Skip to main content

Smart compaction at Istanbul airport with BOMAG machines

A new airport project is benefiting from some of the latest developments in compaction technology Work started on a new airport for Istanbul in June 2014, with the facility set to be one of the world's largest and to set new standards when it opens for business.
January 6, 2017 Read time: 3 mins
The rollers operate in a line to help deliver efficient compaction

A new airport project is benefiting from some of the latest developments in compaction technology

Work started on a new airport for Istanbul in June 2014, with the facility set to be one of the world's largest and to set new standards when it opens for business.

172 BOMAG has been playing a key role in the construction work at the new site, which is located close to the Black Sea coast.

The construction equipment company has worked closely with the engineering team on site and BOMAG machines are now carrying out the largest compaction operation in the firm’s history, using over 130 single drum rollers on the project.

The columns of the terminal building have already been erected and provide a first impression of the dimensions to be expected at the new Istanbul airport. Upon completion, it will extend to some 8,000ha.

The construction site of the major airport is located about 35km north-west of Istanbul's centre, on the coast of the Black Sea.

The area, which is a former open pit coal mine, features rugged terrain that has to be levelled. To do this requires the removal of 400 million m3 of soil and filling in any holes on the site. About 13,000 personnel are deployed on the construction site and they work seven days/week in two shifts totalling 20 hours/day. Meanwhile BOMAG machines are playing a key role in the work.

At the beginning of 2015, a fleet of no less than 136 BOMAG BW 226 and BW 216 heavy single drum rollers with padfoot and polygonal drums started operating on the construction site. Of these, 61 are equipped with the Bomag Terrameter (BTM) and 45 with the Bomag Compaction Management 05 (BCM 05) with GPS.

To optimise the process for the roller drivers involved, depending on the type of material, a combination of four padfoot and/or polygon soil compactors drive behind each other on a lane. These are followed by a smooth drum roller that finishes and documents the compaction process.

One of the challenges posed is the daily compaction checks required. With around 2 million m2 being compacted/day, roughly 2,500 individual tests would usually be required. However this would be both costly and time-consuming.

Instead, BOMAG's BCM 05 compaction control system and the BOMAG GPS system are providing a cost-efficient alternative.

These packages monitor the surface and collect all the relevant data. This is then transferred to a central laboratory, which compiles and reads it.

An external consultant responsible for approving the tested areas evaluates the resulting single documents, an average of 20/day, and checks the compaction processes. This provides complete documentation for the site and helps deliver greater operating efficiency overall.

The single drum rollers are still hard at work at the airport site, with the targeted opening of the first phase in February 2018.

For more information on companies in this article

Related Content

  • Highway rebuild
    March 21, 2012
    A major contractor In Turkey is using new Dynapac pavers to resurface the busy Istanbul-Ankara highway. Onur Insaat Taahhut bought 12 new Dynapac compactors and pavers at the end of last year and is using two of its new SD135C pavers on the D-100 highway. In all 12 Dynapac asphalt paving machines and vibratory compactors were added to its fleet of equipment, and has put two of the tracked pavers to work on the Ankara to Istanbul link. The machines, four SD135C medium-sized tracked pavers, four CC524HF artic
  • Bulgaria plans for operating road infrastructure
    February 21, 2012
    There is a lot of work to do on Bulgarian roads, but the government has plans to increase the length of highways built each year as Krasimir Krastanov reports. Bulgarian roads with a pavement make up 98.4% of all the country's roads, while 92.5% of them have an asphalt surface and 82.8% of them are able to carry 10tonnes/axle.
  • North African roads
    February 8, 2012
    Morocco has a rapidly expanding road network, which is benefiting from expertise offered by French contractor Colas
  • Black sea countries complete preparations for implementation of Black Sea Ring project
    August 23, 2016
    The Black Sea Ring Road project will improve transport connections for the region - Eugene Gerden writes. Russia has officially started implementation of a project, known as the Black Sea Ring Road, which involves building a four-lane highway system connecting the countries surrounding the Black Sea. The Black Sea Ring Road is a substantial project, a highway measuring some 7,140km in all. Among the countries participating in the project are Turkey, Georgia, Russia, Ukraine, Moldova, Romania, Greece and