Sidewinder UK has been using its novel road widener machines on a series of paving jobs, including smart motorway projects. Sidewinder UK has carried out work on the M6 smart motorway contract between junction 16 and junction 19. The company used one of its road wideners to place and grade the final layer of sub-base to the balanced central reservation in readiness for Tarmac Contracting to pave the base and binder courses. An estimated 5,000tonnes of sub-base was used in the initial 6.4km x 4.7m wide st
December 13, 2018 Read time: 3 mins
8889 Sidewinder UK has been using its novel road widener machines on a series of paving jobs, including smart motorway projects. Sidewinder UK has carried out work on the M6 smart motorway contract between junction 16 and junction 19. The company used one of its road wideners to place and grade the final layer of sub-base to the balanced central reservation in readiness for Tarmac Contracting to pave the base and binder courses.


An estimated 5,000tonnes of sub-base was used in the initial 6.4km x 4.7m wide stretch of central reservation. This required the balanced central reservation to be paved in two halves projecting each carriageway crossfall approximately 2.5% to a centre crown. 2399 Tarmac then paved approximately 240mm of base and binder courses, on top of which the concrete barrier was installed.

The 6.4km section of central reservation was one component of the work to upgrade the M6 to smart motorway status between junction 14 and junction 20. The previous phase of the work from junction 19 to junction 20 was managed by 1146 Balfour Beatty, for which Sidewinder UK also laid the sub-base to a similar design for GPL Group and paved the Permaflow concrete for Roocroft Road Restraint Systems.

The company has carried out work for other projects in the UK using its road widener. This includes work on the M20 between junction 10 and junction 8 for Balfour Beatty which is to implement the new Rack and Stack system for the tunnel. For night working on the M180, the machine was used to lay 340tonnes of 14mm SMA along a 1.3m width. And one Sidewinder was recently commissioned by Toppersfield and Carney Construction via Hoctief UK to work on the Shinfield bypass near Reading. The work required the firm to place sub-base 150mm thick, followed by binder and wearing course to a width of 2.5m.

In a move to broaden its operating base, the firm has been opening new depots in the North, South and West of the UK enabling it to provide a better service and reduce mobilisation costs. The company has also expanded its equipment fleet and the five machines now include the smaller 7tonne OP2500, the 9tonne OP3000 and the 16tonne OP4000, which offer paving widths from 2.5-4m wide. Ongoing developments have recently included the addition of screed augers to improve material flow across the width of the screed and vibration to benefit compaction.

For more information on companies in this article

Related Content

  • Istanbul’s new airport benefits from Wirtgen Group machines
    November 22, 2017
    Construction of Istanbul’s new airport facility is benefiting from the use of a large fleet of machines from the Wirtgen Group. When it is complete, this will be the world’s largest airport and will be able to handle 150-200 million passengers/year as well as 6 million tonnes of freight/year. This will make the facility substantially larger than the world’s current largest airport, the Hartsfield-Jackson Atlanta International Airport, which handles around 105 million passengers/year.
  • Asphalt paving developments
    March 13, 2012
    US and European asphalt paving needs are different, but some firms are bridging that gap, reports Mike Woof. With a clear differentiation between the US and European asphalt paving markets, manufacturers from the latter are now developing machines aimed at the former. The US and European markets for paving machines have developed along very different lines. North American pavers are designed for high throughputs and high paving rates, having been designed to meet a need to build roads over long distances wi
  • Three Pavers for German Bypass Works
    July 20, 2012
    Contractor Matthäi used machine technology from Vögele to place surface course on the new stretch of the B 442 Federal road near Eimbeckhausen in Lower Saxony, Germany. After two years of construction, the residents of Eimbeckhausen are finally rid of the barrage of traffic that had rushed through their small village near Hanover on the B 442 Federal road for decades. Towards the end, almost 14,000 vehicles had been counted per day, 15 – 19% of which were HGVs. All vehicles are now diverted along the four k