m
 11m  Precast concrete
 5  Pindo River  70.5m
 12.5m  Metallic arch



Related Content

  • Doka delivers cantilevering for super-slim piers at Lahntal Bridge
    October 21, 2016
    Doka’s formwork expertise is currently in demand during the construction of one of the busiest motorway viaducts in Germany. The 400m six-lane Lahntal Bridge in Limburg dates from the early 1960s. Every day about 100,000 vehicles cross the bridge that spans the valley of the River Lahn. But traffic loads have increased sharply, so a new bridge is being built sited just a few metres west of the old viaduct. The new Lahntal viaduct will measure a massive 43.5m in width, enabling eight lanes plus hard shoul
  • Rich salt harvest – Wirtgen Surface Mining in Mexico
    November 27, 2014
    Close to Guerrero Negro in the west of Mexico the world's largest salt field is located. There two Wirtgen Surface Miners 2200 SM produce enormous amounts of the "white gold" - economically and in top quality. The company Exportadora del Sal S.A. (ESSA) – a joint venture between the Mexican government and Mitsubishi Corporation – has produced salt on a large scale in the Ojo de Liebre Lagoon since 1957. With a total area of 33,000 ha, this gigantic evaporation pond is now the largest salt works of its kind
  • China on road spending spree
    December 11, 2012
    Figures recently released indicate that construction spending in China will increase 8.8% each year in real terms through to 2016. Ongoing urbanisation and industrialisation; rebounding foreign investment funding; rising personal income levels and further population and household growth will all work to drive gains. However, further growth will be prevented by a slow-down in the Chinese economy through the forecast period, especially in fixed asset investment. These and other trends are presented in Constru
  • Turkey plans major infrastructure improvements
    March 22, 2012
    Turkey recently unveiled ambitious targets towards improving its transportation infrastructure for 2023, the year the country will celebrate its 100th year anniversary as Republic of Turkey. The main means of transportation in Turkey is by highways, and the coach and bus industry has played a crucial role in passenger transportation. The recent increases in the number of airports and charter companies have made travel by plane a potential choice for passengers. However, railways have contributed rather insi