Sidewinder UK has been using its novel road widener machines on a series of paving jobs, including smart motorway projects. Sidewinder UK has carried out work on the M6 smart motorway contract between junction 16 and junction 19. The company used one of its road wideners to place and grade the final layer of sub-base to the balanced central reservation in readiness for Tarmac Contracting to pave the base and binder courses. An estimated 5,000tonnes of sub-base was used in the initial 6.4km x 4.7m wide st
December 13, 2018 Read time: 3 mins
8889 Sidewinder UK has been using its novel road widener machines on a series of paving jobs, including smart motorway projects. Sidewinder UK has carried out work on the M6 smart motorway contract between junction 16 and junction 19. The company used one of its road wideners to place and grade the final layer of sub-base to the balanced central reservation in readiness for Tarmac Contracting to pave the base and binder courses.


An estimated 5,000tonnes of sub-base was used in the initial 6.4km x 4.7m wide stretch of central reservation. This required the balanced central reservation to be paved in two halves projecting each carriageway crossfall approximately 2.5% to a centre crown. 2399 Tarmac then paved approximately 240mm of base and binder courses, on top of which the concrete barrier was installed.

The 6.4km section of central reservation was one component of the work to upgrade the M6 to smart motorway status between junction 14 and junction 20. The previous phase of the work from junction 19 to junction 20 was managed by 1146 Balfour Beatty, for which Sidewinder UK also laid the sub-base to a similar design for GPL Group and paved the Permaflow concrete for Roocroft Road Restraint Systems.

The company has carried out work for other projects in the UK using its road widener. This includes work on the M20 between junction 10 and junction 8 for Balfour Beatty which is to implement the new Rack and Stack system for the tunnel. For night working on the M180, the machine was used to lay 340tonnes of 14mm SMA along a 1.3m width. And one Sidewinder was recently commissioned by Toppersfield and Carney Construction via Hoctief UK to work on the Shinfield bypass near Reading. The work required the firm to place sub-base 150mm thick, followed by binder and wearing course to a width of 2.5m.

In a move to broaden its operating base, the firm has been opening new depots in the North, South and West of the UK enabling it to provide a better service and reduce mobilisation costs. The company has also expanded its equipment fleet and the five machines now include the smaller 7tonne OP2500, the 9tonne OP3000 and the 16tonne OP4000, which offer paving widths from 2.5-4m wide. Ongoing developments have recently included the addition of screed augers to improve material flow across the width of the screed and vibration to benefit compaction.

For more information on companies in this article

Related Content

  • Cold road reclamation in South Africa
    July 18, 2012
    Raubex Construction’s new Cat RM500 rotary mixer is proving its worth on a road reclamation work on a South African highway Part of an extensive motorway network some 185km long, South Africa’s ongoing Gauteng Freeway Improvement Project (GIFP) is creating a modern, world-class toll route system. The new road will provide major impetus to socio-economic growth in the country’s most populous and commercially active region. Being built in stages by the South African National Roads Authority (SANRAL), these r
  • New safer road workzone practices
    September 15, 2014
    In the UK, the construction business Connect Plus Services is implementing new practices that reduce the need for crossings of live carriageways. These practices are expected to save the lives of road construction workers. Connect Plus Services is the company that has the contract to maintain, operate and upgrade the M25 motorway around London over a 30-year period. The contract is carried out on behalf of the Highways Agency. The firm has developed a new method of managing traffic approaching road construc
  • High production paving
    February 28, 2012
    In Germany a high production paving operation has been achieved using the largest machine available on the market. This project is all the more notable as the operation has been carried out in a continuous process, without joints. The Vögele SUPER 3000-2 paver was able to advance continuously at a rate of almost 4m/min. The machine was preceded by a bustle of activity, for no fewer than 24 feed lorries were needed to ensure an uninterrupted supply of mix to the paver, which placed an even asphalt surfacing
  • Dual layer, hot to hot paving at German airport
    August 18, 2015
    An airport in Germany has seen the use of very innovative asphalt paving techniques, with the use of dual-layer, hot-to-hot working. The method was used to meet a very tight schedule for the runway rebuilding work, while also delivering the high quality required. Two InLine Pave trains from Vögele were used at Rostock-Laage Airport to lay a new surface and binder course. The operation was innovative as the process used both hot-to-hot, echelon paving as well as dual layer, hot-on-hot working. Using this