Smart compaction at Istanbul airport with BOMAG machines

A new airport project is benefiting from some of the latest developments in compaction technology Work started on a new airport for Istanbul in June 2014, with the facility set to be one of the world's largest and to set new standards when it opens for business.
January 6, 2017 Read time: 3 mins
The rollers operate in a line to help deliver efficient compaction

A new airport project is benefiting from some of the latest developments in compaction technology

Work started on a new airport for Istanbul in June 2014, with the facility set to be one of the world's largest and to set new standards when it opens for business.

172 BOMAG has been playing a key role in the construction work at the new site, which is located close to the Black Sea coast.

The construction equipment company has worked closely with the engineering team on site and BOMAG machines are now carrying out the largest compaction operation in the firm’s history, using over 130 single drum rollers on the project.

The columns of the terminal building have already been erected and provide a first impression of the dimensions to be expected at the new Istanbul airport. Upon completion, it will extend to some 8,000ha.

The construction site of the major airport is located about 35km north-west of Istanbul's centre, on the coast of the Black Sea.

The area, which is a former open pit coal mine, features rugged terrain that has to be levelled. To do this requires the removal of 400 million m3 of soil and filling in any holes on the site. About 13,000 personnel are deployed on the construction site and they work seven days/week in two shifts totalling 20 hours/day. Meanwhile BOMAG machines are playing a key role in the work.

At the beginning of 2015, a fleet of no less than 136 BOMAG BW 226 and BW 216 heavy single drum rollers with padfoot and polygonal drums started operating on the construction site. Of these, 61 are equipped with the Bomag Terrameter (BTM) and 45 with the Bomag Compaction Management 05 (BCM 05) with GPS.

To optimise the process for the roller drivers involved, depending on the type of material, a combination of four padfoot and/or polygon soil compactors drive behind each other on a lane. These are followed by a smooth drum roller that finishes and documents the compaction process.

One of the challenges posed is the daily compaction checks required. With around 2 million m2 being compacted/day, roughly 2,500 individual tests would usually be required. However this would be both costly and time-consuming.

Instead, BOMAG's BCM 05 compaction control system and the BOMAG GPS system are providing a cost-efficient alternative.

These packages monitor the surface and collect all the relevant data. This is then transferred to a central laboratory, which compiles and reads it.

An external consultant responsible for approving the tested areas evaluates the resulting single documents, an average of 20/day, and checks the compaction processes. This provides complete documentation for the site and helps deliver greater operating efficiency overall.

The single drum rollers are still hard at work at the airport site, with the targeted opening of the first phase in February 2018.

For more information on companies in this article

Related Content

  • Repaving an F1 racing circuit
    January 20, 2025
    The refurbishment of the Shanghai International Formula 1 was completed recently with great success. As an important milestone in the construction of racing facilities and modern high-grade roads in China, the project has attracted attention both inside and outside the industry.
  • Desert quarry supplies major road projects
    February 10, 2012
    Egyptian contractor Orascom has set up a new quarry site in the country's desert area, close to the city of Assuit. The quarry was opened specifically to supply Orascom's major road construction projects in this area of Egypt, with high quality aggregates.
  • New methods allow concrete testing on the spot
    July 20, 2015
    This month we look at two new methods which are allowing concrete to be tested on the spot, and [over the page] we catch up on the latest news from concrete testing equipment suppliers - Kristina Smith writes Sometimes test results can be very bad news. If the concrete pavement or bridge abutment has already been poured, and if the concrete does not meet the specification, the outcome could be very expensive remedial work.
  • Improving compact equipment efficiency with machine control
    February 6, 2023
    Leica Geosystems is now offering its Leica iCON site excavator package for use on compact excavators. The firm says that this machine control solution allows compact excavators to carry out designs easily and accurately.