Located in Meeker, Colorado and serving the area for air transportation is Meeker Airport, a C-II general aviation airport. The FAA designation of C-II means the airport can accommodate aircraft with wingspan of less than 24m. Runway 3-21 at the Rio Blanco county-owned Meeker Airport had reached a point of wear and deterioration that required full reconstruction and upgrades to remain compliant with the FAA’s C-II requirements.
August 18, 2014 Read time: 5 mins
Meeker Airport in Colorado now has a new airport runway surface
RSS

Airport construction projects provide paving challenges at jobsites around the world

Located in Meeker, Colorado and serving the area for air transportation is Meeker Airport, a C-II general aviation airport. The FAA designation of C-II means the airport can accommodate aircraft with wingspan of less than 24m.

Runway 3-21 at the Rio Blanco county-owned Meeker Airport had reached a point of wear and deterioration that required full reconstruction and upgrades to remain compliant with the FAA’s C-II requirements. The US$12.5 million project was awarded to local firm Fiore & Sons and was handled in two stages. Construction consisted of the demolition of the existing 18.3m wide by 1.98km long runway and the construction of a new runway to meet C-II runway safety area and longitudinal standards. The new runway was widened to 30.5m but remained 1.98km long. The runway ties into the existing apron connector with a turnaround at the end of the runway.

Fiore & Sons completed the demolition and used milling to remove 35,953m2 of asphalt in preparation for the site conditioning, grading, and paving, which was carried out by local firm United Companies. “We were responsible for base course and paving of the new runway and the overall construction of the large apron and taxiway,” said Jeff Boone, project manager for United Companies. “We needed to complete our portions of the combined projects within the eight-month timeline for the whole project, so our timing was tight.”

United Companies had two major responsibilities in the project: the dirt and stone work to create the sub-base and the finish paving on the runway, apron, and the aircraft turnaround.

After Fiore & Sons completed the demolition of the old runway and moved 784,600m3 to rebuild the runway, United Companies came on site and moved the earth for the large apron and taxiway.  Between the two projects the company placed 63,140tonnes of crushed aggregate base course and  in  150mm lifts with the company’s three 4018 Caterpillar Paving 140H graders equipped with 342 Topcon 3D-MC2 machine control.

“The Topcon system helped us achieve more accurate placement of the base materials at higher speeds and better tolerances,” said Jeff Gross, GPS machine control foreman for United Companies. “With a tight production deadline and stringent FAA requirements, it helped to have the technology.”

As part of the machine control system, the motor graders are equipped with the Topcon GX-60 Control Box that features Windows XP operating system, touch-screen interface, USB file transfer capability, and a colour LCD screen. Additionally, the system includes a GPS antenna, MC-R3 receiver, and the MC² sensor—an inertial sensor which combines gyroscopes and accelerometers to measure the X, Y & Z position as well as the roll, pitch, yaw and acceleration of the grader. The Topcon controlling software is designed to provide position updates up to 100 times/second.   
 
GDA Engineers provided the project control points as well as the points for drainage and utilities for the Meeker Airport project. “A tremendous amount of time and money was saved because we didn’t need to be setting grade stakes,” said Ken Dobey, construction manager for United Companies. “United Companies created the 3D site model which our GPS machine control could use—thus, the job was virtually stakeless.”

Dobey points out that the company has been an early adopter of technology for the past 15 years, with GPS machine control in use for the past four years. “Our business approach is to be at the cutting edge of technology,” Dobey stated. “We’ve found that our investments in technology save us time and resources.”

In keeping with its technology adoption approach, United Companies recently added Topcon Millimeter GPS Asphalt Paver Systems to its three Cat AP-1055D pavers. The Topcon system uses what Topcon refers to as LazerZone technology, which uses GPS positioning together with a zone laser reference provided by a PZL-1A rotating laser, which is said to transmit a signal that creates a measuring area 10m in height.

United Companies consulted with Southwest Positioning, an authorised Topcon dealer, on the technology to acquire. Southwest Positioning installed the asphalt paver system and trained the United Companies machine operators. On the first day of paving, United Companies paved two 183m long test strips measuring 4.88m wide using FAA-specified HMA. Sample cores were taken from the 51mm thick lift to ensure compliance. The paver guided by the Topcon paving control system provided results well within compliance.

To pave the runway, United Companies arranged three PZL-1A rotating lasers spaced 152m apart and then leap-frogged them to maintain continuous production flow.

A 1252 Roadtec SB-2500e material transport vehicle was used to ensure the hot mix asphalt was delivered consistently to the paver at the correct temperature and mix. “We were quite pleased with the results from the Millimeter GPS system,” Gross said. “We completed our work faster than expected and the results were superior, Only 16 out of the 2,500 test shots were out of compliance and none required corrective action.”

In addition to the main runway, United Companies paved a 198m by 97.5m apron and a 366m long by 15.2m wide taxiway. The complete Meeker Airport job required six layers that each needed to be checked for smoothness.

The first layer was a graded dirt layer followed by three 150mm lifts of the P-154 subbase course—which is a gravel that consists of hard durable particles or fragments of granular aggregates. The fifth layer was a 150mm lift of PT-209 base course. And the top layer is two, 51mm lifts of FAA-specified HMA.

“If we had needed to complete all of this work the old way using survey crews and pounding wood, it probably would have
taken us two to three times longer…the technology is that beneficial,” Boone said. Meanwhile the final International Roughness Index of the recently completed Meeker Airport runway surface is well within the FAA specifications.

RSS

For more information on companies in this article

Related Content

  • Asphalt resurfacing at Miami International Airport
    February 8, 2012
    Improvements worth US$30 million are being carried out at Miami International Airport. The work includes runway resurfacing with specialist contractors having been brought in to handle the project. This is a busy facility handling some 34 million passengers/year and the work is being carried out over a period of 454 days in all, starting in September 2009 and due to finish in December 2010. The focus of attention is the upgrade to the airport's second longest runway, 8R 26L as well as the adjoining M and N
  • Machine control technology evolving fast
    February 8, 2012
    The machine control market is evolving fast and is increasingly becoming part of a much wider construction site management concept, Mike Woof reports. Machine control technology has come a long way in the past 20 years and the development of 2D and 3D systems has been rapid in the construction sector.
  • Versatile concrete paving machines
    July 13, 2012
    Concrete paving machines from Guntert & Zimmerman have been carrying out important surface repair jobs around the world. In Belgium a paver from the firm recently completed a high speed road repair, while at Qatar's New Doha International airport one of the firm's S850 units has carried out a major apron paving contract. The new airport is being designed to cope with large passenger aircraft such as the Airbus A380 and the Sinohydro-Gamuda-WCT joint venture was awarded the contract to build two runways, thr
  • GPS machine control technology aids productivity
    February 21, 2012
    GPS technology offers contractors many benefits and product offerings are growing more diverse, Mike Woof reports. The benefit of GPS technology for the construction industry cannot be overstated.