Smart compaction at Istanbul airport with BOMAG machines

A new airport project is benefiting from some of the latest developments in compaction technology Work started on a new airport for Istanbul in June 2014, with the facility set to be one of the world's largest and to set new standards when it opens for business.
January 6, 2017 Read time: 3 mins
The rollers operate in a line to help deliver efficient compaction

A new airport project is benefiting from some of the latest developments in compaction technology

Work started on a new airport for Istanbul in June 2014, with the facility set to be one of the world's largest and to set new standards when it opens for business.

172 BOMAG has been playing a key role in the construction work at the new site, which is located close to the Black Sea coast.

The construction equipment company has worked closely with the engineering team on site and BOMAG machines are now carrying out the largest compaction operation in the firm’s history, using over 130 single drum rollers on the project.

The columns of the terminal building have already been erected and provide a first impression of the dimensions to be expected at the new Istanbul airport. Upon completion, it will extend to some 8,000ha.

The construction site of the major airport is located about 35km north-west of Istanbul's centre, on the coast of the Black Sea.

The area, which is a former open pit coal mine, features rugged terrain that has to be levelled. To do this requires the removal of 400 million m3 of soil and filling in any holes on the site. About 13,000 personnel are deployed on the construction site and they work seven days/week in two shifts totalling 20 hours/day. Meanwhile BOMAG machines are playing a key role in the work.

At the beginning of 2015, a fleet of no less than 136 BOMAG BW 226 and BW 216 heavy single drum rollers with padfoot and polygonal drums started operating on the construction site. Of these, 61 are equipped with the Bomag Terrameter (BTM) and 45 with the Bomag Compaction Management 05 (BCM 05) with GPS.

To optimise the process for the roller drivers involved, depending on the type of material, a combination of four padfoot and/or polygon soil compactors drive behind each other on a lane. These are followed by a smooth drum roller that finishes and documents the compaction process.

One of the challenges posed is the daily compaction checks required. With around 2 million m2 being compacted/day, roughly 2,500 individual tests would usually be required. However this would be both costly and time-consuming.

Instead, BOMAG's BCM 05 compaction control system and the BOMAG GPS system are providing a cost-efficient alternative.

These packages monitor the surface and collect all the relevant data. This is then transferred to a central laboratory, which compiles and reads it.

An external consultant responsible for approving the tested areas evaluates the resulting single documents, an average of 20/day, and checks the compaction processes. This provides complete documentation for the site and helps deliver greater operating efficiency overall.

The single drum rollers are still hard at work at the airport site, with the targeted opening of the first phase in February 2018.

For more information on companies in this article

Related Content

  • Morocco’s new motorway links are boosting connectivity
    December 16, 2014
    Morocco’s massive motorway construction programme will improve transport connections and boost this North African country’s economy - Mike Woof reports A massive road building programme is transforming Morocco, with new motorways connecting cities and major towns, as well as many new rural roads being built. The Moroccan Government has set an impressive plan for its infrastructure investment that will see even the country’s small and remote villages having proper connections to the main road network. The
  • Crane assembly for Tibet excavator
    February 9, 2017
    A tough machine assembly operation at extreme altitude has been carried out by two cranes from XCMG The cranes were used to assist in the assembly of a large excavator needed to assist in production at an extraction operation in Tibet. Located at an altitude of no less than 5,400m on the very remote Mila Mountain, the extraction sites was aiming at upgrading its operations and boosting productivity with the addition of a new 100tonne class excavator. The two cranes, an XCT100 model and a QAY300A machi
  • Efficient recycling and soil stabilisation from Wirtgen 
    October 26, 2022
    Wirtgen says that its latest WR recyclers/stabilisers are more efficient due to the development of the new Resource Efficiency System (RES). This increases the degree of automation in the overall process, boosting efficiency.
  • The upcoming bauma 2013 construction equipment show will be the largest ever
    October 16, 2012
    The bauma 2013 construction equipment exhibition in Munich is set to be the largest event in the show’s history. Organised by Messe München, this will be the 30th bauma exhibition in Munich and will run from the 15th-21st April 2013, with the show covering some 570,000m2 and attracting 3,300 exhibitors. Some 450,000 visitors are expected to attend and Dr Wolf-Dietrich Müller, chief representative and senior executive officers of capital goods shows for the Messe München said, “We are able to increase our ca