The side effect – paving with a road widener

Sidewinder UK has been using its novel road widener machines on a series of paving jobs, including smart motorway projects. Sidewinder UK has carried out work on the M6 smart motorway contract between junction 16 and junction 19. The company used one of its road wideners to place and grade the final layer of sub-base to the balanced central reservation in readiness for Tarmac Contracting to pave the base and binder courses. An estimated 5,000tonnes of sub-base was used in the initial 6.4km x 4.7m wide st
December 13, 2018 Read time: 3 mins
8889 Sidewinder UK has been using its novel road widener machines on a series of paving jobs, including smart motorway projects. Sidewinder UK has carried out work on the M6 smart motorway contract between junction 16 and junction 19. The company used one of its road wideners to place and grade the final layer of sub-base to the balanced central reservation in readiness for Tarmac Contracting to pave the base and binder courses.


An estimated 5,000tonnes of sub-base was used in the initial 6.4km x 4.7m wide stretch of central reservation. This required the balanced central reservation to be paved in two halves projecting each carriageway crossfall approximately 2.5% to a centre crown. 2399 Tarmac then paved approximately 240mm of base and binder courses, on top of which the concrete barrier was installed.

The 6.4km section of central reservation was one component of the work to upgrade the M6 to smart motorway status between junction 14 and junction 20. The previous phase of the work from junction 19 to junction 20 was managed by 1146 Balfour Beatty, for which Sidewinder UK also laid the sub-base to a similar design for GPL Group and paved the Permaflow concrete for Roocroft Road Restraint Systems.

The company has carried out work for other projects in the UK using its road widener. This includes work on the M20 between junction 10 and junction 8 for Balfour Beatty which is to implement the new Rack and Stack system for the tunnel. For night working on the M180, the machine was used to lay 340tonnes of 14mm SMA along a 1.3m width. And one Sidewinder was recently commissioned by Toppersfield and Carney Construction via Hoctief UK to work on the Shinfield bypass near Reading. The work required the firm to place sub-base 150mm thick, followed by binder and wearing course to a width of 2.5m.

In a move to broaden its operating base, the firm has been opening new depots in the North, South and West of the UK enabling it to provide a better service and reduce mobilisation costs. The company has also expanded its equipment fleet and the five machines now include the smaller 7tonne OP2500, the 9tonne OP3000 and the 16tonne OP4000, which offer paving widths from 2.5-4m wide. Ongoing developments have recently included the addition of screed augers to improve material flow across the width of the screed and vibration to benefit compaction.

For more information on companies in this article

Related Content

  • Tunisia road rebuild with BOMAG machines
    October 29, 2018
    Machines from BOMAG have played an important role in the rebuilding of an important road link in Tunisia
  • UK motorway upgrade ahead of schedule
    May 1, 2014
    Joint venture contractor Skanska Balfour Beatty has completed work on a 19km section of the M25 motorway in the UK, six months ahead of schedule. Work on the M25 scheme between junctions 5 and 7 in Kent and Surrey forms part of a new generation of technology-driven improvements on the UK’s strategic road network.
  • Asphalt paving advances available
    June 24, 2024
    Several of the key manufacturers are introducing new developments for the US asphalt paving market with vibration only screeds – Mike Woof writes
  • Highways England awards €2.1 billion of upgrades for UK motorways
    August 7, 2015
    Highways England has today appointed six joint-venture companies to design and build 10 “smart motorways” as part of a €2.1 billion investment. Construction contractors appointed are the Balfour Beatty and VINCI joint venture, a Costain and Galliford Try joint venture, as well as a Carillion and Kier joint venture. Designers are a CHM2 and Hyder joint venture, an Amey and Arup joint venture, as well as a Jacobs and Atkins joint venture. The award is the second major procurement to be given under th